HomeMy WebLinkAboutCrossroad Engineers/ENG/Addl Serv 20/130000/illinois Streeterosskond Engineers
Engineering Department - 21)15
Appropriation =212-R4 62S65; ASA n1: P.O. 322926
Contract Not To Exceed $130.0(10.00
ADDITIONAL SERVICES AMENDMENT TO
AGREEMENT FOR PURCHASE OF GOODS AND SERVICES
THIS AMENDMENT TO THE GOODS AND SERVICES AGREEMENT (°Agreement") entered into by and
between the City of Carmel and CrossRoad Engineers (the "Vendor'), as City Contract dated November 20, 2013
shall amend the terms of the Agreement by adding the addition& services to be provided by Vendor consistent with
the Scope of Work attached hereto and incorporated herein as Exhibit "A". Furthermore, the terms of the Agreement
shall be amended to include the Evenly requirement as stated in Indiana Code § 22-5-1.7 et seq., which is attached
hereto and incorporated herein as Exhibit "6", as, well as the required E -verify Affidavit, attached hereto and
incorporated herein as Exhibit "0". Also, pursuant, to I.C. § 5-22-16.5, Vendor shall certify that in signing this
document, it does not engage in investment activities within the Country of Iran. The terms and conditions of the
Agreement shall not otherwise be affected by this Additional Services Amendment and shall remain in full force and
effect.
IN WITNESS WHEREOF, the parties hereto have made and executed this Amendment as follows:
CITY OF CARMEL, INDIANA
by and through its Board of Public
Works and Safety
By:
ADT— re& n-
CrossRoad Engineers
By:
James Brainard, Presiding Officer Authorized Sigl ature
Date:
Ivi 'ry Ann
Date:
urke, 191emb
1
_.v
Lori S. Watson
Date:
ATTEST:
emt er
7/t' I5
Diana Cordray,IAMC Sierk-Treasurer
Date: Z—1 l5
tt,. ..:h
a
u
c_ t CAmes
Primed Nhme
Title
FID,riIN: 35 tiro 333
Last Four of SSN if Sole Proprietor:
Date: w
1f.A gnli i.1 ,-4L1161161-^PY:I.mit V..,l 11 LIN 1.6
June 12, 2015
Jeremy Kashman, City Engineer
City of Carmel
One Civic Square
Carmel, Indiana 46032
RE: Illinois Street Extension — Spring Mill Road to 111th Street
Project No. 10-10
Supplemental Fee Proposal for Professional Services
Dear Jeremy:
As we discussed, we are requesting a supplemental increase to our inspection contract dated
November 20, 2013. When we submitted our fee proposal almost 2 years ago, the construction
duration was expected to be 48 weeks. It has already lasted 53 weeks and is expected to go
another 15 weeks, counting landscaping, before it's finished. We have been able to stretch our
inspection budget quite a bit, but we can't stretch it that much! So, even though we now
anticipate a total of 20 additional weeks of construction activity, we are only requesting an
additional $130,000 for a ceiling increase, an equivalent of an additional 12 weeks. Please see
the attached spreadsheet for a man-hour justification for this additional budget amount.
If you should have any questions or need any further information, please do not hesitate to call
me or Trent Newport.
Sincerely,
CrossRoad_ ngineers, PC
Chip'Char es, P. E
President
EXHIBIT P
f 661
3417 Sherman Drive O Beech Grove, Indiana 46107 B Tel 317.780.1555 D Fax 317.780.6525
CROSSROAD
ENGINEEIMPE
Illinois Street Extension -- Spring Mill Road to 11 1 th Street
Supplemental Estimated Costs for Construction Inspection
ACTIVITY
DIR
RES PROJ
REP
PROJ INSP
ASST PROJ
INSP
CADD
TECH
Add'I Construction Duration 8 wks
32
400
400
320
0
Landscaping / Final Record 4 wks
16
160
0
TOTAL HOURS
48
560
400
320
0
The proposed fee for these estimated hours is as follows:
DIRECT LABOR COSTS --
Personnel Class Billine Rate Total Hours Direct Labor Costs
Director S140.00 48 86,720.00
Resident Proj. Rep. 5110.00 560 861,600.00
Project Inspector 590.00 400 $36,000.00
Asst. Proj. Inspector 870.00 320 822,400.00
CADD Tech 880.00 0 $0.00
TOTAL DIRECT LABOR COSTS $126,720.00
DIRECT NON - LABOR COSTS --
MILEAGE
mileage rate will be $0.52 /mile
Direct Non -Labor Costs
Director 50 miles/wk x 8 weeks $208.00
Res. Proj. Rep. 250 miles/wk x 8 weeks S1,040.00
Proj. Inspector 250 miles/wk x 8 weeks $1,040.00
Asst. Proj. Inspector 250 miles/wk x 8 weeks 51,040.00
TOTAL ESTIMATED COSTS
USE
$3,328.00
$130,048.00
$130,000.00
EXHIBIT