HomeMy WebLinkAbout080414 Report to CouncilCARMEL REDEVELOPMENT COMMISSION
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 1
Carmel Redevelopment Commission
STRATEGIC HIGHLIGHTS
HJ Umbaugh presented a 2014 Tax Increment Special Purpose Report at the July CRC meeting. The
presentation is attached. Council received digital and printed copies of the report on July 17, 2014.
Since April, the CRC has reduced its forecasted non-operating expenses by $500,000.
Received bids for site work around the Mezz property. A contractor will be selected at an August
meeting.
FINANCIAL HIGHLIGHTS
June Beginning Balance $ 170,077
June Revenues $ 10,354,078
June Expenditures $ 293,482
June Ending Balance $ 10,930,674
OPERATING HIGHLIGHTS
The Department of Redevelopment has hired a summer intern. The intern’s primary
responsibilities has been to focus on asset inventory and file organization. She will complete her
work by the first part of August.
LOOKING AHEAD
The CRC is seeking a mutual agreement sale price/package for the property located at 7th Street NE
and 2nd Avenue NE. Resolution CC-08-04-14-01 represents the proposed package.
The CRC will be opening bids for the Nash site work in August.
Construction should begin in August for both projects.
Corrie Meyer, AICP, RLA, LEED AP
Director
Carmel Redevelopment Commission/Department
July 25, 2014
Prepared for David Bowers and Brad Meyer
FINANCIAL STATEMENT
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 2
Financial Statement
JUNE MONTH-END FINANCIAL BALANCE
Ending Balance without Restricted Funds $ 10,930,674
Ending Balance with Restricted Funds $ 12,233,671
SUMMARY OF CASH
For the Month Ending June 30, 2014
DESCRIPTION ACTUAL BUDGET VARIANCE
Cash Balance 6/1/14
1101 Cash $160,384.14 $160,384.14 $-
1110 TIF 9,693.30 9,693.30 -
Total Cash $170,077.44 $170,077.44 $-
Receipts
1101 Cash $364,711.90 $479,473.00 $(114,761.10)
1110 TIF 10,689,365.84 6,489,842.50 4,199,523.34
Developer Payments - - -
Total Receipts $11,054,077.74 $6,969,315.50 $4,084,762.24
Disbursements
1101 Cash $146,462.07 $87,041.00 $(59,421.07)
1110 TIF 147,019.61 148,962.00 1,942.39
Total Disbursements $293,481.68 $236,003.00 $(57,478.68)
1101 Cash $378,633.97 $552,816.14 $(174,182.17)
1110 TIF 10,552,039.53 6,350,573.80 $4,201,465.73
Cash Balance 6/30/14 $10,930,673.50 $6,903,389.94 $4,027,283.56
Total Usable Funds $10,930,673.50 $6,903,389.94 $4,027,283.56
FINANCIAL STATEMENT
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 3
FUND BALANCES AND OUTSTANDING RECEIVABLES
As of June 30, 2014
Restricted Funds
Energy Center Reserve $ 501,517
Civic Rent Reserve 801,481
Sub-total: 1,302,998
Cash (as seen in Summary of Cash table)
TIF 10,552,040
Operating 378,634
Sub-total: 10,930,674
Total Funds $12,233,671
Outstanding Receivables
Energy Consumption Payments (1) 28,101
Keystone Group (Bond Enhancement) 172,753
Total Outstanding Receivables $200,854
(1) Amounts due reflects months April – July 2014 for Office Building One
and months June – July 2014 for the Tarkington. REI Real Estate
Services, LLC acts as property manager on behalf of the CRC and collects
the Energy Consumption Payments to be forwarded to the CRC.
STATEMENT OF CHANGES IN EQUITY
MONTH END: JUNE 2014
DESCRIPTION REVENUE EXPENSES
Total Receipts (Non-Operating) $10,265,587
Total Receipts (Operating): $88,490
Expenditures (Non-Operating) $157,115
Expenditures (Operating) $136,367
FINANCIAL UPDATE
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 4
Financial Update
TIF REVENUE AND DEBT
As of the approved June budget, projected TIF Revenue was estimated at $17,532,007.
Bond debt payments were made in June and July. Another payment will be made in December of 2014.
Below are the anticipated payments based on the June approved CRC budget;
MONTH TOTAL
June 2014 $ 484,228
July 2014 $ 8,276,336
December 2014 $ 8,774,841
GOING CONCERN
The CRC is managing expenditures to maintain a balanced budget in anticipation of lower TIF Revenue.
TAKEAWAYS
Month-end balance is positive.
The updated TIF report serves as a conservative fiscal forecast for the CRC. The CRC will continue
to operate fiscally responsible to manage its revenue and debt obligations. Staff is actively seeking
ways to increase its revenue to offset any future withdraws from its Supplemental Reserve Fund.
PROJECT UPDATES
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 5
Project Updates
CITY CENTER
• Developer Partner: Pedcor Companies
• Allocation Area: City Center
• Project Summary:
• Use: Mixed-Use
Figure 1 City Center Master Plan, provided by Pedcor City Center Development Company
• Phase 1 – complete
1) Apartments - Demand for apartment’s remains strong which supports the occupancy and rental
rates. Current occupancy is at 99%.
2) Retail – Currently, Pedcor has leases on 91% of the total 79,570 in LSF. The remaining 9% (the old
Mangia, Holy Cow, & Sports Authority locations) of unleased space have future tenants for them,
and are working through the space planning process. Pedcor anticipates to be 100% leased by fall
of 2014.
PROJECT UPDATES
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 6
• Nash Building/ Parcel 73
1) Project Status – under construction
a) The Nash underground parking garage is 90% complete and currently
on budget. The Nash Building roof has been completed and windows
are expected to be installed in the next few weeks. Framing and
electrical/plumbing rough in has started with the anticipation of
drywall install once the building is closed. Electric supply from Duke
Energy is on a critical path. The project is on budget and remaining on
schedule, with an anticipated completion date of fall 2014.
Approximately half of the 9,000 sf of the retail space has been leased
with strong prospects for the remaining commercial space.
2) Council and/or CRC Action Items
ACTION ITEM CITY COUNCIL CRC
Receiving bids on 7/28/14 Open bids in August
3) CRC Commitments
Provide streetscape along Rangeline Road.
a) Budget
Design/ Engineering $5,000 (majority of contract
pd. in 2013)
Construction $100,000
b) Design Consultant: American Structurepoint
c) CRC Commitment Schedule
Design % Complete 100%
Proposed Construction Start Date August 2014
Anticipated Project Completion October 2014
Provided by Pedcor City Center
Dev. Co. 1
PROJECT UPDATES
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 7
• Phase 2
1) Project Status – designs are schematic and construction has not started.
a) Project initiation discussions are continuing between Pedcor and the CRC. Staff has been
meeting with Councilors independently to introduce a comprehensive approach for the
completion of City Center.
2) Proposed Construction/Use Sequence
PROJECT USE START DATE DESIGN RENDERINGS,
PROVIDED BY PEDCOR
Garage
East
A three to four story parking structure with
approximately 470 to 625 parking spaces,
which will include up to approximately
28,000 square feet of luxury apartments
and commercial retail/office space.
Fall 2014
(garage only)
Baldwin/
Chambers
A four story building, of approximately
64,000 square feet, which will include
luxury apartments and commercial
retail/office space. Pedcor is currently
working with four commercial businesses
who will occupy approximately 14,000 sf of
the commercial space.
Fall 2014
Holland A five story building, of approximately
63,000 square feet, which will include
luxury apartments and commercial
retail/office space.
Fall 2014
Playfair A five story building, of approximately
63,000 square feet, which will include
luxury apartments and commercial
retail/office space.
