HomeMy WebLinkAboutE&B Paving/ENG/CO 3/Main Street ImprovementsTO: Tiffany Boone
Project Manager
City of Carmel Indiana
One Civic Square
Carmel, IN 46032
CITY OF CARMEL
CONTRACT CHANGE ORDER NO.: 3
DATE: February 16, 2015
PROJECT NAME: Main Street Improvements
CITY REQ. NO.:
CITY PO NO.:
CITY PO DATE:
14 -06
I. You are directed to make the following changes in this Contract:
Item # 323, 324, and 325 - Decorative sign posts
Item # 42, 105, and 223 - Deduct for cost of original sign post items from contract
SCHEDULED ADJUSTMENT
ITEM AMOUNT ( +) OR ( -) DAYS
II. The following referenced Documents further describe the changes outlined in Paragraph I,
and are to be considered a part of this Change Order: R.F.P.: W.D.C. NO.:
Other:
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order
Contract Price will be increased/decreased by this Change Order
New Contract Price including this Change Order
Contract Time prior to this Change Orde 258 Days 6/1/2015 Completion Date
Net increased /decreased resulting from this Change Order 0 Days
Current Contract Time including this Change Orde 258 Days 6/1/2015 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
$ 4,398,095.94
$ 2,880.02
$ 4,400,975.96
The Above Changes Are
Recommended
American Structurepoint, Inc.
ENGINEER
7260 Shadeland Station
Address
Indianapolis, 6256
C tate/Zip
By.
Phone: I7-7to-55'1
Zil co-115—
The Above Changes Are
Accepted
E &B
CONTRACTOR
17042 Middletown Avenue
Address
Noblesville, IN 46060
City/State/Zip
Approved
/ 4
By: .ta ►�c, �/
Date:
Phone: 3/7- 777.. f/3'Z
Date: Z 1 i
s Brain Mayor,
Mary
Lor' Wa • , Member
ter
iana Cordray, Clerk- reasurer
Date: L3/k //S
Contract Modification
City of Carmel
2/16/2015 9:17 AM
Field Manager 4.5a
Contract: 2014.00444, Main Street Improvements
Cont. Mod.
Number
3
Revision
Number
Cont. Mod.
Date
2/16/2015
Net Change
$2,880.02
Awarded Contract Amount
$4,398,095.94
Route
Contract Location
Carmel, Indiana
Short Description
Covers Parts 1A, 1B and 2
Description of Changes
1. Item # 323, 324 and 325 - Decorative sign posts - Work was a scope change request by the City of Carmel so that new
sign posts match existing decorative streetscape items used on City infrastructure. Posts are standard to the Indiana
Department of Transportation specifications, and will be powder coated according to City of Carmel specifications. Scope is
relative to all three parts of the project so unit quantity reflects estimated quantity for each project part. A deduction of the
original item cost is included and also reflective of quantities' required for each project part.
Increases / Decreases
Project: IN2014.00444, Main Street Improvements
Category: 1A, Sta. 3 +60.00 to 9 +23.12 Line "F1"
Item Description Item Code
Sign Post, Square, Type 1, Reinforced Anchor _0318
Base
Reason: Scope Change
Prop.Ln. Item Type Unit Quantity Chg.
