CHANGE ORDER
Project: WWTP Expansion Final Clarifier Owner: City Of Carmel. Indiana
Contract 79 Change Order No. 1
c` ne
beQI
Contractor: M.K. Betts
Contract Date: 3-06-13
The CONTRACTOR is directed to make the following changes in the Contract Documents as set forth in this
Change Order and attachments:
Description of Change:
1) The Installation of(12) 12" and (2) 18" PEF style plug valves in lieu of PEC style valves. Total cost for
this item $1,500.00. FD#1
2) Contractor to change the grade on the vactor dumping station slab to allow the placement of the
dumpster on a flat surface. Total cost for this Item $1,475.00 FD#2
3) The removal of buried concrete, from the site, impeding the installation of the 6" watennain. Total cost
for this Item $3,598.50 FD#3
4) Due to poor soils, over excavation at the footer for the vactor receiving station. Total cost for this Item
$3,375.00 FD#6
5) The installation of control logics plc in lieu of the slc5/05. Total cost for this Item $12,287.00 FD#7
6) The installation of asphalt wedge in the NE parking lot. Total cost for this Item $2,156.00 FD #8
7) The deletion of reinstalling heater AHU-I in the GBT building. Total deduct for this Item ($2,150.00)
8) The use of Zinc Bolts in place of Stainless Steel as embeds on the center column. Total deduct for this
Item ($1,223.00)
9) The deletion of the Aluminum cover for the supernate tank. Total deduct for this Item ($98,860.00)
This Change results in the following adjustment of Contract Price and Contract Time:
Original Contract Price: $3.423.000.00 Original Contract Time: 300 Days
Contract Price Prior to Net (Increase) Resulting
this C.O: $3.423,000.00 from this C.O.: 146 Days
Net Decrease resulting Current Contract Time
From this C.O: ($77,841.50) including this C.O.: 446 Days
Current Contract Price
Including this C.O.: $3345.158.50
Continued
-I
Recommended By: Approved By:
Engineer: Contractor:
Jones & Henry Engineers, Ltd. M.K. it Engineering & Contracting,Inc
/
AP Air
-01 t QZ La �D. Montgomery, Projev Manager
Namc and Title J Name and Title
Date: f- Z—/t/ Date: 01/22/14
Approved By
Owner:
City of Carmel, Indiana
Board of Public Works
By: 1w1l - �ty FV
ea @nf
By. �a .
tuUu:. Qnn 60_d---e. , JY\c-uv.ber-
By j 1
I✓(--elf., J i tijej5O--., - Ev...L "".U-4,--
Date: 41q/if
CITY OF CARMEL, INDIANA
BY ITS BOARD OF PUBLIC WORKS
AND SAFETY
James Brainard, Presiding Officer
Date:
Mary Ann Burke, Member
Date:
Lori Watson, Member
Date:
ATTEST:
Diana L. Cordray, IAMC Clerk-Treasurer
STATE OF INDIANA )
SS:
COUNTY OF )
Before me, a Notary Public in and for said County and State, personally appeared James
Brainard, Mary Ann Burke, and Lori Watson, by me known to be the Members of the City of
Carmel Board of Public Works and Safety, and Diana L. Cordray, Clerk-Treasure of the City of
Carmel, who acknowledged the execution of the foregoing `Agreement" on behalf of the City of
Carmel, Indiana.
Witness my hand and Notarial Seal this day of , 2014.
NOTARY PUBLIC
My Commission Expires: Printed Name
My County of Residence:
Date:
Jones & Henry Engineers, Ltd.
City of Carmel
Waste Water Treatment Plant Expansion
Final Clarifier Improvements
Contract 79
Field directive fd#1
Date: Tuesday, April 2, 2013
Issued By Tom Schreiber, Resident Engineer
City Approved: Ed Wolf
Contractor: M.K. Betts
E,•`` ,Contractor.to perform following work
Contractor to provide (12) 12" and (2) 18" PEF style plug valves in lieu of the specified
PEC style valves.Work will result in change to contract price of$1,500.00. Work will not
result in a change to contract time.
,, ^°�3.,srixin stwae^av •"zs;Tom Schreiber
All work described above must be completed in accordance with'' - .i
specification"s unless;explicitly, noted
- - - Page No UI Pag°s
11 M. K. BETTS ENGINEERING & CONTRACTING, INC.
PG BOX-2533' III
ANDERSON INDIANA 46018
�� (765) 649 1294 FAX (765) 649-2140 'I�
I �I
City of C rmel II.O v I
April I, 2013 iI
One Civic S uare
�I 9 _ jCarmel WIdTP - Contract 79
-14 Carmel,:TN 46032 --Carnal, IN 11
2 F �fl` E P1.1
I� JuneG fi_llelr}' Eag r,neers,Ltd.. _ I Attn: Tom Schreiber _ jl
I i I
to change the 12' and larger plug valves .from the specified EEC iI
style to, PEI' style (1007 Port). This would include twelve;(12) 12' valves and two (2) IHl' II
valves: � .
?6 Total Price $1,500.00
Ii
�I +c
II
I ,
•
II
1I �[lr'3) pest her bv'o'on , n maranal arid:not, complete In'acoo dance Min above specdmailons toe sum of Il•II
r F�, er,o s oc=, >Ia� - -- _ dollars fb )
• al r1 w I�
M a n
II: I t h e c n n
O z m e o - s ,I s p nP a,be 30 tlays�
arrrfft iler1 iii rn}cur, I - —
peel
o.� a"� , •I I ,. :y � c III Uc�1
Jones & Henry Engineers, Ltd.
City of Carmel
Waste Water Treatment Plant Expansion
Final Clarifier Improvements
Contract 79
Field directive fd#2
Date: Wednesday, July 31, 2W3
Issued By: Tom Schreiber, Resident Engineer
City Approved: Ed Wolf
Contractor: M.K. Betts
y a A�,fi s� v ua a � r _ t yd:�x i @y,F4
;4 .,„ , „,. ,k , , �,.,Contractor,to perform following work .<< �, ,,, „,r ,_t„
Contractor to make changes to the vactor dumping station to allow dumpster placement
on a flat surface. Work will result in a change to contract price of$1,475.00 Work will
not result in a change to contract time.
ronsm,, nsammaTom
Schreiber
All work described above,must be completed1n accordance
pecfications.,unle s,
sexplicitly,noted, t _„ w,
.(32;rt,
Jones & Henry Engineers, Ltd.
City of Carmel
Waste Water Treatment Plant Expansion
Final Clarifier Improvements
Contract 79
Field directive fd#3
Date: Wednesday, July 31, 2013
Issued By: Tom Schreiber, Resident Engineer
City Approved: Ed Wolf
Contractor: M.K. Betts
t ` `, ' ' ;' y,Cont--ctor tq perform following work „„ , , ,,,,t t„,vt,,. , ;
Contractor to provide all labour and material to remove, from the site, the buried concrete
in route for the 6" watermain on the North side of the Headworks building . Work will
result in a change to contract price on a time and material basis, which contractor will
submit for review once work is completed.
•, gym, a � . . Tom Schreiber
All YacAll=workidetcribethabovemust be complete thin accordancwwithArx
-„ if . R; .- specifications unless eXpllcitiy;noted a , ,
l
Jones & Henry Engineers, Ltd.
City of Carmel
Waste Water Treatment Plant Expansion
Final Clarifier Improvements
Contract 79
Field directive fd#4
Date: Wednesday, July 31, 2013
Issued By: Tom Schreiber, Resident Engineer
City Approved: Ed Wolf
Contractor: M.K. Betts
.,# d t 4 fir. ._ �a , Rr a ,, to { i r '.:4 li 3
at?t , ,: 0 ttfc a,:,Contractorto perforTIINIIowing Work.,;;, ,k .,,,,; tc ts,,.
Contractor to provide all labour and material to repair HDPE pipe encountered during
excavating for Watermain installation. Work will result in a change to contract price on a
time and material basis, which contractor will submit to Engineer for review once work is
completed.
e . tacsa.,: ntr a::w ;,nsmTom Schreiber
'R y t M 4 r. F f 'N.. "Y, i
.-sue K .r,lil 3t--5, ' ., k .._sn-a , sr i .. , a,t r.Yt
- , All work described above must be completed in accordance with ,-
x,r„x „ ,., . d- specifications unless explicitly noted - , , ,x r.
C
Jones & Henry Engineers, Ltd.
City of Carmel
Waste Water Treatment Plant Expansion
Final Clarifier Improvements
Contract 79
Field directive fd#5
Date: Wednesday, July 31, 2013
Issued By: Tom Schreiber, Resident Engineer
City Approved: Ed Wolf
Contractor: M.K. Betts
. r��s,} , ,Contractortq perform foilowmg
Contractor to provide all labour and material to adjust footing details on the vactor
receiving station ramp to avoid HDPE Pipe. Work will result in a change to contract price
on a time and material basis, which contractor will submit to Engineer for review once
work is completed.
s .n uaxac,A„ nTom Schreiber
All work described above must be completedrm accordance with'
-- -=specifications unlessez licit) 'notes!
p p Y
Jones & Henry Engineers, Ltd.
City of Cannel
Waste Water Treatment Plant Expansion
Final Clarifier Improvements
Contract 79
Field directive fd#6
Date: Wednesday, July 31, 2013
Issued By: Tom Schreiber, Resident Engineer
City Approved: Ed Wolf
Contractor: M.K. Betts
x7 E, t ,iN -zrt, t n ^e1�f t rG
Contractor to perform following work „ , ,i f ., ' ,t
Contractor to provide all labour and material to over excavate in some areas for the footer
on the vactor dumping station due to poor soils. Work will result in a change to contract
price on a time and material basis, which contractor will submit to Engineer for review
once work is completed.
rie
Schreiber
All work de&cubed above must be completedxm?:accordance with
. x ,' specificatior9s.unless ezplictly,ri'oted " '
Rth
Jones & Henry Engineers, Ltd.
City of Carmel
Waste Water Treatment Plant Expansion
Final Clarifier Improvements
Contract 79
Field directive fd#7
Date: Thursday,August 22, 2013
Issued By: Tom Schreiber, Resident Engineer
City Approved: Ed Wolf
Contractor: M.K. Betts
;. Contractor.to perform;following work _ _,
Contractor to provide all labour and material to provide a control logics plc instead of a
slc5/05 plc in the control panel for the new GBT. Work will result in a change to contract
price of$12,287.00.
