HomeMy WebLinkAbout070714 Report to CouncilCARMEL REDEVELOPMENT COMMISSION
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 1
Carmel Redevelopment Commission
STRATEGIC HIGHLIGHTS
• The CRC approved a mid-year budget at the June meeting.
• CRC and the Clerk Treasurer’s office have established a common understanding of roles and
responsibilities to act accordingly to SEA 118.
FINANCIAL HIGHLIGHTS
May Beginning Balance $ 1,210,704
May Revenues $ 30,584
May Expenditures $ 1,071,211
May Ending Balance $ 170,077
OPERATING HIGHLIGHTS
• The Department of Redevelopment has hired a summer intern. The intern’s primary
responsibilities will focus on inventory and file organization.
LOOKING AHEAD
• The CRC received responses to the Request for Proposals for the property located at 7th Street NE
and 2nd Avenue NE on June 18, 2014. The CRC rejected the bid given that the minimum purchase
price stated in the RFP was not met in the one submittal received. The submittal was from Old
Town Development. Over the next month the CRC staff will coordinate with Council on a mutually
agreeable sale price per the Amended Resolution passed at Council. After 30 days, the CRC will
engage in further negotiations with interested parties regarding this site.
Corrie Meyer, AICP, RLA, LEED AP
Director
Carmel Redevelopment Commission/Department
June 20, 2014
Prepared for David Bowers and Brad Meyer
FINANCIAL STATEMENT
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 2
Financial Statement
MAY MONTH-END FINANCIAL BALANCE
Ending Balance without Restricted Funds $ 170,077
Ending Balance with Restricted Funds $2,173,036
SUMMARY OF CASH
For the Month Ending May 31, 2014
DESCRIPTION ACTUAL BUDGET VARIANCE
(OF JAN. BUDGET)
Cash Balance 5/1/14
1101 Cash $501,011.88 $501,011.88 -
1110 TIF 709,692.48 709,692.48 -
Total Cash $1,210,704.36 $1,210,704.36 -
Receipts
1101 Cash $30,583.24 $210,136.14 $(179,552.90)
1110 TIF 0.82 - 0.82
Developer Payments - - -
Total Receipts $30,584.06 $210,136.14 $(179,552.08)
Disbursements
1101 Cash $371,210.98 $427,506.00 $56,295.02
1110 TIF 700,000.00 700,000.00 -
Total Disbursements $1,071,210.98 $1,127,506.00 $56,295.02
1101 Cash $160,384.14 $283,642.02 $(123,257.88)
1110 TIF 9,693.30 9,692.48 $ 0.82
Cash Balance 5/31/14 $170,077.44 $293,334.50 $(123,257.06)
Total Usable Funds $170,077.44 $293,334.50 ($123,257.06)
FINANCIAL STATEMENT
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 3
FUND BALANCES AND OUTSTANDING RECEIVABLES
As of 5/31/14
Restricted Funds
Energy Center Reserve $1,001,502
Civic Rent Reserve 1,001,457
Sub-total: 2,002,959
Cash (as seen in Summary of Cash table)
TIF 9,693
Operating 160,384
Sub-total: 170,077
Total Funds $2,173,036
Outstanding Receivables
Energy Consumption Payments (1) 31,385
Keystone Group (Bond Enhancement) 172,753
Total Outstanding Receivables $204,138
(1) Amounts due reflects months April – June 2014 for the Tarkington
and Office Building One. REI Real Estate Services, LLC acts as property
manager on behalf of the CRC and collects the Energy Consumption
Payments to be forwarded on to the CRC.
STATEMENT OF CHANGES IN EQUITY
MONTH END: MAY 2014
DESCRIPTION REVENUE EXPENSES
Total Receipts (Non-Operating) $1
Total Receipts (Operating): $30,583
Expenditures (Non-Operating) $898,045
Expenditures (Operating) $173,166
FINANCIAL UPDATE
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 4
Financial Update
TIF REVENUE AND DEBT
As of the approved June budget, projected TIF Revenue was estimated at $17,532,007.
