HomeMy WebLinkAbout233720 06/18/14 J�%,.4eq,,� CITY OF CARMEL, INDIANA VENDOR: 068025
``. CHECK AMOUNT: $****36,190.40*
.{ ® ONE CIVIC SQUARE CROSSROAD ENGINEERS, PC
r ,?a. CARMEL, INDIANA 46032 3417 S SHERMAN DR CHECK NUMBER: 233720
9M,�P6N"�O. BEECH GROVE IN 46107 CHECK DATE: 06/18/14
DEPARTMENT ACCOUNT PO NUMBER INVOICE NUMBER AMOUNT DESCRIPTION
212 R4462865 25294 14305 26,434.90 ILL ST EXT PHASE 2
202 4340100 31836 14340 275.50 2014 DRAINAGE PLAN
202 4340100 31902 14340 7,980.00 PLAN REVIEW
202 R4340100 25306 14342 1,500.00 ALLEYS NE QUAD
CrossRoad Engineers, PC
3417 Sherman Drive
Beech Grove, IN 46107
317-780-1555
City of Carmel Invoice number 14342
Jeremy Kashman Date 06/05/2014
1 Civic Square
Carmel, IN 46032 Project 2013 NE QUAD ALLEY PROJECT
For services performed April 26,2014 through May 30,2014.
PROMPT PAYMENT OF INVOICE IS APPRECIATED!!
These services were provided in accordance with our contract#030310.03.
(:PO#253_06 X02 - R
Appropriation#202-401
Amount
Topographic Survey
Contract Amount 3,500.00
Percent Complete 100.00
Total 3,500.00
Billed
Current Billed 0.00
Design&Construction Drawings
Contract Amount 12,500.00
Percent Complete 100.00
Total 12,500.00
Billed
Current Billed 0.00
Regulatory Submittals&Bidding Phase
Contract Amount 3,000.00
Percent Complete 100.00
Total 3,000.00
Billed
Current Billed 750.00
Construction Staking and Administration
Contract Amount 3,000.00
Percent Complete 25.00
Total 750.00
Billed
Current Billed 750.00
Total 1,500.00
Invoice total 1,500.00
City of Carmel Invoice number 14342 Invoice date 06/05/2014
Page 1 of 2
City of Carmel Invoice number 14342
Project 2013 NE QUAD ALLEY PROJECT Date 06/05/2014
Than Y !
Chip CharleJQ( Y
President
City of Carmel Invoice number 14342 Invoice date 06/05/2014
Page 2 of 2
tr
Cross Road Engineers,PC
3417 Sherman Drive ` �a
Beech Grove, IN 46107
317-780-1555 GARMEI
6'� GIIY s1�
City of Carmel Invoice number 14305
Jeremy Kashman Date 06/05/2014
1 Civic Square
Carmel, IN 46032 Project ILLINOIS STREET PROJECT 10-10
For services performed April 26,2014 through May 30,2014.
PROMPT PAYMENT OF INVOICE IS APPRECIATED!!
These services were provided in accordance with our proposal dated September 16,2013 and our Agreement
for Professio al Services dated November 20,2013:
_��� 2 12— R`F�42� �CS
CO#25294
Inspection
Professional Fees
Billed
Hours Rate Amount
Director 27.00 135.00 3,645.00
Project Inspector 77.00 85.00 6,545.00
Resident Project Representative 147.00 105.00 15,435.00
Reimbursables
Billed
Units Rate Amount
Miles 1,619.80 0.50 809.90
Phase subtotal 26,434.90
Invoice total 26,434.90
Tha o !
