Hi Lisa – please add these Engineering Dept. review comments to the file, to laser fiche. Thank you!
Angie Conn,
Planning Administrator
From: Duncan, Gary R
Sent: Wednesday, October 01, 2014 3:17 PM
To: Matt Huffman
Cc: Barnes, David R; Conn, Angelina V; Glaser, Fred J; Greg R. Hoyes; Jordan, Alex; Thomas, John G; Mishler, Nicholas F
Subject: RE: Docket No. Assignment: 230 1st Ave NE (#14090001 SDR)
Thanks so much Matt.
Comment 1. Thank you for the calculations for the amount of impervious area. Our standards are associated with total
land disturbance (including grading, trenching for utilities/laterals, etc.) Do you think you will be over 0.25-acres with all
construction activity? Are there areas of the site that will not be affected and could be “roped off” as it were to ensure
that area is not disturbed by construction?
Comments 2, 3 have been satisfactorily addressed.
Comment 4. See comment 12 a-d below.
Comments 5-9 have been satisfactorily addressed.
Comment 10. See comment 12 a-d below.
Comment 11 has been satisfactorily addressed.
Comments 12 a-d. Please provide a letter requesting approval from the BPW for lane restrictions, sidewalk closure,
driveway modification, and open pavement cuts. You will also need a variance for the sump pump line to be in the right-
of-way as well as a consent-to-encroach.
Comment 12e. Is irrigation proposed within the right-of-way?
Comment 13a. The plan indicated the sump pump line in the right-of-way but is not specific as to what the line will
discharge? Is there and existing curb inlet?
Comments 13b, 13c, 14 have been satisfactorily addressed.
Comment 15. My understanding is that the site plan has been revised and that the structure is not 2.5-feet from the
right-of-way line?
Additional comments based on this review:
Please confirm with the Hamilton County Surveyors Office that the non-enforcement agreement for the legal drain
includes the installation of the sanitary and water services, the sump pump discharge, the walkway and the driveway.
Thanks so much,
Gary
From: otdgmatt@gmail.com \[mailto:otdgmatt@gmail.com\] On Behalf Of Matt Huffman
Sent: Tuesday, September 16, 2014 2:52 PM
To: Duncan, Gary R
Subject: Re: Docket No. Assignment: 230 1st Ave NE (#14090001 SDR)
1
Gary,
Please see responses below:
1. Ok
2. Yes
3. No paving. There is a existing alley
4. We will be replacing any damaged existing sidewalk caused by construction
5. No new storm piping
6. We will wrap the construction entrance
7. We have submitted for a right of way permit
8. We will have a lined dumpster
9. Driveway will conform to the City of Carmel standards.
10. All easements are on the plot plan
11. a. If necessary before the work is performed we will
b. It is possible, we will use flag men.
c. We will be building a new drive off of the alley way
d. Possible
e. None at this time
12. a. None
b. We will use splash pads
13. Our contractor will connect to the storm at the curb
14. Thank you for your recommendation
Matt Huffman
Old Town Design Group
317-605-8796
This message may contain information that is privileged, proprietary, work product and/or otherwise
confidential. If you are not an intended recipient, use and disclosure of this message are prohibited. If you
received this transmission in error, please notify the sender by reply e-mail and delete the message and any
attachments.
On Fri, Sep 12, 2014 at 3:01 PM, Duncan, Gary R <gduncan@carmel.in.gov> wrote:
Good afternoon! I have reviewed the submitted plan and have the following comments:
1.The lot appears to be right at 0.25-acres…as such, detention and post construction storm water quality
measures are not required.
2.Please confirm that the FFE labeled is 15-inches above the roadway
3.It appears that the existing alley is paved and that no paving of the alley is proposed with this project.
4.Please confirm if new sidewalk is being constructed with this project.
5.Please confirm if any new storm piping is being constructed/installed with this project.
2
6.Thank you for providing the erosion and sediment control plan. Please wrap the silt fence back into the site
on each side of the construction entrance a minimum of two sections of the silt fence being used.
7.Please check with Fred Glaser as to the need for a right-of-way permit and bond for construction access
from the City right-of-way.
8.Will there be a concrete washout on-site or will equipment and tools be washed into a lined dumpster?
9.Is a new driveway proposed? If so, the portion of the driveway within the right-of-way shall conform to
City standards in all respects.
10.Please confirm that all existing and proposed easements are indicated on the plot plan.
11.Please confirm the need for any of the following, which require approval by the Board of Public Works and
Safety:
a.Any road or lane closures or restrictions (I expect these may be needed for new utility
services)
b.Any sidewalk closures (I expect that these may be needed for new utility services and the
sump pump connection)
c.Reconstructing or modifying the existing drive or building a new drive
d.Any open pavement cuts for utility services or other needs.
e.Irrigation or other site improvements within an easement or right-of-way.
12.So that we can identify conformance to the Property Maintenance Code, please indicate the following on the
plot plan, as applicable:
a.Pool or hot tub filter pipe discharge points
b.Roof drain piping discharge points. If splash pads will be used, please indicate as such.
13.Thank you for showing the sump pump location. To what is this discharge being connected.
14.
The property owner is responsible for all damage to the improvements in the right-of-way resulting from the
project, including the alley. It is recommended that the property owner or designee inspect the improvements in
the surrounding right-of-way prior to the start of construction.
Please let me know if you have any questions.
Thanks so much,
3
Gary
Gary R. Duncan, Jr., PE
Assistant City Engineer
City of Carmel
Department of Engineering
One Civic Square
Carmel, IN 46032
(317) 571-2441
(317) 571-2439 (fax)
gduncan@carmel.in.gov
Please consider the environment before printing this e-mail
From: Conn, Angelina V
Sent: Thursday, September 04, 2014 1:56 PM
To: Keesling, Rachel M; Barnes, David R; Blanchard, Jim E; Boone, Tiffany; Lopez, Alexia K; Duncan, Gary R; Haney,
Douglas C; Hollibaugh, Mike P; 'John Molitor'; Kashman, Jeremy M; Kass, Joslyn; Keeling, Adrienne M; Littlejohn, David
W; Lux, Pamela K; Maki, Sue; Martin, Candy; Mindham, Daren; Mishler, Nicholas F; Motz, Lisa; Speth, Nichole M; Stewart,
Lisa M; Thomas, John G; Tingley, Connie S; Boone, Tiffany; Jordan, Alex; Crediford, Maggie; 'Greg Ilko'
Cc: 'matt@oldtowndesigngroup.com'; 'otdgmatt@gmail.com'; 'justin@oldtowndesigngroup.com'
Subject: Docket No. Assignment: 230 1st Ave NE (#14090001 SDR)
230 1st Ave NE – Etgen Residence (SDR).
I have issued the necessary docket number for (Plans are
attached.) It is the following:
Docket No. 14090001 SDR: 230 1st Ave NE – Etgen Residence.
The applicant seeks site plan & design review approval for a new house with attached garage. The site is located
st
at 230 1 Ave NE. It is zoned R-3/Residence within the Old Town Overlay Character Subarea. Filed by Matt
Huffman of The Old Town Design Group, on behalf of Gary & Carrie Etgen, owners.
Matt can be contacted at 317-605-8796.
4
SDR Application Filing Fee Due = $156.50
Petitioner, please note the following:
This item does not require review by the Technical Advisory Committee.
1.
Mailed and Published Public Notice does not need to occur.
2.
Proof of Notice is not needed.
3.
The Filing Fee must be paid before issuance of the Letter of Decision. (Checks can be made out to
4.
the City of Carmel.)
This Item will be reviewed administratively.
5.
The Planning Department’s review comments will be issued soon; in the meantime, please submit a
6.
larger site plan.
Angie Conn, Planning Administrator
City of Carmel Planning & Zoning Division