Two bond debt payments were made in June and the remainder of the semi-annual payments will be made in
July. The second set of bond payments will be made in December 2014. Below are the anticipated payments
based on the revised CRC budget, which was approved June 18, 2014;
MONTH TOTAL
June 2014 $2,812,228
July 2014 $5,985,887
December 2014 $8,774,841
GOING CONCERN
The CRC is managing expenditures to maintain a balanced budget in anticipation of lower TIF Revenue. H.J.
Umbaugh has issued a draft report updating TIF information. Drafts have been issued to the Council
Finance Committee Chair and Clerk Treasurer for review. A presentation of their final report will be made
publicly at the July 16 CRC public meeting.
TAKEAWAYS
• Month-end balance is positive.
• The CRC adopted an amended budget at the June 18 meeting. This budget will guide the CRC over
the next six months.
PROJECT UPDATES
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 5
Project Updates
CITY CENTER
• Developer Partner: Pedcor Companies
• Allocation Area: City Center
• Project Summary:
• Use: Mixed-Use
Figure 1 City Center Master Plan, provided by Pedcor City Center Development Company
• Phase 1 – complete
1) Apartments - Demand for the apartments remains strong, which supports the occupancy and rental
rates. Current occupancy is at 95%.
2) Retail – Currently, Pedcor has leases on 91% of the total 79,570 in LSF. The remaining 9% (the old
Mangia, Holy Cow, & Sports Authority locations) of unleased space have future tenants for them, and
are working through the space planning process. Pedcor anticipates to be 100% leased by fall of
2014.
PROJECT UPDATES
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 6
Provided by Pedcor City Center
Dev. Co. 1
• Nash Building/ Parcel 73
1) Project Status – under construction
a) The Nash underground parking garage is 88% complete and currently
on budget. The Nash Building roof trusses and decking are being
installed while the framing, electrical/plumbing rough in has started.
The project is on budget and remaining on schedule, with an
anticipated completion date of fall 2014. Approximately half of the
9,000 sf of the retail space has been leased with strong prospects for
the remaining commercial space.
1) Council and/or CRC Action Items
ACTION ITEM CITY COUNCIL CRC
Issue CRC site work project
for public bid
June
2) CRC Commitments
Provide streetscape along Rangeline Road.
a) Budget
Design/ Engineering $5,000 (majority of contract
pd. in 2013)
Construction $100,000
b) Design Consultant: American Structurepoint
c) CRC Commitment Schedule
Design % Complete 100%
Anticipated Project out-for-bid June 2014
Proposed Construction Start Date August 2014
Anticipated Project Completion October 2014
PROJECT UPDATES
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 7
• Phase 2
1) Project Status – designs are schematic and construction has not started.
a) Project initiation discussions are continuing between Pedcor and the CRC. The CRC is
evaluating proposed partnership opportunities.
2) Proposed Construction/Use Sequence
PROJECT USE START DATE DESIGN RENDERINGS,
PROVIDED BY PEDCOR
Garage
East
A three to four story parking structure with
approximately 470 to 625 parking spaces,
which will include up to approximately
28,000 square feet of luxury apartments and
commercial retail/office space.
Fall 2014
(garage only)
Baldwin/
Chambers
A four story building, of approximately
64,000 square feet, which will include
luxury apartments and commercial
retail/office space. Pedcor is currently
working with four commercial businesses
who will occupy approximately 14,000 sf of
the commercial space.
Fall 2014
Holland A five story building, of approximately
63,000 square feet, which will include
luxury apartments and commercial
retail/office space.
Fall 2014
Playfair A five story building, of approximately
63,000 square feet, which will include
luxury apartments and commercial
retail/office space.
Fall 2015
Garage
Retail
See Garage East note above. Fall 2015
Pedcor
Office 5
A two story building, of approximately
20,000 to 25,000 square feet, which will
include office space.
Fall 2015
PROJECT UPDATES
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 8
Kent A three story building, of approximately
111,000 square feet of luxury apartments.
Fall 2015
Wren A seven story building, of approximately
88,000 square feet, which will include
luxury apartments and commercial
office/retail space.
Fall 2016
Windsor A four story building, of approximately
64,000 square feet, which will include
luxury apartments and commercial
office/retail space.
