HomeMy WebLinkAboutRates - 1988City of
armel
Dorothy J. Hancock
MAYOR
February 23, 1988
Mr. Beau Wilfong
Hamilton Western Utilities
1350 Greyhound Court
Carmel, Indiana 46032
Dear Beau:
Thank you for getting back to us so quickly on the
sewage treatment plant capacity. Regarding your first
question, at this point I would state I am willing to work
with you on setting a schedule of payments as progress is
being made. However, that may mean we would ask for a letter
of credit from your bank to protect the City. I am willing to
discuss this point further with you at a later date.
Your rate for treatment cost is based upon the method of
calculation set up in our contract with you. Your current rate
of $0.64807 per 1000 gallons was revised downward five percent
two years ago, and as we grow, we expect it to continue down as
costs are shared over more customers.
At this point we would expect the actual expansion project
costs to be divided by our increased capacity to establish the
final cost per gallon of additional treatment capacity. There
may need to be some minor adjustments to this but not of major
significance. As Don said he pointed out to you, there would
also be some capital cost for the use of the North-South Inter-
ceptor.
I hope this is of help to you in setting how much capacity
you will want and look forward to hearing from you on working
out the details.
Sincerely,
Dorothy J. Hancock, Mayor
DJH/bjc
cc: Donald R. Silvey, P.E., Commonwealth Engineers, Inc.
40 EAST MAIN STREET CARMEL; INDIANA 46032 317/844-6433
February 19, 1988
Mr. Beau Wilfong
Hamilton Western Utilities, Inc.
1350 Greyhound Court
Carmel, Indiana 46032
Dear Beau:
Thank you for getting back to us so quickly on the
sewage treatment plant capacity. Regarding your first
question, at this point I would (haveito ask that the
moneys be paid_ when we start construction)"(be willing to
work with you on setting a schedule of payments as progress
is being made).
Your rate for treatment costs is based upon the method
of calculation setup in our contract with you. Your
current rate of $0.64807 per 1000 gallons was revised
downward five percent two years ago, and as we grow, we
expect it to continue down as costs are shared over more
customers.
At this point we would expect the actual expansion
project costs to be divided by our increased capacity to
establish the final cost per gallon of additional treatment
capacity. There may need to be some minor adjustments to
this but not of major significance. As Don said he pointed
out to you, there would also be some capital cost for the
use of the North-South Interceptor.
I hope that this is of help to you in setting how much
capacity you will want and look forward to hearing from you
on working out the details.
Sincerely,
Dorothy J. Hancock, Mayor
DJH/bc
CC: Donald R. Silvey, P.E., Commonwealth Engineers, Inc.
Line
Item
Number
CARMEL - HAMILTON -WESTERN UTILITIES
TREATMENT AGREEMENT`
DATE RECEIVED
JOB NO..�_
FILE
CALCULATION OF WHOLESALE RATE FOR OPERATION AND ROUTE TO: FEB 5 1986
MAINTENANCE COSTS AND FOR REPLACEMENT COST ON EQUIPMENT
Annual operation & maintenance
(0 & M) expense:
Allocation
Total Costs Percentage Shared Costs
1 Treatment plant expense $ 525,890 100% $585,890
2 Sludge handling disposal expense -0- 100% -0-
Collection system expense
3 - interceptor sewers _ 23,721 100%* 23,721
4 - collection sewers 66,894 0% -0-
5 - lift stations 27,992 0% -0-
6 Billing and collection expense 75,162 0% -0-
7 Industrial monitoring expense 0%
6 Subtotal 779,679 609,611
9 General and administrative expense 134,076 78.2%** 104,847
10 Taxes 40,175
Total 0 & M expense - 953,930 714,458
11 Plus: Annual replacement costs on
equipment for items of plant
benefiting wholesale customers 150,000*** 150,000
12 Total annual 0 & M expense and
replacement cost on equipment $1,103,930 864,458
13 Less: Carmel surcharge revenue
for excess BOD and SS -0-
14 Net of surcharge revenue -0-
15 Divided by total annual flow
received at Carmel treatment plants - :1,333.9****
16 Rate per million gallons of flow to
wholesale customers (including
domestic loading) $648.07
Allocation for interceptor based on 20% of collection costs.
Allocation percent = line item *8, shared cost : line item $8, total cost.