srtgla
Schreiber
•
All work described`abovemust be completed m accordance,with
, _,,` i5 ;s PPP ifications unless:`explicitly,noted
August 13 2013 C ptiCf�.AG
Alfa Laval Inc
• M.K. Betts Engineering & Contracting, Inc. 11600 East Hardy Road
Attn: Dave Grimes TX 77093-1098
• . USA
Tel +1 800-362-9041
RE: PO 13-124.07 Fax +1281-44911324
•Carmel, IN VWVfP —GBT Control Panel PLC www aif28 -4 9
Alfa Laval Ashbrook Simon-Hartley, Inc. SO-80649: www as-ri com
Dear Mr Grimes—
Alfa Laval Ashbrook Simon Hartley, Inc. ("Alfa Laval") has reviewed the GBT control panel review
comments dated 5/29/13 for the above mentioned project and would like to bring.to your attention
two comments from the review in regard to products being supplied:
• Alfa Laval will provide the PanelView Plus 6 OIT screen as requested in lieu of the PanelView
+ 1000 as shown.in the'submittal as we have confirmed the +1000 is in fact discontinued
• Alfa Laval included the Allen Bradley SLC 5/05 PLC processor per our proposal, for use in
the GBT control panelras iris the same model currently being used with the GBT equipment
• on-site It has been brought to our attention that the ControlLogix PLC is<being requested
due to its listing in specification 16905, however, it was our understanding that this section
described the main control panel in •the plant, and not our GBT control panel. The GBT
specification section 11850 does not reference any other sections and also does not specify:a
particular model of PLC in our specific control panel section, therefore we priced a control
panel equivalent to what is currently in use
Alfa Laval kindly requests a change order in the amount of$11,170.00..in order to upgrade to the••ControlLogix PLC model •
1756-L71 •(this •model is proposed in lieu of the model in 16905, 1756 L63,••
as it is equivalent and newer, therefore will be supported longer). This change request is at cost, but •
we would like to point out that it does include additional engineering and programming costs from the
panel supplier to accommodate the change in processor.
=1
Please advise as to how we should proceed. Alfa Laval will need to receive a change order prior to'
revising the submittal.documents and proceeding with fabrication of the GBT panels if we are to go.;
• with the ControlLogix•PLC model 1756 L71.
• Should you have any questions, please feel free to contact me on my direct line at 281/389-6699.••Thank you,.
Ryart Gift
Project Manager
• cc BL Anderson RickKocerha s¢v_eri,°r3e±em1,,
Jones & Henry Engineers, Ltd.
City of Carmel
Waste Water Treatment Plant Expansion
Final Clarifier Improvements
Contract 79
Field directive fd#8
Date: Tuesday,November 19, 2013
Issued By: Tom Schreiber, Resident Engineer
City Approved: Ed Wolf
Contractor: MK Betts
u v u o
R:;- ; `i ,,4_ R Contractor to perform folloWmg work . ,y
Contractor to provide all labour and material to provide an asphalt wedge as shown on
the attached. Work will result in a change to contract price of$2,156.00
s:3 >ravnIr. ■,Tom Schreiber
v. kill*; t tl r,t ,.,r* ✓^.*t a ae?§ Nt x_, AN °V-b?N IR _ s_l l}
All work described above must be completead in accordance with
, i ; specification's unless explicitly;noteed =`; " ..r.
�,. +
OBSTACLE': Call
FJ.
i
//
'-r 1 v 1 a r.fd0 1
i�J ( it ' Ti L.kra+ L
//% 1 In e �\ A Nee" ..
p I C�(l lth t}
(1 I t;� kct d t ... .
it
. ` m
�yy� G7d�
Ryt Y"IJxI y151 `YJj 13 5 /,/'
_I th,Al'6'Lf 'i J}'�a. t „.„. 1,...S., r �� GI _ !
} .• Y1 rnr x
pp _J,u -
�• f.; J f , y ; iLL J 4.
t 119 Y7FA '� `l !arK ( Y".. [.:
i • d(f J
�
T
f^�
l t �� J FASG i r' � 3 .}
_ . f 1
j J n ss���� J
_,t
i
3' rJ.ty. J.
ql
f
t` ' S
� " {
ci
\\ e'-r- ; r ice" r."41.oz;7.0 fa''u
j 4.\ t , . -s. t-i
I r • , i 7aTifTf5C?ED! o _ I• 1 9jfILC1NG
1y
I- -� } > �.�
\-
�" a' - sFi?lll: f t
\ >
C_79 ,J aj t -
}
i yJ ,■
_rcoJ
1 f 1 l N' Red r ! r s f 1 ( -� ti a S Teti +'f 4 R 1 ' _ .,a t'` S`Ci? i 1 t y L PRf�,uR1
y ^Kass R. PP„,-..? s^t y ` .�'CC; \ J
it u It
'. \` \ , fi"`+;4 PRIMARI.
Grady Brothers, Inc.
Time and Materials
Customer Name: MK Betts
Work Performed: Wedging at truck dumping station.
EQUIPMENT I LABOR
Straight Time Overtime Total($)
Description Rate/Hour Hours Total($) . Rate Hours Rate Hours
Asphalt Paver $ 103.00- 2.00 $ 206.00: Laborer $48.06 6:00 $ 288:38
Distributor $ - Operator `$64 11 4.00 , $ 256.45
Backhoe $ - Teamster. .$54.84. $ -
Widener $ Foreman -$65.13 - 2.00 . - $ .. 130.25
Bulldozer $. }Supervisor $80.00 2.00 $ 16000 Small Scraper $.. - I Materials
Large Scraper . $ Type Qty unit Price Total($) _.
Grader $ - HAG Base Tons. $. _
Track Loader . . $ RAC Binder Tons $ -
Rubber Tire Loader $ HAC Surface . ..30.00 Tons . $$000 $ .1,50&00!
heel Tractor $ - .AE-T 5.00 Gallons. $ 2.65. $ 13.25
Rollers $ - ,Stone Tons , $
ibratory Roller $ 67:00 2!00 $ 134.00 Cold Mix $ -
Wirtgen Wiling Machine $ -. LEASED.TRUCKS I,
Lowboy Truck $ - Description 1 Qb Una Price Total
,S/A Truck $ - Tri-axleTmck 1.5IHours I $87.15 $ 13073:
Tandem Truck $ -. SUBCONTRACTORS
Tn-Axle Truck $ Description Total($)
Broom $
New Holland $ -
Hand:Compactor . $ -.
