TO: Lisa Scott CONTRACT CHANGE ORDER NO.: ,,,,n ,t„20 3: 08
Engineering Admininstration DATE: J 020,0
City of Carmel Indiana PROJECT NAME: Keystone & Main Street
One Civic Square CITY REQ. NO.:
Carmel, IN 46032 CITY PO NO.: 07-08 E
CITY PO DATE:
I. You are directed to make the following changes in this Contract:
a. Addition of pay items to provide improvements along the detour routes during construction
activities at the interchange.
b. Addition of temporary concrete barrier wall along Keystone for utility relocation activities.
c. Change of the decorative lights per City of Carmel, the lighting will change from Hollophane
to LED.
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+) OR ( -) DAYS
I1. The following referenced Documents further describe the changes outlined in Paragraph 1,
and are to be considered a part of this Change Order: R.F.P.: W.D.C. NO.:
Other:
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $
Contract Price will be increased/decreased by this Change Order $
New Contract Price including this Change Order $
Contract Time prior to this Change Order Days 11/1/2010 Completion Date
Net increased/decreased resulting from this Change Order 0 Days
Current Contract Time including this Change Order Days 11/1/2010 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
11,781,537.16
45,982.31
11,827,519.47
]'he Above Changes Are
Recommended
American Structurepoint Inc.
ENGINEER
7260 Shadeland Station
Address
Indianapolis, IN 46256
City/State/Zip
By:
Phone: 311 2$1 -95(.3
(210
Date:
The Above Changes Are
Accepted
Walsh Construction
CONTRACTOR
2749 N. SR 39
Address
LaPorte, IN 46350
Cip-/Stale/Zi.
Approved
dor resent
James Brainard, Mayor
ich el McBride. Cityyngin1r
Bur . ember
Phone: 311-/I4. 054
Date: 6/z//0
Mem
11111
w: /_/. / /.!j
Diana Cordray CI/Treasurer
Date:
%23
Contract Modification
City of Carmel
6/2/2010 1:42 PM
FieldManager 4.5a
Contract: _07-08E, Keystone Parkway and Main Street Interchange
Cont. Mod.
Number
2
Revision
Number
Cont. Mod.
Date
6/2/2010
Net Change
$45,982.31
Awarded Contract Amount
$11,746,826.97
Route
Contract Location
Keystone Parkway and Main Street Interchange
Short Description
Change Order # 2
Description of Changes
Four of the following items are being added to the contract to provide improvements along the detour routes while the
interchange is under construction. Detour routes have seen a large increase in traffic which has created the need to provide
site improvements along 126th Street near Auman Drive, as well as add signal heads and make modification to the signals
at the 126th and 136th Street intersections with Gray Road.
An item is being added for temporary barrier wall that was added to the contract for safety purposes along Keystone
Parkway while utility relocations took place.
The last item is being added to the project for a switch to LED lighting. The LED lighting is now being added, per the City of
Carmel, in place of the Holophane lighting that was specified in the contract documents.
New Items
Project: 07-08E, Keystone Parkway and Main Street Interchange
Category: 1, Keystone Parkway and Main Street Interchange
Item Description Item Code Prop.Ln. ItemType Unit Proposed Qty. Unit Price Dollar Value
Detour Route - Tree Clearing - 126th _0823 0268 CHANGE LS 1.000 8,119.49000 $8,119.49
Street
Reason: Clearing of pine trees along south side of 126th Street west of Auman Drive for sight distance improvements.
Detour Route - Modular Block Wall - 126th _0824 0269 CHANGE SYD 27.500 136.00000 53,740.00
Street
Reason: Installation of modular block wall along south side of 126th Street west of Auman Drive. The block used was from the City of
Carmel's inventory.
Detour Route - Common Excavation for 0825 0270 CHANGE LS 1.000 5,796.01000 $5,796.01
Modular Block Wall
Reason: Excavation of existing grade to install modular block wall along south side of 126th Street west of Auman Drive for sight
distance improvements.
Detour Route - Modification to Signals on _0826 0271 CHANGE LS 1.000 3,387.43000 53,387.43
Gray Road
Reason: Installation of 5 -head signals and sheet sign at 126th and 136th Streets at Gray Road.