l
l
Chip Charle f 1
President
City of Carmel Invoice number 14305 Invoice date 06/05/2014
Page 1
Illinois Street Project 10-10
Inspection
Date Range from:4/26/2014 to 5/30/2014 Work In Progress
!Employee/Activity Total Billed WIP Total Billable Deferred Hold Non Billable Writeoff�
Justin M.Schneck 77.00 77.00
Billable Time 77.00 77.00
Date Total Billed WIP Total Billable Deferred Hold Non Billable Writeoff
5/1972014 8.50 8.50
5/20/2014 10.00 10.00
5/21/2014 10.50 10.50
5/22/2014 9.00 9.00
5/23/2014 6.00 6.00
5/27/2014 8.00 8.00
5/28/2014 9.00 9.00
5/29/2014 8.00 8.00
5/30/2014 8.00 8.00
Lance A.Stahley 147.00 147.00
Billable Time 147.00 147.00
Date Total Billed WIP Total Billable Deferred Hold Non Billable Writeoff
4/28/2014 8.00 8.00
4/28/2014 1.00 1.00
4/29/2014 6.00 6.00
4/29/2014 2.00 2.00
5/1/2014 4.00 4.00
5/1/2014 1.00 1.00
5/2/2014 8.00 8.00
5/2/2014 1.00 1.00
5/5/2014 7.00 7.00
5/6/2014 8.00 8.00
5/7/2014 7.00 7.00
5/8/2014 7.00 7.00
5/12/2014 4.00 4.00
5/12/2014 1.00 1.00
5/13/2014 5.00 5.00
5/14/2014 4.00 4.00
5/14/2014 1.00 1.00
5/15/2014 4.00 4.00
5/15/2014 1.00 1.00
Illinois Street Project 10-10
l
Inspection
I Date Range from:4/26/2014 to 5/30/2014 Work In Progress i
Employee/Activity Total Billed WIP Total Billable Deferred Hold Non Billable Writeoff
5/16/2014 5.00 5.00
5/16/2014 1.00 1.00
5/19/2014 9.00 9.00
5/20/2014 8.00 8'.00
5/21/2014 8.00 8.00
5/22/2014 6.00 6.00
5/27/2014 7.00 7.00
5/28/2014 9.00 9.00
5/29/2014 5.00 5.00
5/30/2014 9.00 9.00
Trent E.Newport 27.00 27.00
Billable Time 27.00 27.00
Date Total Billed WIP Total Billable Deferred Hold Non Billable Writeoff
4/28/2014 2.00 2.00
4/29/2014 1.00 1.00
4/30/2014 1.00 1.00
5/1/2014 1.00 1.00
5/2/2014 1.00 1.00
5/5/2014 2.00 2.00
5/6/2014 2.00 2.00
5/7/2014 1.00 1.00
5/8/2014 1.00 1.00
5/12/2014 1.00 1.00
5/13/2014 1.00 1.00
5/15/2014 1.00 1.00
5/16/2014 3.00 3.00
5/19/2014 1.00 1.00
5/20/2014 1.00 1.00
5/21/2014 1.00 1.00
5/22/2014 1.00 1.00
5/23/2014 1.00 1.00
5/27/2014 1.00 1.00
5/28/2014 1.00 1.00
5/29/2014 1.00 1.00
5I16nois.Streeffroject 10-10
i Inspection 111E
Date Range from:4/26/2014 to 5/30/2014 Work In Progress
Employee/Activity Total Billed WIP Total Billable Deferred Hold Non Billable Writeoff
5/30/2014 1.00 1.00
Total 251.00 251.00
Illinois St. Inspection Phase Mileage
e . 1
=�rojel* ! ! e a - !es- c-riptione e
Inspection. 1,619.80 809.90
04/28/14 Illinois Street Project 10-10 Inspection Mileage 46.00 23.00 ✓
�-04/29/14 Illinois Street Project 10-10 Inspection _ Mileage 77.00_ 38.50-_ __✓ -�.. ...