Equipment $ 340.00
Labor $ 835.08
Materials $ 1,513.25 Owners Authorized Representative
Leased Trucks $ 130.73
'Subcontractors $ By:
Tax-Materials
Mark Up. 10.00% $ 281.91
Total $ '3,100.96I Name - Title
L, 13 al �, ,_- 5Yu /
�, Z �jf*n ,o v `� eo t7- fit;-D,c
_- t , vv •
/
�Z Rb Imo,u�
I Ste• fx�
o
G
Jones & Henry Engineers, Ltd.
City of Carmel
Waste Water Treatment Plant Expansion
Final Clarifier Improvements
Contract 79
Field directive fd#9
Date: Tuesday, December 18, 2013
Issued By: Tom Schreiber, Resident Engineer
City Approved: Ed Wolf
Contractor: M.K. Betts
tE 4 ,,, °, Cpht�actor to perform follow,mg work r, ' 4 ` , x
Contractor to delete the work associated with the removal and reinstallation of the unit
heater, AFlU-1 in the GBT building . Work will result in a deduct to contract price of
$2,150.00
a:rma:, ami:HTom Schreiber
?CrIPYAI l work described above must be,completed m accordance with :_;
w }specifications unless explicitly noted,, , ,. , ..ter
jrOpOsal Page No. of Pages
•
M. K. BETTS ENGINEERING & CONTRACTING, INC.
P.O. Box 2533
ANDERSON, INDIANA 46018
(765) 649-1294 FAX (765) 649-2140
PROPOSAL SUBMITTED TO PHONE DATE
Cannel WWTP • Dec. 16, 2013
•
STREET
JOE NAME
9609 Hazel Dell Parkway Contract 79
CITY,STATE and ZIP CODE JOE LOCATION
Carmel, IN 46033 • I GBT Building
ARCHITECT/ENGINEER DATE OF PLANS JOB PHONE
Jones & Henry Engineers, Ltd, Attn: . Tom Schreiber
We hereby submit specifications and estimates for:
......._ . . all necessary labor, equipment and materials to delete the
reinstall of AHU-1 heater in .the GBT Building. Unit down only,. Deletion of work for
new opening, old opening and resetting unit. _ .
Deduct $2,150.00
•
■
•
•
...._.....
. . ...........__ ..
. ___..._....._.___.................
Mr Propose hereby to furnish material and labor— complete in accordance with above specifications, for the sum of:
Payment to be made as follows.
dollars(S _ ),
All material Is guaranteed to be as specified. All work k to be completed in a workmanlike �
manner according to standard practices Any alteration of deviation from above specifications Authorize
involving
harg ng extra cools 'I be executed only upon written orders, and will became an extra SIQnntl � ��
charge over and above the estimate. All agreements contingent upon strikes. accidents
Note'Throsal ma 're or delays beyond our co ol. Owner to carry e, to nar and other necessary insu e 0
Our workers are fully covered by Workman's Compensation Insurance withdrawn by us If 1#ut accepted within days
Arrrpthnrr of Proposa l -- The above prices,specifications
and conditions are satisfactory and are hereby accepted_ You are authorized Signature__-
to do the work as specified. Payment wit he made as outlined above.
Date ofA ceplance• Signature
. 57 . j
6T , M. Kn i:i ETTS
: &
K Contraetong
- ^
,, Engineering
U n L. P.O. Box 2533 Anderson, Indiana 46018 Telephone(765)649-1294
Fax(765)649-2140
January 16, 2014
Jones & Henry Engineers, Ltd.
1980 E. 116th Street, Ste. 260
Carmel, IN 46032
RE: Change Order
WWTP - Contract 79
Attn: Tom Schreiber
Tom,
Per your change order listing (copy attached) , please find costs
for line items Nos. 3, 4, 6, and 11 all as follows:
No. 3 Per attached work orders Add $ 3,598.50
No. 4 Per attached work orders Add T.B.D.
No. 6 Per attached work orders Add T.B.D.
No. 11 Attached original equipment
Purchase Order (copy attached) $113,876.00
Adjusted P. 0. for diversion
structure only (copy attached) $ 32,100.00
Equipment Deduct $ 81,775.00
G.C. OHP Deduct (±5%) 4,084.00
Deduct with OHP $ 85,860.00
Deduct underground piping and
associated work ±85 l.f. of
16" PVC, road crossing, concrete
encasement asphalt paving and
minor miscellaneous. Deduct $ 13,000.00
Total deduct No. 11 Deduct $98,860.00
If you need additional information, please contact me at your earliest
convenience.
M. K etts Engineering & Contracting, Inc.
a ry D. Montgomer• '
Attachments: NO. 3 - Work Orders 7
NO. 11 - Contract Documentation
tee
Ultraflote Corporation -
ne AwVI 3640 West 12th Street
y j Houston, Texas 77008 Aluminum Geodesic Domes
�. �; Flat Panel Coven
ePhone: 713-461-2100 Ge s ss Covers
MS Fax: 713-461-2213 !.1001
To ALL BIDDING CONTRACTORS Date : 2/5/13
Project : Carmel, IN Bid Date : 2/6/13
From . Ray P. Mutz Ref. : UC-40535
Municipal Account Manager
We are pleased to provide this quotation for the following equipment:
Ultraflote Corporation proposes to furnish and deliver a ALUMTNUIM FLAT PANEL COVER with a standard mill finish
for the value stated below and based on the following clarifications in conjunction with specification section 13130 and
addendum 1,2.