Contract: _07-08E
Cont. Mod.: 2 Page 1 of 2
223
Contract Modification
City of Carmel
6/2/2010 1:42 PM
FieldManager 4.5a
New Items
Project: 07.08E, Keystone Parkway and Main Street Interchange
Category: 1, Keystone Parkway and Main Street Interchange
Item Description Item Code Prop.Ln. ItemType Unit Proposed Qty. Unit Price Dollar Value
Temporary Barrier Wall for Duke Energy _0827 0272 CHANGE LS 1.000 4,023.70000 $4,023.70
Reason: Installation of temporary concrete barrier wall along the northbound traffic during Duke Energy's relocation efforts
Switch Decorative Holophane Lighting to _0828 0273 CHANGE LS 1.000 20,915.68000 $20,915.68
LED Lights
Reason: The City of Carmel has requested the decorative lighting to change from Hollophane to LED.
Subtotal for Category 1: $45,982.31
Subtotal for Project 07 -OBE: $45,982.31
FEDERAL PARTICIPATION -ACTION BY F.H.W.A.
_Approved _Not Eligible
_See Letter Dated
(Signature) (Date)
Contract: _07-08E Cont. Mod.: 2
Page 2 of 2
3723
The Walsh Group
Walsh Construction
EXTRA WORK SUMMARY
Date: 04/23/2010
Project Number: 07-08E
Project Name: Keystone Ave/Main St
Title: Tree Clearing at 126th & Auman
'.'Item•.-
Nninber.
.' . .'.' bgsEription:. .... .::.
',Unit,'.'.''.'.''''''
. pRanfMp'.'.'lJnit.'.'.' .' G9st•.'.' .' .' .SY4tVtal,' .
''.Mark,op.•.'. .-Markbp.. '
. -: • .'R4k '.'.' .' .'. • .C9st.'. -.
.Total.•.•.
..: •:.00sf.:.
LABOR
Walsh Construction
16.00
HR
$35.73
$571.68
L
$114.34
$686.02
MATERIALS
M
M
EQUIPMENT
E
SUBCONTRACT
Indy Tree Service
1
LS
$6,750.00
$6,750.00
S2
$562.50
$7,312.50
BOND & INSURANCE
Insurance
1
LS
$63.99
$63.99
I/13
$6.40
$70.39
Performance Bond
1
LS
$45.99
$45.99
1/8
$4.60
$50.59
TOTAL $8,119.49
Note: Mark-up rules are L=20% labor, E=12% equipment, M=12% materials, S1=10%sub <$3000 & S2=sub >$3000, I/B=10% Bonds & Insurance
Comments: Please see attached sheets for breakdown of Indy Tree Service Costs
07-0BE Clearing at 126th & Auman St Pricing.xlsx, Pagel
0
OQ
Indy Tree & Landscape Inc.
2878 N. Raceway Rd.
Indianapolis, IN 46234
Estimate
Phone #
317-293-7299
Fax #
317-293-7314
E-mail
indytree a att.net
Name / Address
Date
4/20/2010
Walsh Construction
2749 N. State Rd. 39
Estimate #
23145
Laporte: Indiana 46350
Project
Carmel 1 26th & Au...
Description
Qty
Cost
Total
Remove Pines and scrub trees along I26th St. as discussed with
Charlie Gannon
Walsh will supply Baggers and dump site for wood chips
No Stumps will be removed
JOB LOCATION - Carmel. In. 126th & Auman Dr.
6.750.00
6.750.00
Subtotal $6.750.00
Sales Tax (7.0%) $0.00
Total $6,750,00
cti
sh Construction Insurance & Bond Cost Breakdown
Tree Clearing at 126th & Auman
INDOT Contract I2-28177
ITEM
CHANGE ORDER VALUE
RATE UNIT TOTAL
INSURANCE
PERFORMANCE BOND
$ 7,998.52 0.008 1 $ 63.99
$ 7,998.52
5.75 $ 1.000 $ 45.99
TOTALS: S 109.98
IO%Mark-up: S 11.00
S 120.98
423
Unit Pricing for Installation of Modular Block at 126th St and Auman
Page 1 of 1
02(0`\
Unit Pricing for Installation of Modular Block at 126th St and Auman
Gannon, Charlie [cgannon@walshgroup.com]
Sent: Monday, April 26, 2010 6:43 AM
To: Machala, Dave
Cc: Partlow, Zachary [zpartlow@walshgroup.com]
Dave,
Walsh's pricing for the installation of the proposed modular block wall along 126th St at Auman Drive is:
$136.00/SY.
This price includes the mob/demob of equipment, furnishing and installing the #53 stone base, placing the
modular blocks that will be furnished and delivered by the City of Carmel, furnishing and installing a 4"
underdrain pipe, and furnishing and installing the #8 aggregate backfill.