0042 ORIGINAL LFT - 205.000
Unit Price
12.00000
CNST
Dollar Value
$- 2,460.00
Subtotal for Category 1A: $- 2,460.00
Category: 1B, Sta. 9 +23.12 to 16 +44.35 Line "F1"
Item Description Item Code Prop.Ln. Item Type Unit Quantity Chg. Unit Price Dollar Value
Sign Post, Square, Type 1, Reinforced Anchor _0318 0105 ORIGINAL LFT - 26.000 12.00000 $- 312.00
Base
Reason: Scope Change
Subtotal for Category 1B: $- 312.00
Category: 2, East of U.S. 31 Interchange
Item Description Item Code Prop.Ln. Item Type Unit Quantity Chg. Unit Price Dollar Value
Sign Post, Square, Type 1, Reinforced Anchor _0318 0223 ORIGINAL LFT - 458.000 12.00000 $- 5,496.00
Base
Reason: Scope Change
Subtotal for Category 2: $- 5,496.00
Subtotal for Project IN2014.00444: $- 8,268.00
Contract: _2014.00444 Cont. Mod.: 3
Page 1 of 2
Contract Modification
City of Carmel
2/16/2015 9:17 AM
FieldManager 4.5a
New Items
Project: IN2014.00444, Main Street Improvements
Category: 1A, Sta. 3 +60.00 to 9 +23.12 Line "F1"
Item Description
Sign Post - Black (Item #42)
Reason: Scope Change
Item Code Prop.Ln. ItemType Unit Proposed Qty. Unit Price Dollar Value
0522 0323 CHANGE LFT 205.000 16.18000 $3,316.90
Subtotal for Category 1A :- $3,316.90
Category: 1B, Sta. 9 +23.12 to 16 +44.35 Line "F1"
Item Description Item Code Prop.Ln. ItemType Unit Proposed Qty. Unit Price Dollar Value
Sign Post - Black (Item #105) _0526 0324 CHANGE LFT 26.000 16.18000 $420.68
Reason: Scope Change
Category: 2, East of U.S. 31 Interchange
Item Description
Sign Post - Black (Item #223)
Reason: Scope Change
Subtotal for Category 1B: $420.68
Item Code Prop.Ln. ItemType Unit Proposed Qty. Unit Price Dollar Value
_0527 0325 CHANGE LFT 458.000 16.18000 $7,410.44
(Signature)
Z 1L 1
(Date)
Subtotal for Category 2: $7,410.44
Subtotal for Project 1N2014.00444: $11,148.02
7 1 r
(D te)
City of Carmel
(Date)
Contract: _2014.00444 Cont. Mod.: 3
Page 2 of 2
CITY OF CARMEL
14 -06
MAIN STREET IMPROVEMENTS
CHANGE ORDER #3 ITEM DESCRIPTIONS
1. Item #323/ 324/ 325 — Decorative sign posts — Work was a scope change request by the City of
Carmel so that new sign posts match existing decorative streetscape items used on City
infrastructure. Posts are standard to the Indiana Department of Transportation specifications,
and will be powder coated according to City of Carmel specifications. Scope is relative to all
three parts of the project so unit quantity reflects estimated quantity for each project part. A
deduction of the original item cost is included and also reflective of quantities' required for
each project part.
C °Q Ii m a one
World -Class Solutions at a Local Level'
ADD TDONAL WO
To: City of Carmel
One Civic Square
Carmel IN 46032
Attn: Tiffany Boone
K AU HORlZAT @O
Phone: 317 -571 -2678
Fax:
Project: Carmel - Main St 14-06
Location: Carmel - Main St, e and w of US 31
City: Carmel
Date: 12/11/2014
Job No: 02143299
The following quoted prices are for additional work that is not a part of our original contract scope of work:
DESCRIPTION:
Per your request, the attached pricing is extra work done at the roundabout of Illinois St and Main St roundabout
If you need any additoinal information, please let me know.
Item # Description Quantity Unit Unit Price Extension
EWA Sign Post - Black (Item #42, 105 and 223) 689.00 LFT $ 15.00 $ 10,335.00
original price was $12.00 /LFT
Subtotal $ 10,335.00
10% of first $3,000.00 $ 300.00
7% of remainder $ 513.45
TOTAL $ 11,148.45
PRICE PER LFT FOR NEW BLACK SIGN POST $ 16.18
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date: Owner or Contractor Signature
(Authorized Representative)
We hereby agree to furnish labor and materials - complete in accordancgwith th bove specifications, at the above stated price.
,.........?
E & B Paving, Inc., Authorized Signature
c--� Date: 12/11/14
THIS IS ADDITIONAL WORK AUTHORIZATION MO. 3
AN EQUAL OPPORTUNITY EMPLOYER
17042 Middletown Ave. • Noblesville, IN 46060
PHONE: 317.773.4132 • FAX: 317.773.4137
www.ebpaving.com
ASPHALT ANCONCQE�ljE GONATAC7,ORS
MORPHEY CONSTRUCTION, INC.
EXTRA WORK AGREEMENT DETAIL
DATE: 9-Dec-14
CONTRACT: EB Main St.