04/29/14 Illinois Street Project 10-10 Inspection Mileage 70.00 35.00 ✓
04/30/14 Illinois Street Project 10-10 _Inspectio_n _Mileage_ 37.00 18.50 ✓
05/01/14 -Illinois Street Project 10-10 Inspection __ --Mileage 39.00- 19.50- --_✓
05/02/14 Illinois Street Project 10-10 Inspection Mileage 56.00 28.00 ✓
05/05/14 Illinois Street Project 10-10 Inspection Mileage 24.00 12.00 ✓
05/06/14 Illinois Street Project 10-10 Inspection Mileage 63.00 31.50 ✓
05/07/14 Illinois Street Project 10-10 Inspection Mileage 49.00 24.50 ✓
- 05/08/14 Illinois Street Project 10-10 Inspection Mileage _ 53.00 _ 26.50 _____,✓_____
05/12/14 Illinois Street Project 10-10 Inspection Mileage 41.00 20.50 ✓
_05/13/14 Illinois Street Project 10-10 Inspection Mileage 45.00 22.50 ✓
05/14/14 __. Illinois Street Project 10-10 Inspection-�---- Mileage
g 41.00 20.50 ✓
05/15/14 Illinois Street Project 10-10 Inspection Mileage 63.00 31.50 ✓
05/16/14 Illinois Street Project 10-10 Inspection Mileage 72.00 36.00 ✓
05/16/14 Illinois Street Project 10-10 Inspection Mileage 40.00 20.00 ✓
05/19/14 Illinois Street Project 10-10 Inspection Mileage 45.00 22.50 ✓
05/19/14 Illinois Street Project 10-10 Inspection Mileage 45.40 22.70 ✓
/14 Illinois Street Project 10-10 Inspection Mileage 55.20 27.60 ✓
05/20/14 Illinois Street Project 10-10 Inspection Mileage 41.00 20.50 ✓
_05/21/14 Illinois_Street Project 10-10 Inspection Mileage_ 52.20 26.10 ✓_
�- 05/21/14 Illinois Street Project 10-10 Inspection -� - Mileage _ _- 43.00- 21.50 ✓_ __
05/22/14 Illinois Street Project 10-10 _Inspection Mileage - 55.20 27.60 `✓
�__.__.._..._.�._..�.�.._..�_.µ 'ect 10-� Inspection Ins
05/22 14 Illinois Street Project 10-_ _ p Mileage 30.00 15.00 ✓
05/23/14�Illinois-Street Project 10-10 Inspection M�� -- --Mileage- - 5_2.20 - 26.10
05/27/14 Illinois Street Project 10-10 Inspection _ - Mileage --� 45.40 22.70 N ✓
05/27/14 Illinois Street Project 10-10 Inspection Mileage 53.00 26.50 ✓
05/28/14 Illinois Street Project 10-10 Inspection Mileage 42.00 21.00 ✓
05/28/14 Illinois Street Project 10-10 Inspection Mileage 51.40 25.70 ✓
05/29/14 Illinois Street Project 10-10 Inspection Mileage 54.40 27.20 ✓
05/29/14 Illinois Street Project 10-10 Inspection Mileage 41.00 20.50 ✓
05/30/14 Illinois Street Project 10-10 Inspection Mileage 54.40 27.20 ✓
05/30/14 Illinois Street Project 10-10 Inspection Mileage 43.00 21.50 ✓
SSR REGI\�
Cross Road Engineers,PC �- ,`"." ®o
3417 Sherman Drive
Beech Grove, IN 46107 C,NG`oE
317-780-1555 Com, G�� ��
City of Carmel Invoice number 14340
Jeremy Kashman Date 06/05/2014
1 Civic Square
Carmel, IN 46032 Project CITY OF CARMEL-2014 ON-CALL PLAN
REVIEW
For services performed April 26,2014 through May 30,2014.
PROMPT PAYMENT OF INVOICE IS APPRECIATED!!
These services were provided in accordance with our contract dated May 1,2013 and ASA#7 dated February
14,2014 and ASA#9 dated May 21,2014.
