HomeMy WebLinkAbout3 Structural Garage Permit_150701ROOF PLAN (GENERIC BUILDING SHOWN)
WALLS (GENERIC BUILDING SHOWN)
OVERHANGS
(CANOPIES,
ETC)
T/PARAPET
T/ROOF
T/PARAPET
T/ROOF
a a
5P
5
4P
4
a
5P
5
5P
5
4P
4
5P
5
a
a
a
3o 3o
2o
2o
2o
33
3 3
32
2
2
2
1 2
4) PRESSURES SHOWN ARE NOMINAL PRESSURES,
MULTIPLY BY 1.67 FOR ULTIMATE PRESSURES.
GENERAL NOTES
MASONRY
ALL LOAD BEARING WALLS AND EXTERIOR WALLS SHALL BE COMPOSED OF ASTM C90 HOLLOW
CONCRETE MASONRY UNITS WITH ASTM C270, TYPE "S" MORTAR. GROUT SHALL CONFORM TO
THE REQUIREMENTS OF ASTM C476 AND HAVE A COMPRESSIVE STRENGTH OF 3000 PSI.
ALL EXTERIOR CMU WALLS SHALL BE REINFORCED FULL HEIGHT IN A GROUT FILLED CELL WITH
1-#5 AT:
- EACH CORNER, WALL ENDS, WALL INTERSECTIONS
- EACH SIDE OF CONTROL JOINTS AND
- AT A MAXIMUM SPACING OF 24" OC, UON
- SEE DETAIL 1/S1.1 FOR TYPICAL REINFORCING AT WALL OPENINGS.
- AT BEAM & JOIST GIRDER BEARING LOCATIONS ADD REINFORCING AS SHOWN IN PLAN.
LAPPED BARS SHALL BE SECURED WITH WIRE TIES OR OTHER MEANS TO ENSURE THAT THE
BAR IS NOT DISPLACED DURING GROUT PLACEMENT OUTSIDE THE TOLERANCES ESTABLISHED
BY ACI 530. LAP VERTICAL BARS 72 BAR DIAMETERS AND HORIZONTAL BARS 48 BAR DIAMETERS
(UNLESS OTHERWISE NOTED).
GROUT ALL CELLS CONTAINING VERTICAL REINFORCEMENT IN 5'-0" MAXIMUM LIFTS. DO NOT
BEGIN PLACEMENT OF GROUT UNTIL ALIGNMENT OF CELLS ARE INSPECTED AND APPROVED.
FILL ALL CELLS BELOW FINISHED GRADE.
PROVIDE HORIZONTAL JOINT REINFORCEMENT IN WALLS AT 16" OC VERTICALLY, UON. IN
ADDITION, INSTALL JOINT REINFORCING IN THE FIRST TWO MORTAR JOINTS ABOVE & BELOW
OPENINGS, EXTENDING AT LEAST 24 INCHES BEYOND THE OPENING. PROVIDE HORIZONTAL
JOINT REINFORCEMENT IN PARAPETS AND FREE STANDING WALLS & 8" OC VERTICALLY. LAP
JOINT REINFORCEMENT 6" MINIMUM.
SEE ARCHITECTURAL DRAWING FOR EXPANSION OR CONTROL JOINTS. IF NOT SHOWN, LOCATE
VERTICAL CONTROL JOINTS AT 25'-0" OC MAXIMUM, BUT NOT LESS THAN 2'-0" FROM A JOIST OR
BEAM BEARING PLATE. AT BUILDING CORNERS, PROVIDE ONE JOINT IN ONE OF THE TWO WALL
SIDES NO MORE THAN 5'-0" FROM THE BUILDING CORNER.
ALL PRECAST OR POURED LINTELS SHALL BE REINFORCED WITH TWO #4 TOP & BOTTOM WITH #
3 TIES @ 12" AS A MINIMUM AND HAVE A MINIMUM MASONRY END BEARING OF 8".
BOND/TIE BEAM REINFORCEMENT SHALL BE CONTINUOUS ACROSS CONTROL JOINTS.
16" U-BLOCK OR BOND BEAM SHALL CONSIST OF TWO 8" KNOCK-OUT BLOCKS.
BARS SPECIFIED TO BE EACH FACE SHALL BE HELD IN PLACE WITH SPACERS AND SHALL BE
LOCATED 2 3/8" FROM EACH FACE TO THE CENTER OF THE BAR.
MASONRY WORK SHALL BE INSPECTED IN ACCORDANCE WITH ACI 530-05 QUALITY ASSURANCE
LEVEL B
FOUNDATION
IF FOOTING ELEVATIONS SHOWN OCCUR IN A DISTURBED, UNSTABLE, OR UNSUITABLE SOIL,
THE ENGINEER SHALL BE NOTIFIED.
THE BOTTOM OF ALL FOUNDATIONS SHALL EXTEND A MINIMUM OF 36 INCHES BELOW THE
TOP OF FINISH GRADE.
STEEL
ALL BOLTS SHALL BE SNUG TIGHT (AS DEFINED BY AISC) UON.
MINIMUM SIZE OF ALL FILLET WELDS SHALL CONFORM TO SECTION J2 AISC
SPECIFICATIONS EVEN THOUGH SHOWN OTHERWISE ON ARCHITECTURAL,
MECHANICAL, OR STRUCTURAL DRAWINGS.
