HomeMy WebLinkAboutMidwest Contractors/CRC/CO 4/247.17/The MezzCITY OF CARMEL
TO: Midwest Constructors, LLC CONTRACT CHANGE ORDER NO.:
2916 Bluff Road, Suite D DATE:
Indianapolis, IN 46225 PROJECT NAME: Me 7 Z S! e work
CITY REQ. NO.:
CITY PO NO.:
CITY PO DATE:
I. You are directed to make the following changes in this Contract:
ITEM AMOUNT
Change Amelancheir canadensis $247.17
trees from 2" clump to 2" single stem
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $ 250307.00
Contract Price will be increased /decreased by this Change Order $ 247.17
New Contract Price including this Change Order $ 250,954.17
Contract Time Prior to this Change Order VA
Net increased /decreased resulting from this Change Order 4!A Days
Current Contract Time including this Change Order
The Above Changes Are
Approved:
c1Meyer
Executive Director, CRC
N/A
The Above Changes are
Approved:
J. L..r:.�...dt/�� ►►
William .1 131er,
President, CRC
SCHEDULED ADJUSTMENT
( +) OR ( -) DAYS
Project:
Becker Project No.:
Submitted to:
Work Description:
MATERIALS
BECKER ANDSCAPE
PROPOSED CHANGE ORDER
Parcel 7C -4, 7C -9
850 S Rangeline Road
Carmel, IN 46032
C140045A
Michael Jacobs
Midwest Constructors, LLC
2916 Bluff Road Suite D
Indianapolis, IN 46225
3749 N. Kitley Avenue
Indianapolis, Indiana 46226
(317) 542-5200
(317) 542-5202 fax
Date: March 9 2015
Work Performed: TBD
Reference No.:
Proposed Change Order Total: $247.17
Cost impact to change the Amelanchier canadensis from 2" clump to 2" single stem
Material Code Size Impact quantity Unit Unit Cost Amount
AME -C - Amelanchier canadensis clump 2" DEDUCT -6 each $ 115.000 $ (690.00)
AME -C - Amelanchier canadensis single stem 2" ADD 6 each $ 150.000 $ 900.00
210.00
Plant Material Warranty
Sales Tax
Overhead and Profit (Material)
SU MMARY
12.0%
7.0%
10.0%
Material Cost Subtotal $
of $
of $ 210.00 $
of $ 224.70 $
Total Material Cost»
14.70
22.47
$ 247.17
Performance & Payment Bond
Overhead & Profit (Bond)
Total Labor Cost » $
Total Resources /Equipment Cost » $
Total Material Cost» $
Total Rental Equipment Cost » $
Total Subcontractor Cost » $
Subtotal $
0.0% of $ 247.17 $
10.0% of $ - $
247.17
247.17
TOTAL PROPOSED CHANGE ORDER» $ 247.17
F Attachments Time Extension (days)
Notes:
trees subject to availability at time of approval
Exclusions: