HomeMy WebLinkAboutEmail to Joseph Sepcic re: tower feature dated 06-11-15
Motz, Lisa
From:Conn, Angelina V
Sent:Thursday, June 11, 2015 10:30 AM
To:'Joseph Sepcic'; Motz, Lisa
Cc:Mishler, Nicholas F; Blanchard, Jim E; Keesling, Rachel M
Subject:RE: Giant Eagle Market District at The Bridges (South Elevation material change
request)
Attachments:generator photo.jpg; Approved, Revised South Elevation_06-11-2015.pdf
Good afternoon, Joe –
Thank you for the additional information and photos. Please accept this email as the Planning/Zoning Department’s
administrative approval of the material change on the two ‘tower’ features on the South Elevation, and this approval is
Conditioned upon you increasing the wall height of the screen wall that surrounds the big green emergency generator. A
copy of the elevations, photo, and email will be placed in the Plan Commission folder Docket No. 14010013 DP – for the
Giant Eagle Market District Grocery Store, at The Bridges.
(Lisa – please add these items to Laser Fiche; I will place paper copies in the file.)
Angie Conn,
AICP | Planning Administrator
City of Carmel Dept. of Community Services
1 Civic Square, 3rd Flr., Carmel, IN 46032
O: 317-571-2417 | Direct: 317-571-2281 | F: 317-571-2426 | W: www.carmeldocs.com
From: Joseph Sepcic \[mailto:JMSEPCIC@dlaplus.com\]
Sent: Tuesday, June 09, 2015 11:56 AM
To: Conn, Angelina V
Subject: Giant Eagle Market District at The Bridges
Importance: High
Ms. Conn,
Attached are comparative images of the South Elevation showing the receiving dock components. We are asking if the
red/brown brick instead of the beige brick would be permissible.
The contractor mistakenly installed the red/brown mix and is nearly complete. Of course, maintaining schedule is
important.
Please let me know your thoughts.
Thanks,
Joe
Joseph M. Sepcic, RA
Principal
DLA+
Architecture & Interior Design
Foster Plaza 9, Suite 200
750 Holiday Drive
Pittsburgh, PA 15220
412.921.4300 ext. 210
jmsepcic@dlastorino.com
www.dlastorino.com
1