FORCE ACCOUNT /EXTRA WORK FOR: Install black sign post
Per each. 19'
PAGE 1 OF2
LABOR 109.04(a)
WEEK ENDING:
EMPLOYEE
CRAFT
HOURS
RATE
TOTAL
Ryan Davis
laborer
0.25
33.15
8.29
Leo Flores
laborer
0.25
23.62
5.91
Eric Voight
laborer
0
25.62
0.00
John Henry
laborer
0
25.62
0.00
Jeff Hubbard
operator
r 0
30.75
0.00
Chad Ash
operator
0.,
31.50
0.00
Kyle Bowles
laborer
0
25.62
0.00
Jirn Hardy
laborer
0
28.50
0.00
FRINGES
LABORERS
OPERATORS
CARPENTERS
TEAMSTERS
TOTAL LABOR:
FICA: 7.7 % x LINE (1):
0.5 FIRS x 12.41 =
0 HRS x 15.31 =
HRS x
HRS x =
HRS x =
14.19 (1)
6.21
0.00
1:09 (2)
TOTAL FRINGES: 6.21 (3)
WORKMENS COMPENSATION: 4.2 '% X LINE (1) 0.60 (4)
BODILY INJURY INSURANCE: 6.5 % X LINE (1) 0.92 (5)
PROPERTY DAMAGE INS.: 6.5 % X LINE(1) 0.92 (8)
STATE UNEMPLOYMENT: 4.2 % X LINE (1) 0.60 (7)
FEDERAL UNEMPLOYMENT: 0.08 % X LtNE (1) 0.11 (8)
TRAVEL ALLOWANCE OR SUBSISTENCE (NOTE #3): 0 (9)
TOTAL LINES 1,2,3,4,5,6,7,8, & 9 : 24.64 (10)
10% x LINE (10): 2.46 (11)
GRAND TOTAL LABOR LINES (10) + (11): 27.11 (12)
MATERIALS 109.04 (c )
MATERIALS WEEK ENDING: SEE ATTACHED DETAIL
(ATTACH COPIES OF INVOICES)
TOTAL MATERIALS: 80.00 (18)
10% x LINE (18): 8.00 (19)
GRAND TOTAL MATERIALS LINE (18) + (19): 88.00 (20)
EQUIPMENT 109.04 (d )
PAGE 2 OF 2
CONTRACTOR OWNED EQUIPMENT
MODEL AND YEAR
TOTAL
HOURS
BLUE BOOK RA
MONTHLY/ 176
ADJUSTED RATE
AGE AND REGION
EXTENSION
Ford F350 OW truck
0.5
15.00
7.50
Dump Truck
0
30.00
0.00
Trencher
0
25.00
0.00
Bucket Truck
0
25.00
0.00
Air Compressor
0.5
10.00
5.00
Crane
0
40.00
0.00
TOTAL CONTRACTOR OWNED EQUIPMENT: 12.50 (21)
RENTED EQUIPMENT ( ATTACH DAILY COPIES OF INVOICES): (22)
FUEL, LUBRICANTS, AND TRANSPORTATION COSTS: 20.00 (23)
TOTAL LINES (21) + (22) + (23) : 32.50 (24)
10% x LINE (24): 3.25 (25)
GRAND TOTAL EQUIPMENT LINES (24) + (25): 35.75 (26)
SUBCONTRACTS 109.04 (f )
SUBCONTRACTS WEEK ENDING:
DESCRIPTION
None
AMOUNT
TOTAL SUBCONTRACT WEEK ENDING:
TOTAL SUBCONTRACT TO DATE:
10% x LINE (28) $3000.00 OR LESS:
7% x LINE (28) OVER 3000.00:
GRAND TOTAL SUBCONTRACT LINES (28) + (29) + (30):
0 (27)
0 (28)
0 (29)
0 (30)
0 (31)
TOTAL LINES (12), (17), (20), (26), & (31): 150.86 (32)
% OF BOND RATE BASED UPON LINE 32: NA (33)
10% x LINE (33) 0 (34)
TOTAL EXTRA WORK LINES (32) + (33) + (34): 150.86 (35)
$15,00 per f