ASA#7 PO#31902 2 p 2 - 401 _�R EO
ASA#9 PO#31836 -20-2 -401
General Plan Review
Professional Fees
Billed
Hours Rate Amount
Director 2.00 135.00 270.00
Senior Project Manager 19.50 120.00 2,340.00
Project Engineer 6.00 90.00 540.00
Reimbursables
Billed
Units Rate Amount
Miles 131.00 0.50 65.50
Phase subtotal 3,215.50
126th&Bay Hill
Professional Fees
Billed
Hours Rate Amount
Project Engineer 4.50 90.00 405.00
AMPG
Professional Fees
Billed
Hours Rate Amount
Project Engineer 5.00 90.00 450.00
Bethlehem Lutheran Parking Lot
Professional Fees
Billed
Hours Rate Amount
Project Engineer 2.50 90.00 225.00
City of Carmel Invoice number 14340 Invoice date 06/05/2014
Page 1 of 3
City of Carmel Invoice number 14340
Project CITY OF CARMEL-2014 ON-CALL PLAN REVIEW Date 06/05/2014
Butler Hyundai
Professional Fees
Billed
Hours Rate Amount
Project Engineer 1.50 90.00 135.00
Gateway Plaza
Professional Fees
Billed
Hours Rate Amount
Project Engineer 4.00 90.00 360.00
Hazeldell Christian Church
Professional Fees
Billed
Hours Rate Amount
Project Engineer 1.50 90.00 135.00
Overbrook Farms Section 2
Professional Fees
Billed
Hours Rate Amount
Project Engineer 6.00 90.00 540.00
Overbrook Farms Section 3
Professional Fees
Billed
Hours Rate Amount
Project Engineer 6.00 90.00 540.00
Playschool at the Legacy
Professional Fees
Billed
Hours Rate Amount
Project Engineer 3.00 90.00 270.00
Point Blank Range&Gun Shop
Professional Fees
Billed
Hours Rate Amount
Project Engineer 3.50 90.00 315.00
Saddlebrook @ Shelbourne 3&4
Professional Fees
Billed
Hours Rate Amount
Project Engineer 6.00 90.00 540.00
Schumacher Residence
Professional Fees
Billed
Hours Rate Amount
Project Engineer 3.50 90.00 315.00
Tallyn's Ridge
Professional Fees
Billed
Hours Rate Amount
Project Engineer 1.00 90.00 90.00
Tallyn's Ridge
City of Carmel Invoice number 14340 Invoice date 06/05/2014
Page 2 of 3
City of Carmel Invoice number 14340
Project CITY OF CARMEL-2014 ON-CALL PLAN REVIEW Date 06/05/2014
The Sanctuary at 116th Street-Section 6(Formerly Section 413)
Professional Fees
Billed
Hours Rate Amount
Project Engineer 3.50 90.00 315.00
Tom Wood Audi
Professional Fees
Billed
Hours Rate Amount
Project Engineer 1.50 90.00 135.00
Woodland Terrace of Carmel
Professional Fees
Billed
Hours Rate Amount
Project Engineer 3.00 90.00 270.00
Woodland Terrace of Carmel
Woodland terrace of Carmel
Invoice total 8,255.50
Thank 0u!
r r
Chip C ar P. E.
President
City of Carmel Invoice number 14340 Invoice date 06/05/2014
Page 3 of 3
Prescribed by State Board of Accounts City Form No.201(Rev.1995)
ACCOUNTS PAYABLE VOUCHER
CITY OF CARMEL
An invoice or bill to be properly itemized must show: kind of service, where performed, dates service rendered, by whom,
rates per day, number of hours, rate per hour, number of units, price per unit, etc.
Payee
Crossroad Engineers Purchase Order No.
3417 Sherman Drive Terms
Beech Grove, IN 46107 Date Due
Invoice Invoice Description
Date Number (or note attached invoice(s)or bill(s). Amount
61512014 14342 NE Quad Alley Project $ 1,500.00
6/5/2014 14305 Illinois Street Project 10-10-Inspection $ 26,434.90
6/5/2014 14340 2014 On-call plan review $ 7,980.00
6/5/2014 14340 2014 On-call plan review $ 275.50
Total $ 36,190.40
1 hereby certify that the attached invoice(s), or bill(s), is (are)true and correct and I have audited same in accordance
with IC 5-11-10-1.6.
,20
Clerk-Treasurer
VOUCHER NO WARRANT NO.
Crossroad Engineers ALLOWED 20
3417 Sherman Drive IN SUM OF$
Beech Grove, IN 46107
$ 36,190.40
ON ACCOUNT OF APPROPRIATION FOR
Board Members
P09 or INVOICE NO. ACCT#/TITLE AMOUNT
DEPT# I hereby certify that the attached invoice(s), or
25306 14342 202-R4340100 $ 1,500.00 bill(s) is (are)true and correct and that the
materials or services itemized thereon for
25294 14305 212-R4462865 $ 26.434.90 which charge is made were ordered and
31902 14340 202-401 $ 7,980.00 received except
31836 14340 202-401 $ 275.50
6/16/2014
Sign ure
City Engineer
Cost Distribution ledger classification if Title
claim paid motor vehicle highway fund