ALL WELDS ALONG THE LENGTH OF MEMBERS INDICATED ON ARCHITECTURAL OR
STRUCTURAL DRAWINGS, BUT NOT SIZED, SHALL BE A MINIMUM OF:
3/162-12
3/162-12
DESIGN CRITERIA
SOIL BEARING (DESIGN MAXIMUM)
PAINT & PROTECTION
DEFORMED BARS
ANCHOR RODS
HIGH-STRENGTH BOLTS
WELDING ELECTRODES
STEEL PIPES
HSS SQUARE & RECTANGULAR SHAPES
OTHER SHAPES & PLATES
STRUCTURAL STEEL (DESIGN PER CURRENT EDITION AISC), UNLESS OTHERWISE
NOTED (UON) MATERIALS SHALL BE AS FOLLOWS:
COMPRESSIVE STRENGTH
CONCRETE MASONRY (DESIGN PER CURRENT EDITION ACI 530)
WELDED WIRE FABRIC
PRESTRESSED PRECAST CONCRETE
RETAINING WALLS
SLAB ON GRADE
CONCRETE (DESIGN PER CURRENT EDITION ACI 318)
ANALYSIS PROCEDURE
RESPONSE MODIFICATION FACTOR, R
SEISMIC RESISTING SYSTEM
BASIC STRUCTURAL SYSTEM
SEISMIC DESIGN CATEGORY
MAPPED SPECTRAL RESPONSE ACCELERATION, S1
MAPPED SPECTRAL RESPONSE ACCELERATION, Ss
IMPORTANCE FACTOR, I
THERMAL FACTOR, Ct
EXPOSURE FACTOR, Ce
FLAT ROOF SNOW LOAD (INCLUDING RAIN ON SNOW SURCHARGE)
GROUND SNOW LOAD, Pg
ROOFS AND CANOPIES: (REDUCIBLE)
WELDED STUDS
W-SHAPES
FOOTINGS
SITE CLASS
SEISMIC:
SNOW LOADS:
WIND LOADS:
FLOORS
STAIRS
LIVE LOADS:
GRADE 36 ASTM F1554
AWS A5.1 OR A5.5 SERIES E70
ASTM A53 GRADE B, Fy=35 KSI
ASTM A500 GRADE B, Fy=46 KSI
ASTM A36, Fy=36 KSI
ASTM 992, Fy=50 KSI
EQUIV LATERAL FORCE
ORDINARY PRECAST SHEAR WALLS
HSS ROUND SHAPES ASTM A500 GRADE B, Fy=42 KSI
IMPORTANCE FACTOR, I
SPECTRAL RESPONSE COEFFICIENT, Sds
SPECTRAL RESPONSE COEFFICIENT, Sd1
SEISMIC RESPONSE COEFFICIENT, Cs
DESIGN BASE SHEAR, V
DESIGN PER 2014 INDIANA BUILDING CODE, UNLESS OTHERWISE NOTED.
ALL REINFORCING STEEL ASTM A615 GRADE 60. REINFORCING STEEL SHOWN ON THESE
DRAWINGS TO BE WELDED SHALL BE ASTM A706.
WELDABLE BARS
20 PSF
100 PSF
40 PSF
20 PSF
21.8 PSF
1.0
1.0
1.2
1.0
0.159
0.086
C
0.127
0.097
B
BEARING WALL
3
0.042
0.042W
F'C=3000 PSI
F'C=3000 PSI
F'C=4000 PSI
F'C=5000 PSI
F'M= 1500 PSI
3/4"ø ASTM A325
ASTM A108
ASTM A496
ASTM A706
SSPC PAINT 25
5500 PSF
SHAPE FACTORS
DIRECTIONALITY FACTOR (Kd)
INTERNAL PRESSURE COEFFICIENT
ENCLOSURE CLASSIFICATION
WIND EXPOSURE
RISK CATEGORY
MEAN ROOF HEIGHT
ULTIMATE WIND SPEED: (ASCE 7-10)115 MPH
36 FT
II
C
ENCLOSED
± 0.18
0.85
PER CODE
NOMINAL WIND SPEED:89.1 MPH
FASTENERS
EXPANSION BOLTS SHALL BE HILTI KWIK BOLT 3, SIMPSON STRONG-TIE STRONG-BOLT2 OR
APPROVED EQUAL, UON. EMBEDMENT DEPTH INTO CONCRETE OR SOLID GROUTED MASONRY
SHALL BE AT LEAST 7 TIMES THE BOLT DIAMETER. CLEAN HOLE AND INSTALL PER
MANUFACTURER'S PRINTED INSTRUCTIONS.
ADHESIVE ANCHORING (EPOXY) FOR CONCRETE SHALL BE HILTI HIT-HY 200 CARTRIDGE
SYSTEM, SIMPSON STRONG-TIE AT-XP OR APPROVED EQUAL, UON. EMBEDMENT DEPTH SHALL
BE AT LEAST 12 TIMES THE INSERT DIAMETER, UON. HOLE DIAMETER SHALL BE NO GREATER
THAN RECOMMENDED BY MANUFACTURER. THE HOLE SHALL BE CLEANED PER
MANUFACTURER'S RECOMMENDATIONS BY BRUSHING OUT WITH WIRE BOTTLE BRUSH AND
BLOWN OUT WITH AIR USING A COMPRESSOR WITH A FUNCTIONAL OIL TRAP (EXCEPT WHERE
PERMITTED WHEN USING A HILTI SAFE SET HIT Z ANCHOR ROD OR HILTI HOLLOW DRILL BIT W/
VACUUM). INSTALLATION SHALL BE IN ACCORDANCE WITH MANUFACTURER'S PRINTED
INSTRUCTIONS AND PERFORMED BY AN INSTALLER TRAINED BY THE MANUFACTURER.
ADHESIVE ANCHORING (EPOXY) FOR MASONRY SHALL BE HILTI HIT-HY 70 CARTRIDGE SYSTEM
OR APPROVED EQUAL, UON. EMBEDMENT DEPTH INTO SOLID GROUTED MASONRY SHALL BE AT
LEAST 9 TIMES THE INSERT DIAMETER, UON. HOLE DIAMETER SHALL BE NO GREATER THAN
RECOMMENDED BY MANUFACTURER. HOLES SHALL NOT BE PLACED WITHIN 1" OF A VERTICAL
MORTAR JOINT. CLEAN HOLE AND INSTALL IN ACCORDANCE WITH MANUFACTURER'S PRINTED
INSTRUCTIONS AND PERFORMED BY AN INSTALLER TRAINED BY THE MANUFACTURER.
SCREW ANCHORS SHALL BE HILTI KWIK HUS-EZ, SIMPSON STRONG-TIE TITEN HD OR APPROVED
EQUAL, UON. EMBEDMENT IN CONCRETE OR SOLID GROUTED MASONRY SHALL BE AT LEAST 9
TIMES THE BOLT DIAMETER. CLEAN HOLE AND INSTALL PER MANUFACTURER'S PRINTED
INSTRUCTIONS.
POWER ACTUATED FASTENERS (PAF) SHALL BE 0.157" DIAMETER HILTI X-U, SIMPSON STRONG-
TIE PDPA OR EQUAL, UON. EMBED MIN 1-1/4" INTO CONCRETE AND CMU. DO NOT PLACE WITHIN
1" OF CMU MORTAR JOINT. PAF SHALL COMPLETELY PENETRATE STRUCTURAL STEEL.
ASTM A185
ALL OTHER CONCRETE F'C=3000 PSI
CONCRETE
UNLESS OTHERWISE NOTED (UON) ON THE DRAWINGS, MINIMUM COVER FOR REINFORCING SHALL BE AS
FOLLOWS:
FOOTINGS .......................................................................................................................................... 3"
COLUMNS AND PEDESTALS (OVER VERTICAL REINF) ..................................................................2"
SLABS AND WALLS (EXPOSED TO EARTH, LIQUID OR WEATHER) ..............................................2"
SLABS AND WALLS (NOT EXPOSED TO EARTH, LIQUID OR WEATHER) ...................................3/4"
CANOPY SLABS ........................................................................................................................... 1 1/2"
BEAMS (OVER MAIN REINFORCING) ..........................................................................................1 1/2"
SLABS ON GRADE ......................................................................................................... 2" FROM TOP
ALL REINFORCING SHALL BE HELD SECURELY IN POSITION WITH STANDARD ACCESSORIES
IN CONFORMANCE WITH CRSI MANUAL OF STANDARD PRACTICE AND ACI 315 DURING
THE PLACING OF THE CONCRETE.
UNLESS OTHERWISE NOTED, SPLICES IN REINFORCING, WHERE PERMITTED, SHALL BE AS FOLLOWS:
WELDED WIRE FABRIC ............................................. WIRE SPACING PLUS 6"
REINFORCING BARS .................................................. 40 BAR DIAMETERS
ALL HOOKS IN REINFORCING BARS SHALL BE AN ACI STANDARD HOOK, UNLESS OTHERWISE NOTED.
IN TWO-WAY SLABS, PLACE SHORT SPAN BARS IN OUTER LAYER.
DOWELS FROM FOUNDATIONS OR SLABS TO WALLS SHALL MATCH WALL REINFORCING, UNLESS
OTHERWISE NOTED. DOWELS SHALL BE PLACED BEFORE CONCRETE IS POURED. THEY SHALL NOT BE
PUSHED INTO THE CONCRETE.
PROVIDE 3/4" CHAMFER AT ALL EXPOSED CORNERS OF BEAMS, WALL, ETC.
PRIOR TO CONSTRUCTION, CONCRETE WALL ELEVATION DRAWINGS SHALL BE SUBMITTED FOR REVIEW
WITH A MINIMUM SCALE OF 1/8" = 1'-0". WALL ELEVATIONS SHALL INDICATE LOCATIONS OF STEEL
EMBEDS, BEARING POCKETS, AND WALL OPENINGS. THE CONTRACTOR IS RESPONSIBLE FOR
COORDINATION OF STEEL EMBEDS, BEARING POCKETS, AND WALL OPENINGS WITH THE CONCRETE
REINFORCEMENT DRAWINGS.
SPECIFICATIONS
CONCRETE WORK SHALL CONFORM TO THE REQUIREMENTS OF ACI 301. "SPECIFICATIONS FOR
STRUCTURAL CONCRETE FOR BUILDINGS" (LATEST EDITION). EXCEPT AS MODIFIED BY THE
REQUIREMENTS OF THE CONTRACT DOCUMENTS. THE CONTRACTOR SHALL EMPLOY AND PAY AN
INDEPENDENT TESTING LABORATORY TO PERFORM CONCRETE TESTING.
MASONRY CONSTRUCTION AND MATERIALS SHALL CONFORM TO THE REQUIREMENTS OF
"SPECIFICATIONS FOR MASONRY STRUCTURES - ACI 530.1/ASCE 6" (LATEST EDITION), EXCEPT AS
MODIFIED BY REQUIREMENTS OF THE CONTRACT DOCUMENTS. THE CONTRACTOR SHALL EMPLOY AND
PAY AN INDEPENDENT TESTING LABORATORY TO PERFORM MASONRY TESTING.
ALL STRUCTURAL STEEL WORK SHALL BE IN ACCORDANCE WITH THE LATEST EDITIONS OF AISC
"SPECIFICATIONS FOR STRUCTURAL STEEL BUILDINGS", AISC "CODE OF STANDARD PRACTICE FOR
STEEL BUILDINGS AND BRIDGES", AND AWS D1.1" "STRUCTURAL WELDING CODE", EXCEPT AS MODIFIED
BY THE REQUIREMENTS OF THE CONTRACT DOCUMENTS. PROOF OF WELDER CERTIFICATION SHALL
BE AVAILABLE AT THE JOB SITE DURING TIMES OF INSPECTION.
BOLTED CONNECTIONS SHALL BE ASSEMBLED AND INSPECTED IN ACCORDANCE WITH RESEARCH
COUNCIL ON STRUCTURAL CONNECTIONS "SPECIFICATIONS FOR STRUCTURAL JOINTS USING ASTM
A325 OR A490 BOLTS".
BOLTED AND WELDED CONNECTIONS: THE CONTRACTOR SHALL EMPLOY AND PAY AN INDEPENDENT
TESTING LABORATORY TO INSURE THAT ALL FASTENERS AND WELDS ARE INSTALLED IN ACCORDANCE
WITH THE SPECIFICATIONS. A VISUAL INSPECTION SHALL BE MADE OF ALL WELDED AND BOLTED
CONNECTIONS. IN ADDITION, A MINIMUM OF 10% OF ALL HIGH STRENGTH BOLTS SHALL BE CHECKED
FOR PROPER TENSION AND A MINIMUM OF 10% OF ALL FULL PENETRATION WELDS SHALL BE CHECKED
BY ULTRASONIC TESTING. ADDITIONAL BOLTS AND WELDS MAY BE TESTED AT THE OPTION OF THE
TESTING LAB REPRESENTATIVE. DEFECTIVE BOLTS OR WELDS SHALL BE REMOVED AND REPLACED AT
NO ADDITIONAL COST TO THE OWNER.
FOOTING AND SLAB SUBGRADE PREPARATION SHALL BE IN ACCORDANCE WITH RECOMMENDATIONS
OF THE GEOTECHNICAL REPORT FOR THE PROJECT PREPARED BY GEOTRACK TECHNOLOGIES, INC.
(DATED OCTOBER 10, 2012), AND SHALL BE IN COMPLIANCE WITH APPLICABLE REQUIREMENTS OF
GOVERNING AUTHORITIES HAVING JURISDICTION.
A GEOTECHNICAL TESTING AND INSPECTION FIRM SHALL BE EMPLOYED TO PERFORM A SOIL SURVEY
FOR SATISFACTORY SOIL MATERIALS, SAMPLING AND TESTING FOR QUALITY CONTROL AS PER THE
RECOMMENDATIONS OF THE GEOTECHNICAL REPORT FOR THIS PROJECT. ALL EARTHWORK
OPERATIONS SHALL BE PERFORMED TO THE SATISFACTION OF THE GEOTECHNICAL TESTING FIRM.
SUPPLEMENTARY NOTES
PROVIDE ALL TEMPORARY BRACING, SHORING, GUYING OR OTHER MEANS TO AVOID EXCESSIVE
STRESSES AND TO HOLD STRUCTURAL ELEMENTS IN PLACE DURING CONSTRUCTION. THE
STRUCTURE SHOULD NOT BE CONSIDERED STABLE UNTIL ALL STRUCTURAL ELEMENTS HAVE
BEEN CONSTRUCTED IN ACCORDANCE WITH THE CONTRACT DOCUMENTS.
MCVEIGH & MANGUM ENGINEERING, INC OR ANY OF IT'S EMPLOYEES SHALL NOT HAVE CONTROL
OR BE RESPONSIBLE FOR CONSTRUCTION MEANS, METHODS, TECHNIQUES, PROCEDURES OR
SEQUENCES FOR THE ACTS OR OMISSIONS OF THE CONTRACTOR OR ANY OTHER PERSONS
PERFORMING THE WORK, OR FOR THE FAILURE OF ANY OF THEM TO CARRY OUT THE WORK IN
ACCORDANCE WITH THE CONTRACT DOCUMENTS.
VISUAL OBSERVATIONS OF THE STRUCTURAL SYSTEM BY MCVEIGH & MANGUM ENGINEERING FOR
GENERAL CONFORMANCE TO THE APPROVED PLANS AND SPECIFICATIONS DOES NOT INCLUDE
OR WAIVE THE RESPONSIBILITY FOR THE INSPECTIONS REQUIRED BY THE INTERNATIONAL
BUILDING CODE.
VERIFY ALL DIMENSIONS WITH ARCHITECTURAL DRAWINGS.
SEE ARCHITECTURAL, MECHANICAL, ELECTRICAL AND PLUMBING DRAWINGS FOR EMBEDS,
OPENINGS, SLEEVES, ETC. NOT SHOWN ON THE STRUCTURAL DRAWINGS.
ALL STRUCTURAL OPENINGS AROUND OR AFFECTED BY MECHANICAL, ELECTRICAL AND
PLUMBING EQUIPMENT SHALL BE VERIFIED WITH EQUIPMENT PURCHASED BEFORE PROCEEDING
WITH STRUCTURAL WORK AFFECTED.
CONTRACTOR SHALL VERIFY ALL EXISTING DIMENSIONS AND CONDITIONS OF EXISTING
STRUCTURE AND SITES THAT ARE AFFECTED BY NEW WORK BEFORE PROCEEDING WITH
FABRICATION AND CONSTRUCTION.
SHOP DRAWINGS AND SUBMITTALS
SHOP DRAWING SUBMITTALS ARE ONLY REVIEWED FOR GENERAL CONFORMANCE WITH THE
INFORMATION SHOWN ON THE CONSTRUCTION DOCUMENTS. THE GENERAL CONTRACTOR MUST
REVIEW AND APPROVE THE SHOP DRAWINGS PRIOR TO THEIR SUBMITTAL TO THE ARCHITECT.
SUBMITTALS WHICH DO NOT CONTAIN THE CONTRACTOR'S SHOP DRAWING STAMP SHALL BE
RETURNED WITHOUT REVIEW. ANY REQUESTED CHANGES TO THE CONTRACT DOCUMENTS
SHALL BE COMMUNICATED IN WRITING PRIOR TO SUBMITTING THE SHOP DRAWINGS AND
CLOUDED ON THE SHOP DRAWINGS.
COMPLETE SHOP DRAWINGS FOR CONSTRUCTION OF EACH BUILDING COMPONENT NOT
DESIGNED BY THE DESIGN TEAM OF RECORD AND NOT SPECIFIED ON THE PROJECT
CONSTRUCTION DOCUMENTS SHALL BE SIGNED AND SEALED BY A PROFESSIONAL ENGINEER
REGISTERED IN THE STATE OF THE PROJECT AND SHALL BE AVAILABLE AT THE JOB SITE DURING
TIMES OF INSPECTION.
SOME STRUCTURAL SYSTEMS ARE DEFINED AS VENDOR-DESIGNED COMPONENTS PER THE
STRUCTURAL DOCUMENTS. THESE ELEMENTS OF THE DESIGN ARE DEFERRED SUBMITTAL
COMPONENTS AND HAVE NOT BEEN PERMITTED UNDER THE BASE BUILDING APPLICATION.
VENDOR-DESIGNED COMPONENT SHOP DRAWINGS SHALL BE APPROVED BY THE COMPONENT
DESIGNER ENGINEER PRIOR TO CURSORY REVIEW BY THE ENGINEER OF RECORD FOR LOADS
IMPOSED ON THE BASE STRUCTURE. THE COMPONENT DESIGNER IS RESPONSIBLE FOR CODE
CONFORMANCE AND ALL NECESSARY CONNECTIONS NOT SPECIFICALLY CALLED OUT ON
ARCHITECTURAL OR STRUCTURAL DRAWINGS. SHOP DRAWINGS SHALL INDICATE MAGNITUDE
AND DIRECTION OF ALL LOADS IMPOSED ON BASIC STRUCTURE. THE CONTRACTOR SHALL
SUBMIT THE STAMPED COMPONENT SYSTEM DOCUMENTS TO THE BUILDING OFFICIAL FOR
APPROVAL.
COMPONENT & CLADDING DESIGN
WIND PRESSURES (PSF)
ROOF
WALLS
ZONE
1
2
3
10 SF 50 SF 100 SF
ZONE 10 SF 100 SF 500 SF
4
4p
5
5p
NOTES:
1) TABLE PRESSURES ARE FOR THE SQUARE FOOT
(SF) TRIBUTARY AREA SHOWN. FOR OTHER
TRIBUTARY AREAS, LINEARLY INTERPOLATE
BETWEEN VALUES SHOWN ABOVE.
2) POSITIVE PRESSURES ACT TOWARD THE
BUILDING. NEGATIVE PRESSURES ACT AWAY
FROM THE BUILDING.
3) SEE DIAGRAMS FOR LOCATION OF ZONES.
10.0 psf 10.0 psf 10.0 psf
-20.8 psf -19.5 psf -19.0 psf
-34.8 psf -26.2 psf -22.5 psf
-34.8 psf -26.2 psf -22.5 psf
-29.9 psf -28.7 psf -28.2 psf
-29.9 psf -28.7 psf -28.2 psf
16.2 psf 14.3 psf
-17.8 psf -15.8 psf
48.6 psf 33.1 psf 31.1 psf
-34.0 psf -28.3 psf -24.3 psf
-25.3 psf -19.7 psf -15.8 psf
48.6 psf 33.1 psf 31.1 psf
-38.9 psf -30.2 psf -24.3 psf
19.0 psf
-20.6 psf
16.2 psf 14.3 psf19.0 psf
OVERHANG
ZONE 1&2
OVERHANG
ZONE 3
19.0 psf 17.1 psf 16.2 psf
19.0 psf 17.1 psf 16.2 psf
a=36'-10"
N
GENERAL SYMBOLS
PLAN, SECTION OR DETAIL NO
SHEET NUMBER
KEYED NOTE TO PLAN
NORTH ARROW
1
S
STRUCTURAL ABBREVIATIONS
1
FB
FD
FDN
FF
FLR
FTG
FS
GA
GALV
GC
HGT
HORIZ
HSA
HT
IF
INFO
INT
JNT
JST
LB
LG
LLH
LLV
LSH
LSV
MANUF
MAT'L
MAX
MECH
MIN
MISC
NIC
NO
NTS
NS
OC
OD
OF
O/O
OPNG
OPP
PERP
PL
PNL
PREFAB
PSF
PSI
QTY
FLAT BAR
FLOOR DRAIN
FOUNDATION
FINISH FLOOR
FLOOR
FOOTING
FAR SIDE
GAGE
GALVANIZED
GENERAL CONTRACTOR
HEIGHT
HORIZONTAL
HEADED STUD ANCHOR
HEIGHT
INSIDE FACE
INFORMATION
INTERIOR
JOINT
JOIST
POUND
LONG
LONG LEG HORIZONTAL
LONG LEG VERTICAL
LONG SIDE HORIZONTAL
LONG SIDE VERTICAL
MANUFACTURER
MATERIAL
MAXIMUM
MECHANICAL
MINIMUM
MISCELLANEOUS
NOT IN CONTRACT
NUMBER
NOT TO SCALE
NEAR SIDE
ON CENTER
OUTSIDE DIAMETER
OUTSIDE FACE
OUT TO OUT
OPENING
OPPOSITE
PERPENDICULAR
PLATE
PANEL
PREFABRICATED
POUNDS PER SQUARE FOOT
POUNDS PER SQUARE INCH
QUANTITY
#
ø
□
&
@
ALUM
AR
ARCH
ASSY
B/
BETWN
BOT
BM
BLDG
BPL
BRG
C TO C
CANT
CJ
CL
CLR
CMU
COL
CONC
CONN
CONST
CONT
CONTR
CTR
CTRD
DBA
DEFL
DET
DIAG
DIA
DIFF
DIM
DO
DWG
EA
EF
EJ
EL
ELEC
ELEV
ENGR
EQ
EQUIP
EXIST
EXP
EXT
EW
NUMBER OR POUND
ROUND OR DIAMETER
SQUARE
AND
AT
ALUMINUM
ANCHOR ROD
ARCHITECTURE
ASSEMBLY
BOTTOM OF
BETWEEN
BOTTOM
BEAM
BUILDING
BASE PLATE
BEARING
CENTER TO CENTER
CANTILEVER
CONSTRUCTION JOINT
CENTER LINE
CLEAR
CONCRETE MASONRY UNIT
COLUMN
CONCRETE
CONNECTION
CONSTRUCTION
CONTINUOUS
CONTRACTION
CENTER
CENTERED
DEFORMED BAR ANCHOR
DEFLECTION
DETAIL
DIAGONAL
DIAMETER
DIFFERENT
DIMENSION
DITTO
DRAWING
EACH
EACH FACE
EXPANSION JOINT
ELEVATION
ELECTRICAL
ELEVATOR
ENGINEER
EQUAL
EQUIPMENT
EXISTING
EXPANSION
EXTERIOR
EACH WAY
R OR RAD
RD
REF
REINF
REQ
REQ'D
RET
REV
SCHED
SECT
SIM
SPA
SPEC
SQ
STD
STIFF
STL
STR
STRUCT
SYM
T&B
T/
T/U PANEL
TE
THK
THRD
TRANSV
TS
TYP
UON
VER
VERT
W/
W/O
WS
WWF
RADIUS
ROUND
REFERENCE
REINFORCE(MENT)
REQUIRE
REQUIRED
RETAINING
REVISION
SCHEDULE
SECTION
SIMILAR
SPACE
SPECIFICATION
SQUARE
STANDARD
STIFFENER
STEEL
STRAIGHT
STRUCTURAL
SYMMETRICAL
TOP & BOTTOM
TOP OF
TILT-UP PANEL
THICKENED EDGE
THICK
THREADED
TRANSVERSE
THICKENED SLAB
TYPICAL
UNLESS OTHERWISE NOTED
VERIFY
VERTICAL
WITH
WITHOUT
WATERSTOP
WELDED WIRE FABRIC
FOUNDATION TYPE
REVISION NUMBER
FOOTING STEP
1
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
2
:
0
3
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S0.1
STRUCTURAL
GENERAL NOTES
& DESIGN
CRITERIA
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 3/4" = 1'-0"S0.1
1 COMPONENTS AND CLADDING LOADS1
1705.3 Concrete Construction
1. Inspection of reinforcing steel
installation (see 1705.2.2 for welding)Shop (3) and field inspection Periodic
2. Inspection of prestressing steel
installation Shop (3) and field inspection Periodic
3. Inspection of anchors cast in
concrete where allowable loads have
been increased per section 1908.5 or
where strength design is used
Shop (3) and field inspection Periodic
4. Inspection of anchors and
reinforcing steel post-installed in
hardened concrete: Per research
reports including verification of
anchor
type, anchor dimensions, hole
dimensions, hole cleaning
procedures, anchor spacing, edge
distances, concrete minimum
thickness, anchor embedment and
tightening torque
Field inspection
Periodic or as
required by the
research report
issued by an
approved source
5. Verify use of approved design mix Shop (3) and field inspection Periodic
6. Fresh concrete sampling, perform
slump and air content tests and
determine temperature of concrete Shop (3) and field inspection Continuous
7. Inspection of concrete and
shotcrete placement for proper
application techniques Shop (3) and field inspection Continuous
8. Inspection for maintenance of
specified curing temperature and
techniques Shop (3) and field inspection Periodic
9. Inspection of prestressed concrete:Shop (3) and field inspection
a. Application of prestressing forceContinuous
b. Grouting of bonded prestressing
tendons in the
seismic-force-resisting system
Continuous
10. Erection of precast concrete
members
a. Inspect in accordance with
construction documents Field inspection
In accordance with
construction
documents
b. Perform inspections of welding
and bolting in accordance with
Section 1705.2
Field inspection In accordance with
Section 1705.2
11. Verification of in-situ concrete
strength, prior to stressing of tendons
in post tensioned concrete and prior
to removal of shores and forms from
beams and structural slabs
Review field testing and
laboratory reports Periodic
12. Inspection of formwork for shape,
lines, location and dimensions Field inspectionPeriodic
13. Concrete strength testing and
verification of compliance with
construction documents
Field testing and review of
laboratory reports Periodic
SCHEDULE OF STRUCTURAL INSPECTIONS
PROJECT
APPLICABLE TO THIS PROJECT
MATERIAL / ACTIVITYSERVICEY/N EXTENT AGENT*DATE COMPLETED
1704.2.5 Inspection of
Fabricators
Verify fabrication/quality control
procedures In-plant review (3)
1705.1.1 Special Cases(work
unusual in nature, including but not
limited to alternative materials and
systems, unusual design applications,
materials and systems with special
manufacturer's requirements)
Submittal review, shop
(3)
and/or field inspection
1705.2 Steel Construction
1. Fabricator and erector documents
(Verify reports and certificates as
listed in AISC 360, chapter N,
paragraph 3.2 for compliance with
construction documents)
Submittal ReviewEach submittal
2. Material verification of structural
steel Shop (3) and field inspection Periodic
3. Embedments (Verify diameter,
grade, type, length, embedment. See
1705.3 for anchors)
Field inspectionPeriodic
4. Verify member locations, braces,
stiffeners, and application of joint
details at each connection comply
with construction documents
Field inspectionPeriodic
5. Structural steel welding:
a. Inspection tasks Prior to Welding
(Observe, or perform for each
welded joint or member, the QA
tasks listed in AISC 360, Table
N5.4-1)
Shop (3) and field inspection Observe or Perform
as noted (4)
b. Inspection tasks During Welding
(Observe, or perform for each
welded joint or member, the QA
tasks listed in AISC 360, Table
N5.4-2)
Shop (3) and field inspectionObserve (4)
c. Inspection tasks After Welding
(Observe, or perform for each
welded joint or member, the QA
tasks listed in AISC 360, Table
N5.4-3)
Shop (3) and field inspection Observe or Perform
as noted (4)
d. Nondestructive testing (NDT) of
welded joints:see Commentary
1) Complete penetration groove
welds 5/16" or greater in risk
category III or IV
Shop (3) or field ultrasonic
testing - 100%Periodic
2) Complete penetration groove
welds 5/16" or greater in risk
category II
Shop (3) or field ultrasonic
testing - 10% of welds
minimum
Periodic
3) Thermally cut surfaces of
access holes when material t > 2"
Shop (3) or field magnetic
Partical or Penetrant testing Periodic
4) Welded joints subject to fatigue
when required by AISC 360,
Appendix 3, Table A-3.1
Shop (3) or field radiographic
or
Ultrasonic testing
Periodic
5) Fabricator's NDT reports when
fabricator performs NDT Verify reports Each submittal (5)
6. Structural steel bolting:Shop (3) and field inspection
a. Inspection tasks Prior to Bolting
(Observe, or perform tasks for each
bolted connection, in accordance
with QA tasks listed in AISC 360,
Table N5.6-1)
Observe or Perform
as noted (4)
b.Inspection tasks During Bolting
(Observe the QA tasks listed in
AISC 360, Table N5.6-2)
Observe (4)
1) Pre-tensioned and slip-critical
joints
a) Turn-of-nut with matching
markings Periodic
b) Direct tension indicator Periodic
c) Twist-off type tension control
bolt Periodic
d) Turn-of-nut without matching
markings Continuous
e) Calibrated wrench Continuous
2) Snug-tight joints Periodic
c. Inspection tasks After Bolting
(Perform tasks for each bolted
connection in accordance with QA
tasks listed in AISC 360, Table
N5.6-3)
Perform (4)
7. Inspection of steel elements of
composite construction prior to
concrete placement in accordance
with QA tasks listed in AISC 360,
Table N6.1
Shop (3) and field inspection
and testing
Observe or Perform
as noted (4)
1705.2.2 Steel Construction
Other Than Structural Steel
1. Material verification of cold-formed
steel deck:
a. Identification markingsField inspectionPeriodic
b. Manufacturer's certified test
reports Submittal ReviewEach submittal
2. Connection of cold-formed steel
deck to supporting structure:Shop (3) and field inspection
a. Welding Periodic
b. Other fasteners (in accordance
with AISC 360,Section N6)
1) Verify fasteners are in
conformance with approved
submittal
Periodic
2) Verify fastener installation is in
conformance with approved
submittal and manufacturer's
recommendations
Periodic
3. Reinforcing steel Shop (3) and field inspection
a. Verification of weldability of steel
other than ASTM A706 Periodic
b. Reinforcing steel resisting flexural
and axial forces in intermediate and
special moment frames, boundary
elements of special concrete
structural walls and shear
reinforcement
Continuous
c. Shear reinforcementContinuous
d. Other reinforcing steelPeriodic
4. Cold-formed steel trusses spanning
60 feet or greater
a. Verify temporary and permanent
restraint/bracing are installed in
accordance with the approved truss
submittal package
Field inspectionPeriodic
1705.4 Masonry Construction
(A) Level A, B and C Quality
Assurance:
1. Verify compliance with approved
submittals Field InspectionPeriodic
(B) Level B Quality Assurance:
1. Verification of f'm and f'C prior to construction
Testing by unit strength
method
or prism test method
Periodic
(C) Level C Quality Assurance:
1. Verification of f'm and f'C prior to construction and for
every 5,000 SF during
construction
Testing by unit strength
method
or prism test method
Periodic
2. Verification of proportions of
materials in premixed or
preblended mortar, prestressing
grout, and grout other than
self-consolidating grout, as
delivered to the project site
Field inspectionContinuous
3. Verify placement of
masonry
units
Field InspectionPeriodic
(D) Levels B and C Quality
Assurance:
1. Verification of Slump Flow and
Visual Stability Index (VSI) of
self-consolidating grout as
delivered to the project
Field testingContinuous
2. Verify compliance with approved
submittals Field inspectionPeriodic
3. Verify proportions of site-mixed
mortar, grout and prestressing
grout for bonded tendons
Field InspectionPeriodic
4. Verify grade, type, and size of
reinforcement and anchor bolts,
and prestressing tendons and
anchorages
Field InspectionPeriodic
5. Verify construction of mortar
joints Field InspectionPeriodic
6. Verify placement of
reinforcement, connectors, and
prestressing tendons and
anchorages
Field InspectionLevel B - Periodic
Level C - Continuous
7. Verify grout space prior to Field InspectionLevel B - Periodic
grouting Level C - Continuous
8. Verify placement of grout and
prestressing grout for bonded
tendons
Field InspectionContinuous
9. Verify size and location of
structural masonry elements Field InspectionPeriodic
10. Verify type, size, and location
of anchors, including details of
anchorage of masonry to structural
members, frames, or other
construction.