BASE PROPOSAL - MATERIALS ONLY
Ow Diameter/Size Tank Description
1 50'-0" Supernate
1 11'-6 ` x 42'-0" Diversion
ACCESSORIES
— (3) 24" x 30" sq. access hatches
e (2) 6"Nozzles or penetrations for piping or valves
Cover designed to 40 psf live load and 400 lb concentrated load at deflection of L/240.
® Estimated man hours to install the cover is 145 with a 4-man crew.
e Max panel weight 170 lbs.
e Total sq. ft. covered 2,446 sq. ft.
Total Material Price F.O.B. Job site S 95,026.00
Installation labor is not included in the scope of our base proposal
• If supervision is required during installation, Ultraflote can provide an experienced supervisor at the rate of
$1,000.00 per day, from portal-to-portal. This rate is based on a five- (5) day at (8) hours per day normal
workweek, for a total of forty (40) hours. Should more hours a day or for the week be required,they will be
charged at the rate of$ 187.50 per hour. However, it is not recommended to exceed twelve(12) hours per day for
efficiency and safe working conditions for a supervisor. In addition, all travel and living expenses will be for the
customer's account.
• The estimated Man-hours are based on the productivity of an experienced Ultraflote crew. The installation contractor
should consider carefully the productivity of his work force, the site conditions and the construction strategy to be
employed when evaluating these estimates.
Ultraflote Corporation
Project: Cannel, IN
UC#: 40535
Page (2 of 4)
INSTALLED OPTION MATERIALS & LABOR
Total Installed Price $ 113, 876.00
Our Installed Option Price is based upon delivery all materials at one time with installation being done in a continuous
construction program with one UNREPRESENTED field crew at prevailing wage rate.
Ultraflote Corporation is an unrepresented company offering installation of these aluminum flat covers on a non union
basis. In the event there is a claim for the work by others Ultrafiote will exit the site and invoice customer for our costs,plus
overheads and profit to date.
If customer elects to award the order for this project to Ultraflote Corporation, such award will be made according to these
conditions. Accordingly,if any labor difficulties result from the performance of this work,Ultraflote Corporation will exert
its best efforts to assist the customer in resolving any such dispute. Any expenses incurred by Ultrafiote Corporation as a
result of such labor difficulties shall be for the account of the customer.
IF INSTALLATION LABOR IS PROVIDED BY ULTRAFLOTE CORPORATION THEN
THE FOLLOWING ARE TO BE PROVIDED BY THE PURCHASER OF THE FLAT PANEL COVER:
• Crane and required rigging for off loading materials.
• Crane for setting of flat panels and trusses (if required)
• Electric service (115 volt/30 amp) for small tool operation.
• Adequate, level dry working area as close as possible to the tank.
• Structure or site modifications other than construction of the Quad-Seal Welded Aluminum Flat Panel Cover are not
included in our scope of work.
• Any work of other trades, such as electrical, pipe fitting, painting, ductwork, or miscellaneous metal work (e.g.,
handrails, platforms, etc.).
PRICING IS BASED AND CONTINGENT UPON:
• Customer is responsible for providing accurate and complete measurements of tank basin, their attachments and
accessories, existing or to be installed, and site dimensions, unless otherwise agreed to in writing by Ultraflote. If
customer elects, Ultraflote will survey tank/basin or site for additional costs.
• Customer is responsible for providing suitable unobstructed access to the tank/basin and perimeter for the crane,truck
and man-lift.
• Ultraflote will not be responsible for:
• Verifying the tank/basin's ability to support the cover.
♦ Modifications required to the tank/ basin to mount the cover, or modifications required in the field to avoid
interference with equipment or appurtenances not defined in the customer's drawings or specifications.
♦ The tank/basin coating system damage, or repair thereof, resulting from the installation of the cover, or use of
erection equipment, that must be bolted to the wind girder and tank shell.
• Published prevailing wage rates (if applicable) for estimated time of erection. Erection at later dates (i.e. higher
prevailing wage rates)will be charged to the purchaser of the cover.Notice of correct prevailing wage rate is required.
• The pipe work that penetrates the Flat Panel Cover being routed to avoid interference with its structural members.
Ultraflote will provide information to the pipe supplier at time of submittal so he can coordinate his pipe work. Pipe
connection/penetrations at the Flat Panel Cover will be made(by others)such that the pipes penetrate the cover surface
perpendicularly.
Ultraflote Corporation
Project: Carmel. IN
UC #: 40535
Page (3 of 4)
CLARIFICATIONS:
• Bid validity is 30 days from the date of this quotation,for delivery third quarter 2013.Note that prices for aluminum and
other metal components in our products are increasing dramatically.These increases could force price adjustments for
later purchases and deliveries.
• If the project is specified as tax-exempt, the purchaser must provide Ultraflote with a tax-exempt certificate.
• Unless otherwise stated,prices do not include any taxes, license, bonds or permit fees. All such fees and taxes are for
the account of Buyer and shall be paid for by him.If applicable,tax-exempt certificates or resale exemption certificates
should be provided.
• Ultraflote uses Silicone gasket and Silicone elastomers in our covers.
• Ultraflote design based all walls being level,smooth with no handrails around tank(s).Ultraflote will use Silicone tape
for dissimilar materials.