Fall 2017
Eastern
Motor
Court Site
A building, of approximately 76,000 to
91,000 square feet, which will include
luxury apartments and commercial
office/retail space designed so that in the
future it could be in whole, or in part,
converted to hotel rooms and/or hotel
amenities.
Fall 2017
Hotel A four story hotel, of approximately 44,000
square feet, which will include parking.
TBD
3) Council and/or CRC Action Items
ACTION ITEM CITY COUNCIL CRC
None at this time.
4) CRC Commitments
No commitments have been formalized.
PROJECT UPDATES
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 9
THE MEZZ/ MONON LOFTS
• Developer Partner: Anderson Birkla
• Allocation Area: City Center
• Project Summary:
• Use: Primary Residential. 42 residential units with 12,000 square feet of office.
• Total project budget: $7.7mm
• Secured Tenants: Fat Atom, Vocare, Anderson Birkla
• Manpower count has remained 6-16 men daily for both buildings.
• Street cleaners have been hired to sweep weekly or as needed.
• Duke Energy is engineering power for both buildings. We need power to begin elevator installation.
Figure 2 Image provided by Anderson Birkla
PROJECT UPDATES
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 10
• Anticipated Project Schedule
Office Move In August 1, 2014
Residential Move In October, 2014
Project complete December, 2014
• Mezz Building (3rd Avenue)
1) Project Status – under construction
a) Framing is 90% complete.
b) MEPS - Plumbing under slab rough is 90%
completed.
c) Roof install is 90% complete.
d) Tyvek, Windows, & doors are 70%
complete.
2) Council and/or CRC Action Items
ACTION ITEM CITY COUNCIL CRC
Issue CRC site projects for
public bid
June
3) CRC Commitments
Provide parking spaces on 3rd Ave and streetscape on the west and south side of the building and
relocate street utilities.
a) Budget
Design/ Engineering $8,900 for Utility Relocation
Approved and funded with TIF
monies.
Site Construction $67,021
Project is TIF funded. Invoices are
expected to be paid May-August.
Utility Relocation $250,000
Project is TIF funded. Invoices are
expected to be paid May-October.
b) Design Consultant: American Structurepoint
c) Construction Contractor: Calumet Civil Contractors/ TBD
PROJECT UPDATES
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 11
d) CRC Commitment Schedule
Design % Complete 100%
Anticipated Project out-for-bid Complete/ June for site work
Proposed Construction Start Date July 2014/ August for site work
Anticipated Project Completion September 2014/ October for site work
• Monon Lofts Building (Monon side)
1) Project Status – under construction
a) Framing is 98% complete.
b) Tyvek, Windows, Doors are 90% complete.
c) 4 Spiral stairs are delivered and in place in the
units. 8 more remain to be delivered.
d) Concrete cutting of the parking garage walls is
completed.
e) Building 2 MEP”S - Plumbing under slab rough is 90% completed. Plumbing 2nd rough has
started. Electrical is to begin next week, Fire Suppression is being installed next week. HVAC is
to begin next week.
f) Building 2 roof is 90% completed.
g) Miscellaneous Structural steel items will be completed next week.
h) Materials received in the warehouse are: Plumbing, lighting fixtures, tubs, marble vanity sinks,
windows and screens and wood for the spiral stairs.
2) Council and/or CRC Action Items
ACTION ITEM CITY COUNCIL CRC
Create an easement in the Tarkington
Garage to allow for an emergency access
hallway connecting the parking area and
the new building.
CRC to finalize in July
Issue CRC site work projects for public bid July
3) CRC Commitments
Monon Connection path, Small pocket park, Monon upgrades
a) Budget
Design/ Engineering Not to exceed $75,000
Construction $310,000
PROJECT UPDATES
June 20, 2014 CRC Report for July 7, 2014 City Council Meeting Page | 12
b) Design Consultant: American Structurepoint
c) CRC Commitment Schedule
Design % Complete 50%.
Anticipated Project out-for-bid July 2014
Proposed Construction Start Date September 2014
Anticipated Project Completion November 2014
-End of report-