Fall 2015
Garage
Retail
See Garage East note above. Fall 2015
Pedcor
Office 5
A two story building, of approximately
20,000 to 25,000 square feet, which will
include office space.
Fall 2015
PROJECT UPDATES
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 8
Kent A three story building, of approximately
111,000 square feet of luxury apartments.
Fall 2015
Wren A seven story building, of approximately
88,000 square feet, which will include
luxury apartments and commercial
office/retail space.
Fall 2016
Windsor A four story building, of approximately
64,000 square feet, which will include
luxury apartments and commercial
office/retail space.
Fall 2017
Eastern
Motor
Court Site
A building, of approximately 76,000 to
91,000 square feet, which will include
luxury apartments and commercial
office/retail space designed so that in the
future it could be in whole, or in part,
converted to hotel rooms and/or hotel
amenities.
Fall 2017
Hotel A four story hotel, of approximately 44,000
square feet, which will include parking.
TBD
3) Council and/or CRC Action Items
ACTION ITEM CITY COUNCIL CRC
None at this time.
4) CRC Commitments
No commitments have been formalized.
PROJECT UPDATES
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 9
THE MEZZ/ MONON LOFTS
• Developer Partner: Anderson Birkla
• Allocation Area: City Center
• Project Summary:
• Use: Primary Residential. 42 residential units with 12,000 square feet of office.
• Total project budget: $7.7mm
• Secured Tenants: Fat Atom, Vocare, Anderson Birkla
Figure 2 Image provided by Anderson Birkla
• Anticipated Project Schedule
Office Move In August, 2014- Seeking 1st floor COM of Monon
Lofts building soon.
Residential Move In October, 2014
Project complete December, 2014
PROJECT UPDATES
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 10
• Mezz Building (3rd Avenue)
1) Project Status – under construction
a) Framing is complete.
b) MEPS - Plumbing under slab are complete.
c) Roof install is complete.
d) Tyvek, Windows, & doors are 90% complete.
2) Council and/or CRC Action Items
ACTION ITEM CITY COUNCIL CRC
See next section
3) CRC Commitments
Provide parking spaces on 3rd Ave and streetscape on the west and south side of the building and
relocate street utilities.
a) Budget
Design/ Engineering $8,900 for Utility Relocation
Approved and funded with TIF
monies.
Site Construction $67,021
Invoices are expected to be paid
October/November.
Utility Relocation
$250,000
Waiting on Duke Energy to
complete easement work and
submit work order. Invoices are
expected to be paid in December.
b) Design Consultant: American Structurepoint
c) Construction Contractor: Calumet Civil Contractors/ Duke Energy
d) CRC Commitment Schedule
Design % Complete 100%
Proposed Construction Start Date August 2014/ September for site work
Anticipated Project Completion September 2014/ November for site work
PROJECT UPDATES
July 25, 2014 CRC Report for August 4, 2014 City Council Meeting Page | 11
• Monon Lofts Building (Monon side)
1) Project Status – under construction
a) Framing is complete.
b) Tyvek, Windows, Doors are complete.
c) Building 2 MEP - Plumbing under slab rough is complete. Fire Suppression is complete.
d) Building 2 roof is complete
2) Council and/or CRC Action Items
ACTION ITEM CITY COUNCIL CRC
Create an easement in the Tarkington
Garage to allow for an emergency access
hallway connecting the parking area and
the new building.
CRC to finalize in August
Issue for construction of the Monon
connecting path
August
Bids Received for walks and landscaping August, approve
contract
August, select contractor
3) CRC Commitments
Site Improvements, Monon Connection path, Small pocket park (by developer)
a) Budget
Design/ Engineering Not to exceed $75,000
Construction
$310,000
Low-bid for site work was
$206,070 + alternates.
Monon connection not
issued yet.
b) Design Consultant: American Structurepoint
c) CRC Commitment Schedule
Design % Complete 100%.
Proposed Construction Start Date September 2014
Anticipated Project Completion November 2014
-One enclosure-