• Since Ultraflote Corporation is not in charge of the project's schedule Ultraflote is not in a position to accept any type of
liquidated damages.
• Unless otherwise stated all trusses will be above panel surfaces.
• Cover to be mounted on angle at center bridge and two piece adjustable z-bend at stem wall.
TERMS: Ultraflote's Standard Terms and Conditions for the domestic purchase of the Ultradome roof are made a part of
this proposal.
DELIVERY:
Based upon current material inventory and space presently available in our schedule, it is estimated that the proposed
Flat Cover Roof could be in manufacturing and shipped within 10 to 12 weeks after receipt of your order and approval.
Assume 6 to 8 weeks after receipt of complete tank information after receipt of complete tank information for approval
drawing preparation and submittal. Please contact us if our proposed delivery schedule does not meet your operational
requirements.
Should you have any questions please feel free to call the under signed at 713-581-7851.
Respectfully,
Ray P.Mutz
Municipal Account Manager
STANDARD TERMS AND CONDITIONS FOR DOMESTIC PURCHASE OF THE,ULTRA DOMED ROOF
I. ACCEPTANCE: The Standard Terms and Conditions set forth herein for purchase of the ULTRADOME from ULTRAFLOTE CORPORATION,(hereinafter call UC)shall be
applicable to all orders accepted by UC and shall cancel and supercede any terms and conditions on purchase order forms or contract fonns submined by Buyer,whether or not
acknowledged or accepted by UC. No modification of the Standard Terms and Conditions shall be effective unless agreed to in writing by an Officer of UC_ These terms and
conditions shall become a binding contract between Buyer and UC upon acknowledgment of Buyer's order by UC.
2. BUYER OBLIGATIONS:To insure optimum performance and proper installation of the ULTRADOME.Buyer shall at its own expense perform the following tank preparation
work and supply all necessary materials therefor,prior to the scheduled arrival of UC and/or subcontractor installation crews. Buyer shall provide to UC and/or subcontractor
satisfaction,suitable and safe 115 volt 50 amp 60 Hz electrical service at the site for use with 110-volt power tools. Buyer shall provide a suitable unobstructed crane and truck
(tractor/40'trailer)access way to tank,which access is to be kept continuously above water,accessible,and passable during erection until all work by UC has been completed and
accepted. Should Buyer so desire,UC shall arrange to door have done the above work,all of which is for the account of the Buyer at a price to be agreed upon by UC and Buyer.
Buyer shall maintain the work area in safe and suitable condition throughout the course of the project. Buyer shall be responsible for storage and protection of materials and UC
equipment during times when UC and/or subcontractor erection crews are not at the construction site. Buyer shall not alter or modify the completed ULTRADOME unless such
modifications have been discussed with UC and agreed to in writing It shall be Buyer's responsibility to comply with all local building codes and to obtain all required building
permits.
3_ PRICES:Unless otherwise stated,prices do not include any license or permit fees,sales,excise,use or other such taxes now in effect or hereinafter levied. All such fees and taxes
are for the account of Buyer and shall be paid for by him. Our prices are based on current material prices,present freight rates and our current rates for shop and field labor. Should
- there be any changes in any of these prices or rates,our proposal shall be adjusted by the difference in our costs,including overhead and profit resulting from such changes.
4. TERMS OF PAYMENT:The full contract price shall he due and payable as follows. The material portion,or 75%of the contract price for each dome shall be due and payable by
the Buyer within 15 days after the dome materials have been delivered to the Buyer's tank site by UC. The remaining 25%of the contract price,or the labor portion for each dome
shall be due and payable within 15 days after the dome installation has been completed. Interest shall he payable on any over-due amounts at the rate of 1 1/2%per month or portion
thereof or the maximum rate allowable by law whichever is lower. If UC shall retain a collection agency and/or attorneys to collect amounts overdue,all collection costs,including
anorney's fees,shall be payable by Buyer. UC shall give at least 10 days written notice of its intention in this respect. Progress payments are required for orders in excess of
$500,000.00.
5. CREDIT:Fabrication,delivery,and erection of the ULTRADOME shall at all times be subject to the continuing approval of financial responsibility of Buyer by UC. If financial
responsibility and/or condition of Buyer reasonably appears to call for such action,UC may decline to fabricate,deliver or erect,or may require payment in advance or a suitable
guarantee that all invoices will be paid when due. If Buyer becomes insolvent or for any reasons fails to make payment when due,UC reserves the right to terminate the Contract
forthwith upon written notice to Buyer,without prejudice to any other remedy available to UC.
6. LOSS OF MATERIALS:All risks concerning damage to or loss of materials furnished to the Buyer under the Contract shall transfer immediately to the Buyer upon delivery of the
materials to the Buyer's facility or other point specified in the Contract.
7. WARRANTY:UC warrants free and clear title to all products delivered hereunder. On those installations where erection is performed by UC personnel and/or authorized
subcontractor,UC further warrants that the ULTRADOME shall be free from defects in materials or workmanship for a period of 12 months from the date of completion of work;
misuse,negligence,or ordinary wear and tear excepted,and UC agrees to repair or replace without expense to Buyer any workmanship or materials furnished hereunder that may
prove defective within said period. UC shall not be responsible for any consequential,special or contingent damages. Any claim by Buyer under this warranty shall be deemed
conclusively waived unless written notice is given to UC within 10 days after discovery of any claimed defective workmanship and/or materials. This warranty shall not apply to any
dome,which has been repaired,altered,or modified by anyone unless specifically authorized by UC so to do. The warranty as set forth herein is in lieu of all other warranties either
expressed or implied. ALL IMPLIED WARRANTIES,INCLUDING MERCHANTABILITY AND FITNESS FOR PURPOSE,ARE HEREBY DISCLAIMED AND EXCLUDED.
