HomeMy WebLinkAboutMidwest Constructors, LLC Change Order #2 - Increase $3,410 CITY OF CARMEL
r
TO: . Midwest Constructors,LLC CONTRACT CHANGE ORDER NO.:
2916 Bluff Road,Suite D DATE:
Indianapolis,IN 46225 PROJECT NAME: A1&S 4 S j P work
CITY REQ.NO.:
CITY PO NO.:
CITY PO DATE:
I. You are directed to make the following changes in this Contract:
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+)OR(-)DAYS
Concrete sidewalk/stoop at South end $3,410.00
Additional 53's and Skidsteer for subgrade
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $ 235,816.00
Contract Price will be increased/decreased by this Change Order $ 3,410.00
New Contract Price including this Change Order $ 239,226.00
Contract Time Prior to this Change Order A//,l
Net increased/decreased resulting from this Change Order N/1/4 Days
Current Contract Time including this Change Order II/A
The Above Changes Are The Above Changes ar:
Approved: Approved:
62:04,41,
f Vati
Corrie Meyer William Ha„rer,1.
Executive Director,C President, RC
ANIL MIDWEST
CONSTRUCTORS
January 20,2015
Carmel Redevelopment Commission
Attn:Mrs.Corrie Meyer
30 W.Main St.,Suite 220
Carmel,IN 46032
RE: Parcel 73 Nash Building
Change Request
Dear Mrs.Corrie Meyer
Please add the total sum of $ 3,410 to our contract amount per the attached time and material
work agreement. Our breakdown is as follows:
C200 Concrete Sidewalk/Stoop at South End "$ 2,560.00
Additional 53's and Skidsteer for Subgrade $ 850.00
Total $ 3,410.00
Respectfully,
Midwest Constructors,LLC
Michael Jacobs
Project Manager