Amount estimated by the consulting engineer.
Plant flow 1,314.4 mg (August 1984 -July 1985) plus estimated Hamilton -Western
increase of 1.625 mg per month.
Revised February 3, 1986
August 26, 1985
mo above unaudited and limited
financial information is presented
for the purpose of dlscu✓sion and
consideration of appropriate officers
aid officials and in oub;cct to
future revision and anal report.
HAMILTON WESTERN UTILITIES, INC.
1350 GREYHOUND COURT
CARMEL, INDIANA 46032
Telephone: (317) 846-6561
February 17, 1988
The Honorable Dorothy Hancock
Mayor of the City of Carmel
40 E. Main Street
Carmel, Indiana 46032
Dear Dottie:
I want to thank you for taking time out the other day to
meet and discuss with me the possibility of our
participating with Carmel in the sewer expansion. I met
with Don Silvey the next week and we discussed the matter in
further detail.
We would like to obtain between 300,000 to 500,000 gallons
per day capacity in this expansion. There were a couple of
items that were still up in the air and if I knew the answer
to these then I could give you a more definitive answer
today. Specifically I would like to know when the money
would be required to be paid for the expansion. I would
hope it would be as progress was being made on the
expansion, but Don seemed to indicate that this might not be
the case. Also I would need to know what the cost would be
to treat the sewage per 1000 gallons. Finally I would like
to know how the final cost per gallon will be determined.
As soon as you can, please get back with me so that we can
work out the details and proceed with the project.
Sincerely,
/
u)(1 -7 -
Beau Wilfong
BW/pc
cc Don Silvey
IOMMONWEALTH
ENGINEERS, INC.
ENVIRONMENTAL ENGINEERS & CONSULTANTS
February 18, 1988
Honorable Dorothy J. Hancock, Mayor
City Hall
40 East Main Street
Carmel, Indiana 46032
RE: Hamilton -Western Utilities
Dear Dottie:
I received a carbon copy of Beau Wilfong's February 17th letter
today. In it he raised three (3) questions which I wanted to
comment upon.
First, he wanted to know when the money would need to
be paid: When he and I discussed this, I pointed out
that in the current project Jane asked that the money
be paid by Clay and Westfield up front, before
construction began. He indicated that he had hoped
there would be a bond issue and that he could pay the
cost over a period of time. I told him that there
probably would be no bond and that the schedule for
payment would be up to you as a policy decision. He
appears to be receptive to paying but wants to spread
payments over the construction period. The major risk
with this would be a default during construction with
the City left responsible. The risk could be limited
by requiring a letter of credit from his bank, if you
wanted to go along with him.
Second, he wanted to know what the cost would be for
treatment per 1000 gallons: This per his contract
would be calculated essentially the same as he is
paying now, $0.64807 per 1000 gallons. It is based
upon actual costs for treatment with a schedule
detailing the calculation attached to their contract.
The latest calculation sheet is attached.
Last, he wanted to know how cost per gallon of
capacity would be determined: The simple answer is
total project cost divided by the increased gallon per
day capacity. This ignores that there will be some
costs for nitrification and dechlorination which
should be shared on the total capacity used rather
than the incremental increase, but these costs will
not be a major item. So it may be premature to get
into that with him. When he and I met, I pointed out
710 Executive Park Drive
P.O. Box 406
Greenwood, Indiana 46142
(317) 888-1177
8770 Guion Road
Suite P
Indianapolis, Indiana 46268
(317) 872-1177
Honorable Dorothy J Hancock, Mayor
February 18, 1988
Page -2-
that he would also have cost associated with use of
the North-South Interceptor. The method of assigning
cost for that was established in the Westfield
agreement. That was established at $103,360 per
million gallons ($0.10336/gallon in his terms). Since
that was bonded, with interest cost incurred by the
City, it would be up to you if you wanted to adjust
the 1984 price. In our meeting I told him $0.10 to
$0.15/gallon.
Sorry to be so long winded, but wanted to get you some facts to
work with.
I have tried to draft a quick response for your consideration to
send back, but it will have to be retyped since 1 did not know
if you would want them to pay up front or offer any
alternatives.
Very truly yours,
COMMO ALTH ENGINEERS, INC.
Donald R. Silvey, P.E.
DRS/djw
attachment