8. DELAYS:UC shall not be liable for any delays or failure in performance caused by any condition beyond our direct control including but not limited to Acts of God,unusual
delays in manufacture,unusual delays in transportation or shipments,strikes,lockouts,or other labor difficulties,fires floods,unavoidable causes not due to fault or negligence of
UC. UC shall not be liable for any delays or failure in performance caused by any act or neglect of Buyer,or by delays of our suppliers in furnishing materials or supplies due to one
or more of the foregoing causes.
9. PERFORMANCE:Unless otherwise specified in writing,UC shall famish all necessary materials,labor supervision and equipment for installation of the ULTRADOME in
compliance with the terms for this contract between Buyer and UC_ All materials shall be new unless otherwise specified and he suitable for the intended purpose. UC shall have the
right to subcontract all or any part of the work to one or more subcontractors of its selection provided each such subcontractor agrees to assume all the responsibilities and obligations
of UC with respect to said work. UC shall not permit any third party attachment or lien arising out of work to be performed hereunder to be imposed upon property of Buyer. UC
shall protect Buyer's property and adjacent property from injury or loss arising from UC and/or subcontractor performance of the work hereunder. UC shall not be responsible for
any injury or loss caused by Buyer or its representatives,employees,or contractors. UC shall at all II times keep Buyer's premises free from accumulations of waste materials
resulting from its operations. UC shall take all necessary precautions for the safety of employees on the work and shall comply with security,safety and fire regulations of Buyer in
force at the site of work. Buyer shall furnish all fire watch and lire protective services,all at its own expense. UC shall comply with all governmental laws relating to the
performance of work hereunder and certifies that all materials purchased by Buyer hereunder were produced in compliance with all applicable requirements of the Fair Labor
Standards Act of 1938,as amended. UC shall have the right to use its own discretion in the employment of labor. In case of interference in the work hereunder by reason of changed
conditions,local labor conditions,or any requirements on the part of buyer with reference to labor or other conditions,UC shall have the right to stop the work without prejudice until
such interference is satisfactorily adjusted. Work shall be performed on the basis of a normal 8 hour day and 40 hour work week,excluding holiday's,and weekends. Additional costs
incurred from working overtime at Buyer's request will be for Buyer's account. Should Buyer be responsible for any cessation of normal work procedure by UC and/or subcontractor
erection crews. Buyer shall accept billing and pay UC for all extra costs resulting therefrom. UC and/or its subcontractor shall indemnify Buyer against any valid claim for patent
infringement or trademark infringement. By notice in writing to the other party hereto,UC and Buyer shall have the right to make changes in the nature or extent of the work
required by this Contract within its general scope but no additional charges will be allowed unless authorized in writing by Buyer. If any such changes materially affects the
completion or costs of the work,UC shall promptly notify Buyer,and the parties hereto shall negotiate an adjustment. The method and agency of transportation and the routing will
be designated by UC. Due to a policy olcontinuous improvement,UC reserves the right to modify the design of the ULTRADOME_ Any such modifications shall not incur any
obligations to previous ULTRADOME owners.
10. INSURANCE:UC and/or subcontractors shall maintain the following insurance coverage in amounts not less than that indicated. Certificates of such insurance will be furnished
to Buyer on request.
A. Workmen's Compensation Statutory
B. Employer's Liability $100,000
C. Comprehensive General Liability':
Bodily Injury and Properly Damage $500,000 Each occurrence
D. Comprehensive Automobile Liability:
Bodily Injuy and Property Damage $500,000 Each occurrence
E. Contractual Liability:
Bodily Injury and Property Damage $500,000 Each occurrence
F. Umbrella Excess Liability $1,000,000
It CANCELLATION:In the event that Buyer fails to accept materials ordered or advises UC of its intention not to accept delivery,buyer shall be liable for UC cancellation charges
which shall not exceed the purchase price of all undelivered materials and labor expended on the order at the time of cancellation plus 10%thereof,together with all handling and
shipping costs incurred by UC as a result of such cancellation.
12. CONSTRUCTION:this contract shall be construed under laws of the State of Texas.
F:\COMMON\WP\ORIG INA L\DOMR FTRM.W I'D
rte„
ran t e a Ultraflote Corporation
imp
P !'4 �F
3640 West 120 Street l
its Houston, Texas 77008 Awmmum Geodesic Domes
d Flat Panel Covers
Phone: 713-461-2100 Geowss Covers
°i%SOF Fax: 713-461-2213 \
To : MK Betts Date : 8/14/13
Project : Carmel, IN Bid Date : 2/6/13
From . Ray P. Mutz Ref. : UC-40535
Municipal Account Manager
We are pleased to provide this quotation for the following equipment:
Ultraflote Corporation proposes to furnish and deliver a ALUMINUM FLAT PANEL COVER with a standard mill finish
for the value stated below and based on the following clarifications in conjunction with specification section 13130 and
addendum 1,2.
BASE PROPOSAL - MATERIALS ONLY
Qtv Diameter/Size Tank Description
1 11'-6 ` x 42'-0" Diversion
ACCESSORIES
e (3) 24" x 30" sq. access hatches
e (2) 6"Nozzles or penetrations for piping or valves
e Cover designed to 40 psf live load and 400 lb concentrated load at deflection of L/240.