Capping of the aggregate backfill and final grading will be included in our excavation price.
Thanks,
Charlie Gannon, PM 1 walsh construction
Project #210008 1 Keystone Ave/Main St. Roundabout
810 E. Main St I Carmel, IN 46032
317.848.3403 OfficeI317.848.4018 Fax 317.714.8654 Cell
743
https://mail.structurepoint.com/owa/?ae=Item&t=IPM.Note&id=RgAAAACiEu%2N9R7 V... 6/2/2010
The Walsh Group
Walsh Construction
EXTRA WORK SUMMARY
Date: 05/12/2010
Project Number: 07-08E
Project Name: Keystone Ave/Main St
Title: Common Excavation for Sight Clearance at 126th St
•.Nufnb?r.
.'. . . . .'.•DesrjPjiRn.'.'.'.'.'. .'
'.;O n}itjr, ;•uriit; ;
.'.Unit.'.'. ,'.'.''.'. .'.'
; ;•post•.'.'.••.subtot0l.'.
'...Mark,up. ..•.Markaup. '
,'.-.-Rule.'.'.'.'.'.'.Cst.'.'.
'..Total.'.'.'
.'.'.•Cost'.'.'.
LABOR
Walsh Construction
28.00
HR
$55.19 $1,545.32
L
$309.06
$1,854.38
3
HR
$69.36 $208.08
$41.62
$249.70
8
HR
$39.85 $318.80
$63.76
$382.56
MATERIALS
Dumpsters
1
EA
$575.00 $575.00
M
$69.00
$644.00
EQUIPMENT
Cat320 Exc
23
HR
$53.80 $1,237.40
E
$148.49
$1,385.89
Skid Loader
8
HR
$22.00 $176.00
E
$21.12
$197.12
SUBCONTRACT
Ward Trucking
8
FIR
$75.00 $600.00
S2
$132.00
$732.00
3
HR
$88.00 $264.00
$264.00
BOND & INSURANCE
Insurance
1
LS
$45.68 $45.68
I/8
$4.57
$50.24
Performance Bond
1
LS
$32.83 $32.83
I/B
$3.28
$36.11
TOTAL $5,796.01
Note: Mark-up rules are L=20% labor, E=12% equipment, M=12% materials, S1=10%sub <$3000 & S2=sub >$3000,1/8=10% Bonds & Insurance
Comments: Please see attached sheets for breakdown of Indy Tree Service Costs
07-0eE Common Excavation at 126th 8 Auman St Pricing.xlsx, Pagel
Walsh Construction Labor Cost Breakdown
Common Excavation for Sight Clearance at 126th St
Keystone Ave/136th St
EMPOL YEE CLASSIFICATION DATE WORKED RT HRS OT HRS RATE/HR OT RA TE/HR TOTAL NOTE
Rick Campbell Journeyman Oper_ 5/3/2010 8 $ 55.19 $ 441.54
5/4/2010 4 5 55.19 $ 220.76
5/6/2010 8 3 5 55.19 5 69 36 $ 649.60
5/1412010 8 $ 55.19 $ 471.52
Boyd Hobson Journeyman Laborer 5/14/2010 8 $ 39.85 $ 318.80
SUBTOTAL: $
20% Mark-up:TOTA
$
2,072.22
414.44
$ 2,486.66
7/3
Walsh Construction Equipment Cost Breakdown
Common Excavation for Sight Clearance at 126th St
Keystone Ave/136th St
EQUIPMENT DE.SC'RIPTTON DATE REG. HRA CT ORS RATE/HR TOTAL IiVVOICE
Excavator
Skid Loader
Cat320 5/3-5/6 23 S 53.80 $ 123740
Cat 277 5/14/2010 8 S 22.00 S 176.00
SUBI OlAL: 5
12%3lark-up: 5
EOE' S L:
1,413.40
169.61
S 1,583.01
23
sh Construction Insurance & Bond Cost Breakdown
Common Excavation for Sight Clearance at 126th St
INDOT Contract R-28177
ITEM
CHANGE ORDER VALUE
RATE UNIT TOTAL
INSURANCE
PERFORMANCE BOND
5.709.65 0.008 1 $ 45.68
$ 5,709.65 5.75 $ 1,000 $ 32.83
TOTALS: $
IO% Mark-up: S
78.51
7.85
S 86.36
�� 23
The Walsh Group
Walsh Construction
EXTRA WORK SUMMARY
Date: 05/2612010
Project Number: 07-08E
Project Name: Keystone Ave/Main St
Title: Signal Work at 126th & 136th at Gray Road
•,Nuinber,
, , , , , .'.•Description.-.'.'.'. . .
