Midwest Constructors; Mezz site work change order #2; $10,436 •
CITY OF CARMEL
TO: Midwest Constructors,LLC CONTRACT CHANGE ORDER NO.: Z
2916 Bluff Road,Suite D DATE: 0-1-lµ
Indianapolis,IN 46225 PROJECT NAME: J1 e z 7 Si-FP wppk
CITY REQ.NO.:
CITY PO NO.:
CITY PO DATE:
I. You are directed to make the following changes in this Contract:
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+)OR(-)DAYS
Construction of American Way $10,436.00
temporary drive
(less deducts from original contract)
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $ 238,814.00
Contract Price will be increased/decreased by this Change Order $ 10,436.00
New Contract Price including this Change Order $ 249,250.00
Contract Time Prior to this Change Order NSA
Net increased/decreased resulting from this Change Order_,l /4 Days
Current Contract Time including this Change Order T B D
The Above Changes Are The Above Changes are
Approved: Approved:
11 k 1r„ll�iI;r1I
Come Meye William v'. e.;
Executive Director, RC President,CRC
MIDWE T
CONSTRUCTORS
September 30,2014
Carmel Redevelopment Commission
Attn: Ms.Corrie Meyer
30 W. Main St.,Suite 220
Carmel ,IN 46032
RE: Parcels 7C4 and 7C9
Change Request#2
Dear Ms. Meyer
Please add the total sum of $10,436 to our contract amount per the agreed upon additions and deletions
listed below:
American Way Temporary Drive $25,506
Deletion of water detail(per 0100) -$15,070
Total Add $ 10,436
Respectfully,
Midwest Constructors,LLC
Tim Golden
Project Manager
cc: File