Estimated man hours to install the cover is 22 with a 4-man crew.
re Max panel weight 165 lbs.
e Total sq. ft. covered 483 sq. ft.
e Total weight 1,446 lbs.
e (1)Panel notch at gate
Total Material Price F.O.B. Job site $ N/A
Installation labor is not included in the scope of our base proposal
♦ If supervision is required during installation, Ultraflote can provide an experienced supervisor at the rate of
$1,000.00 per day, from portal-to-portal. This rate is based on a five- (5) day at(8) hours per day normal
workweek, for a total of forty (40) hours. Should more hours a day or for the week be required, they will be
charged at the rate of$ 187.50 per hour. However, it is not recommended to exceed twelve (12) hours per day for
efficiency and safe working conditions for a supervisor. In addition, all travel and living expenses will be for the
customer's account.
• The estimated Man-hours are based on the productivity of an experienced Ultraflote crew. The installation contractor
should consider carefully the productivity of his work force, the site conditions and the construction strategy to be
employed when evaluating these estimates.
Ultraflote Corporation
Project: Cannel, IN
UCII: 40535
Page (2 of 4)
INSTALLED OPTION MATERIALS & LABOR
Total Installed Price $ 32,100.00
Our Installed Option Price is based upon delivery all materials at one time with installation being done in a continuous
construction program with one UNREPRESENTED field crew at prevailing wage rate of$45.69 per hour.
Ultraflote Corporation is an unrepresented company offering installation of these aluminum flat covers on a non union
basis.In the event there is a claim for the work by others Ultraflote will exit the site and invoice customer for our costs,plus
overheads and profit to date.
If customer elects to award the order for this project to Ultraflote Corporation,such award will be made according to these
conditions. Accordingly, if any labor difficulties result from the performance of this work,Ultraflote Corporation will exert
its best efforts to assist the customer in resolving any such dispute. Any expenses incurred by Ultraflote Corporation as a
result of such labor difficulties shall be for the account of the customer.
IF INSTALLATION LABOR IS PROVIDED BY ULTRAFLOTE CORPORATION THEN
THE FOLLOWING ARE TO BE PROVIDED BY THE PURCHASER OF THE FLAT PANEL COVER:
• Crane and required rigging for off loading materials.
• Crane for setting of flat panels and trusses (if required)
• Electric service (115 volt/30 amp) for small tool operation.
• Adequate, level dry working area as close as possible to the tank.
• Structure or site modifications other than construction of the Quad-Seal Welded Aluminum Flat Panel Cover are not
included in our scope of work.
• Any work of other trades, such as electrical, pipe fitting, painting, ductwork, or miscellaneous metal work (e.g.,
handrails, platforms, etc.).
PRICING IS BASED AND CONTINGENT UPON:
• Customer is responsible for providing accurate and complete measurements of tank/basin, their attachments and
accessories, existing or to be installed, and site dimensions, unless otherwise agreed to in writing by Ultraflote. If
customer elects, Ultraflote will survey tank/basin or site for additional costs.
• Customer is responsible for providing suitable unobstructed access to the tank/basin and perimeter for the crane,truck
and man-lift.
• Ultraflote will not be responsible for:
• Verifying the tank/ basin's ability to support the cover.
♦ Modifications required to the tank/ basin to mount the cover, or modifications required in the field to avoid
interference with equipment or appurtenances not defined in the customer's drawings or specifications.
• The tank/basin coating system damage, or repair thereof, resulting from the installation of the cover, or use of
erection equipment, that must be bolted to the wind girder and tank shell.
• Published prevailing wage rates (if applicable) for estimated time of erection. Erection at later dates (i.e. higher
prevailing wage rates) will be charged to the purchaser of the cover.Notice of correct prevailing wage rate is required.
• The pipe work that penetrates the Flat Panel Cover being routed to avoid interference with its structural members.
Ultraflote will provide infonnation to the pipe supplier at time of submittal so he can coordinate his pipe work. Pipe
connection/penetrations at the Flat Panel Cover will be made(by others)such that the pipes penetrate the cover surface
perpendicularly.
•
Ultraflote Corporation
Project: Carmel, IN
UC #: 40535
Page (3 of 4)
CLARIFICATIONS:
• Bid validity is 30 days from the date of this quotation,for delivery third quarter 2013.Note that prices for aluminum and
other metal components in our products are increasing dramatically. These increases could force price adjustments for
later purchases and deliveries.
• If the project is specified as tax-exempt, the purchaser must provide Ultraflote with a tax-exempt certificate.
• Unless otherwise stated, prices do not include any taxes, license, bonds or permit fees. All such fees and taxes are for
the account of Buyer and shall be paid for by him.If applicable,tax-exempt certificates or resale exemption certificates
should be provided.
• Ultraflote uses Silicone gasket and Silicone elastoniers in our covers.
• Ultraflote design based all walls being level, smooth with no handrails around tank(s).Ultraflote will use Silicone tape
for dissimilar materials.
• Since Ultraflote Corporation is not in charge of the project's schedule Ultraflote is not in a position to accept any type of
liquidated damages.
• Unless otherwise stated all trusses will be above panel surfaces.
• Cover to be mounted directly on the top wall.
TERMS: Ultraflote's Standard Terms and Conditions for the domestic purchase of the Ultradome roof are made a part of
this proposal.
DELIVERY:
Based upon current material inventory and space presently available in our schedule, it is estimated that the proposed
Flat Cover Roof could be in manufacturing and shipped within 10 to 12 weeks after receipt of your order and approval.
Assume 4 to 6 weeks after receipt of complete tank information after receipt of complete tank information for approval
drawing preparation and submittal. Please contact us if our proposed delivery schedule does not meet your operational
requirements.