•,Qirn(ity,•: omit: ,
, .•Cpst .'. .'.'.s:6t4t01.•.
, • ,-_ •Rule.'.'.'.'.'.'GAstI-'•'
Total. . .
, .'.•Cos{'.'.• •,
LABOR
L
MATERIALS
M
EQUIPMENT
E
SUBCONTRACT
Midwestern Electric
1
LS
$3,034.54
$3,034.54
S2
$302.42
$3,336.96
BOND & INSURANCE
Insurance
1
LS
$26.70
$26.70
118
$2.67
$29.37
Performance Bond
1
LS
$19.19
$19.19
I/B
$1.92
$21.11
TOTAL $3,387.43
Note: Mark-up rules are L=20% labor, E=12% equipment, M=12% materials, S1=10%sub $3000 & S2=sub >$3000, IB=10% Bonds & Insurance
Comments: Please see the attached quote from Midwestern Electric
07-08E Signal Work on Gray Road at 128th 8 136th81ax, Pagel
W
MIDWESTERN ELECTRIC, INC.
INDIANAPOLIS
3385 N. Arlington Avenue 0 Indianapolis, Indiana 46218-2542
ELECTRICAL CONTRACTOR
WALSH CONSTRUCTION
ATTN: CHARLIE GANNON
ITEMIZED BILLING
Project Description:
Telephone 317-545-7641
Fax 317-545-7643
Invoice # 5260
Signal Work on Gray Road at 126th Street & 136th
Street
Description
u/m
Qty
Rate
Amt
Labor
Foreman
hr
2
59.75
119.50
Electrician
hr
5
52.66
263.30
Technician
hr
15
39.21
588.15
Laborer
hr
6
38.07
228.42
20% Mark-Up
239.87
TOTAL LABOR
1,439.24
Material
Used 5 -section Signal Head
ea
2
412.50
825.00
Laod Switch
ea
2
22.00
44.00
Sheet Sign, R10-12
ea
2
50.25
100.50
Signal Cable, 7c/14ga
ft
221
0.47
103.87
12% Mark-Up
128.80
TOTAL MATERIAL
1,202.17
Equipment
Utility Truck
hr
13
9.00
117.00
Bucket Truck
hr
13
18.00
234.00
12% Mark-Up
42.12
TOTAL EQUIPMENT
393.12
TOTAL DUE THIS INVOICE
$ 3,034.54
COMMERCIAL
• STREET LIGHTING 0 TRAFFIC SIGNALS 0 MAINTENANCE
AN EQUAL OPPORTUNITY EMPLOYER
/2/
sh Construction Insurance & Bond Cost Breakdown
Signal Work at 126th & 136th at Gray Road
1NDOT Contract R-28177
ITEM CHANCE ORDER VALUE
RATE UNIT TOTAL
INSURANCE
PERFORMANCE BOND
$ 3336.96 0.008 1 $ 26.70
$ 3,336.96 5.75 $ 1,000 $ 19.19
TOTALS: S 45.88
IO% Mark-up: S 4.59
$ 50.47
f 23
Walsh Construction
May 20, 2010
David P. Machala, El
American Structure Point, Inc.
7260 Shadeland Station
Indianapolis. IN 46256
Re: 07-08E Keystone Ave at Main St Project - Pricing Temporary Concrete Barrier for Duke Energy
David:
Walsh Construction is pleased to submit the following for the temporary barrier rail furnished for the
Duke Energy relocation work.
Furnish, Install, and Remove 200 LF of Temporary Concrete Barrier - 54023.70 Lump Sum
Please see the attached breakdown of our cost with allowable mark-ups.
Sincerely,
,,.4r .�..,..
Charles Gannon �, ,
Charles Gannon 1 Project Manager
WAI SH CONSTRUCTION
810E. Main St. Carmel, IN 46032
317.848.3403 Office 1 317.848.4018 Fax 1 317.714.8654 Cell
Cc: Brian Hoppel Senior Project Manager
Office File
#0072-
.Z3
212
'Z3
The Walsh Group
Walsh Construction
EXTRA WORK SUMMARY
Date: 05/20/2010
Project Number: 07-08E
Project Name: Keystone Ave/Main St
Title: Temporary Barrier Rail for Duke
•,Number..'.
. . . .•.'besjiptign.'.'.'.'. . .
.'.Unit.'.'.'.'.'.'.'.•.','.'
• Q4rgn}itjr:•. Qnit'.'.'.'Post' .'.•.'.'.SPt,t4tdl:':
'.'.Mark-ap.•.'. .'Mark-up.' .
•.•? '' ' '..Cost.'.'.
'Total.•....
. .•.Cosj'.•:•.
LABOR
Walsh Construction
26.00 HR $35.73 $928.98
L $185.80
$1,114.78
MATERIALS
Barrier Rail Rent
200 LF $5.25 $1,050.00
M $126.00
$1,176.00
M
EQUIPMENT
Excavator
4 HR $53.36 $213.44
E $25.61
$239.05
SUBCONTRACT
Trucking
16 HR $78.50 $1,256.00
S2 $177.92
$1,433.92
BOND & INSURANCE
Insurance
1 LS $31.71 $31.71
I/B $3.17
$34.88
Performance Bond
1 LS $22.79 $22.79
I/B $2.28
$25.07
TOTAL $4,023.70
Note: Mark-up rules are L=20% labor, E=12% equipment, M=12% materials, S1=10%sub <$3000 & S2=sub >$3000, I/8=10% Bonds & Insurance
Comments:
c\ -3
07-08E Temporary Barrier Rail For Duke Pricing.xlsx, Pagel
tI
sh Construction Insurance & Bond Cost Breakdown
Temporary Barrier Rail for Duke
INDOT Contract R-28177
ITEM
CHANGE ORDER VALUE
RATE UNIT TOTAL
INSURANCE
PERFORMANCE BOND
$ 3,963.75 0.008 I S 31.71
$ 3.963.75 5.75 $ 1,000 $ 22.79
TOTALS: $
10% Mark-up: $
54.50
5.15
$ 59.95
The Walsh Group
Walsh Construction
EXTRA WORK SUMMARY
Date:
Project Number: 07-08E
Project Name: Keystone Ave/Main St
Title: Cost to Convert to LED Lights
05/2012010
'.•Item'.•.
•.Number::'.
. .:.•:•Boai:riptrott:•:-'... .
•.Ol+ant•
.'.bnit:
Unit. -. .'.'. _'.
::. 00st:.:.:.:-:su4tgtal:•:.•:
- .' .Mark,up.•.•.'. -Mark--up.. '
• .-Rule:':-:: :':'cgst:'.'...'.
' ..•.Total.-••.
-DOA •:•:•
LABOR
L
MATERIALS
M
EQUIPMENT
E
SUBCONTRACT
Midwestern Electric
1
LS
$19,172.00
$19,172.00
S2
$1432.04
$20,604.04
BOND & INSURANCE
Insurance
1
LS
$164.83
$164.83
1/8
$16.48
$181.32
Performance Bond
1
LS
$118.47
$118.47
I/6
$11.85
$130.32
TOTAL $20,915,68
Note: Mark-up rules are L=20% labor, E=12% equipment, M=12% materials, S1=10%sub <$3000 & S2=sub >$3000,1/8=10% Bonds & Insurance
Comments: Please see the attached quote from Midwestern Electric
7-08E Cost to convert to LED Lights.xlsx, Pagel
MIDWESTERN ELECTRIC, INC.
INDIANAPOLIS Telephone 317-545-7641
Fax 317-545-7643
May 12, 2010
3385 N. Arlington Avenue o Indianapolis, Indiana 46218-2542
ELECTRICAL CONTRACTOR
Charlie Gannon
Walsh Construction
300 E. Main Street
Carmel, IN 46032
Re: City of Carmel, Keystone Pkwy and Main St. Roundabout
Charlie,
Please find below our additional cost to substitute the metal halide ornamental luminaires with
LED luminaires as per the city's and project engineer's request.
Cost Difference for LED
Ornamental Luminaires $ 19,712.00
Our cost breakdown along with copies of our vendors' quotes is attached.
If you have any questions regarding our pricing, feel free to contact me.
Dean Balazs
Division Manager
COMMERCIAL 0 STREET LIGHTING 0 TRAFFIC SIGNALS 0 MAINTENANCE
.IN EOUAL OPPORTUNITY EMPLOYER
sh Construction Insurance & Bond Cost Breakdown
Cost to Convert to LED Lights
INDOT Contract R-28177
ITEM
CHANGE ORDER VALUE
RATE UNIT TOTAL
INSURANCE
PERFORMANCE BOND
$ 20,604.04 0.008 1 $ 164.83
$ 20,604.04 5.75 $ 1.000 $ 118.47
TOTALS: $ 283.31
I0%Mork-up: $ 28.33
S 311.64
2y
Z3
PRICE DIFFERENCE
LED Ornamental Luminaire 41,000.00
Cost for Porte Huron Luminaire
(markup) + 10%
23,080.00
17,920.00
1,792.00
Total 19,712.00
2/23
QUOTE # 131ST LED DATE: 05-20-10 PAGE 1
LITE
ILLUMINATING SINCE 1987
Techlite Corporation
7718 Loma Court
Fishers, IN 46038
317.578.2626 P
317.578.2727 F
www_techlitecorp.com
To: DEAN
MIDWESTERN ELECTRIC
3385 N ARLINGTON AVE
INDPLS, IN 46218
54 - - -
Proj: 131ST(MAIN STREET) LED
Arrh•
Enar:
rent•
Spec:
Remarks:
Qty
Type
Mfg
Description
Unit Price
Extd.Price
16
SPRI
COLUMBIA LUMINAIRE LED
2075.00
$33200.00
FOR 30FT POLES 162 WATT
4
SPRI
COLUMBIA LUMINAIRE LED
1950.00
$7800.00
FOR 15FT POLES 125 WATT
Total =_
$41000.00
F.O.B. Per Mfg Terms: Net 30 Days Lead time:
Prices firm for entry by: 30 Days Shipment by:
Quotation is based on the above listed bill of material and counts.
Any changes would make quotation void and require a requote.
Given lead times are strictly estimates and are subject to change once
order is entered. PLEASE NOTIFY US OF ANY REQUIRED DATES.
ORDERS ARE SUBJECT TO MANUFACTURERS TERMS AND CONDITIONS.
Printed 05/20/10 13:36:34 Per: STEVE BATES
203
MIDWESTERN ELECTRIC, INC.
3385 N. Arlington Ave.
INDIANAPOLIS, IN 48218
PHONE: 317-545-7641
FAX: 317-545-7643
TO: Graybar
ATTN:
E -Mail
PHONE:
FAX:
821-5700
821-5750
PURCHASE ORDER
Show this Purchase Order Number on all
correspondence, invoices, shipping papers
and packages.
PAGE 1 OF 1
P.O.# 1486-10108
DATE: 4/16/10
AUTHORIZED BY: Ryan Lepper
SHIP TO: MWE - INDIANAPOLIS SHOP
3385 N. ARLINGTON AVE.
INDIANAPOLIS, IN 46218
EMAIL: I N(a)m idwestern-electric.com
Order is to be entered in accordance with prices, delivery and specifications shown above. jAUTHORIZED BY
Notrfy us immediately if you are unable to ship as specified. Do Not Duplicate
Seller shall comply with the EEO Clause in Section 202 of Executive Order 11246, as amended,
45 CFR -60-250 and 41 CFR -60-741, as amended, which are incorporated herein by specific reference.
23
3
ORDERED
Qty
RECEIVED
Qty
Date
STOCK NO.
DESCRIPTION
UNIT
PRICE .
. TOTAL
20
ea
20
Holophane "Port Huron" 250W MH Luminaire
1,154.00
23,080.00
11
ea
-
Holophane "Mongoose" 250W MH Luminaire
-
2 •
ea
G.E. Underpass Luminaire 150W HPS
11
ea
Valmont Light Pole, 30 ft. EMH Dual 1.5 Arm
w/Breakaway Base Powder Coated Black
-
16
ea
Spring City Decorative Light Pole, 30 ft. EMH
w/8 ft. Decorative Arm + Cast Base,
-
Powder Coated Black
-
4
ea
Spring -City Decorative tiyhl Pole, 15ft. EMH
.
w/4ft. Decorative Arm & Cast Base, Powder
-
Coated Black
-
1.) All material to meet or exceed City of
-
Carmel project #07-08E Specifications
-
2.) -Submit 10 sets -of shop drawings for
-
approval.
-
3.) All Freight Allowed
-
-
4.) Call 48 hrs. prior toany.delivery
-
TOTAL:
$
REQ'D
WHEN
SHIP
F.O.B.
TERMS
BY -
SHIP
VIA -
POINT
Order is to be entered in accordance with prices, delivery and specifications shown above. jAUTHORIZED BY
Notrfy us immediately if you are unable to ship as specified. Do Not Duplicate
Seller shall comply with the EEO Clause in Section 202 of Executive Order 11246, as amended,
45 CFR -60-250 and 41 CFR -60-741, as amended, which are incorporated herein by specific reference.
23
3