Field inspectionLevel B - Periodic
Level C - Continuous
11. Verify welding of reinforcement
(see 1705.2.2)Field inspectionContinuous
12. Verify preparation,
construction, and protestion of
masonry during cold weather
(temperature below 40oF) or hot
weather (temperature above 90o F)
Field inspectionPeriodic
13. Verify application and
measurement of prestressing
force
Field InspectionContinuous
14. Verify placement of AAC
masonry units and construction of
thin-bed mortar joints (first 5000
SF of AAC masonry)
Field inspectionContinuous
15. Verify placement of AAC
masonry units and construction of
thin-bed mortar joints (after the first
5000 SF of AAC masonry)
Field inspection
Level B - Periodic
Level C - Continuous
16. Verify properties of thin-bed
mortar for AAC masonry (first
5000 SF of AAC masonry)
Field inspectionContinuous
17. Verify properties of thin-bed
mortar forAAC masonry (after the
first 5000 SF of AAC masonry)
Field inspection Level B - Periodic
Level C - Continuous
18. Prepare grout and mortar
specimens Field testingLevel B - Periodic
Level C - Continuous
19. Observe preparation of prismsField inspectionLevel B - Periodic
Level C - Continuous
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
N
N
N
Y
Y
Y
Y
N
Y
N
Y
Y
Y
N
N
Y
N
N
N
N
N
N
N
Y
N
Y
N
Y
Y
NOTE: DENOTES "NOT APPLICABLE"
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
2
:
1
0
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S0.2
SCHEDULE OF
STRUCTURAL
INSPECTIONS
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
1705.11.4 Designated
Seismic
Systems Verification
Inspect and verify that that the
component label, anchorage or
mounting conforms to the certificate of
compliance in accordance with
Section 1705.12.3
Field inspectionPeriodic
1705.11.5 Architectural
Components Special
Inspections for Seismic
Resistance
1. Inspection during the erection and
fastening of exterior cladding and
interior and exterior veneer
Field inspectionPeriodic
2. Inspection during the erection and
fastening of interior and exterior
nonbearing walls
Field inspectionPeriodic
3. Inspection during anchorage of
access floors Field inspectionPeriodic
1705.11.6 Mechanical and
Electrical Components Special
Inspections for Seismic
Resistance
1. Inspection during the anchorage of
electrical equipment for emergency or
standby power systems
Field inspectionPeriodic
2. Inspection during the anchorage of
other electrical equipment Field inspectionPeriodic
3. Inspection during installation and
anchorage of piping systems
designed to carry hazardous
materials, and their associated
mechanical units
Field inspectionPeriodic
4. Inspection during the installation
and anchorage of HVAC ductwork
that will contain hazardous
materials
Field inspectionPeriodic
5. Inspection during the installation
and anchorage of vibration isolation
systems
Field inspectionPeriodic
1705.11.7 Storage Racks
Special Inspections for Seismic
Resistance
Inspection during the anchorage of
storage racks 8 feet or greater in
height
Field inspectionPeriodic
1705.11.8 Seismic Isolation
Systems
Inspection during the fabrication and
installation of isolator units and
energy dissipation devices used as
part of the seismic isolation system
Shop and field inspectionPeriodic
1705.5 Wood Construction
1. Inspection of the fabrication
process of wood structural
elements
and assemblies in accordance with
Section 1704.2.5
In-plant review (3)Periodic
2. For high-load diaphragms, verify
grade and thickness of structural
panel sheathing agree with
approved
building plans
Field inspectionPeriodic
3. For high-load diaphragms, verify
nominal size of framing members at
adjoining panel edges, nail or staple
diameter and length, number of
fastener lines, and that spacing
between fasteners in each line and at
edge margins agree with approved
building plans
Field inspectionPeriodic
4. Metal-plate-connected wood
trusses spanning 60 feet or
greater:
verify temporary and permanent
restraint/bracing are installed in
accordance with the approved truss
submittal package
Field inspectionPeriodic
1705.6 Soils
1. Verify materials below shallow
foundations are adequate to achieve
the design bearing capacity.
Field inspectionPeriodic
2. Verify excavations are extended to
proper depth and have reached
proper material.
Field inspectionPeriodic
3. Perform classification and testing of
controlled fill materials.Field inspectionPeriodic
4. Verify use of proper materials,
densities, and lift thicknesses during
placement and compaction of
controlled fill
Field inspectionContinuous
5. Prior to placement of controlled fill,
observe subgrade and verify that site
has been prepared properly
Field inspectionPeriodic
1705.7 Driven Deep Foundations
1. Verify element materials, sizes
and
lengths comply with requirements
Field inspectionContinuous
2. Determine capacities of test
elements and conduct additional load
tests, as required
Field inspectionContinuous
3. Observe driving operations and
maintain complete and accurate
records for each element
Field inspectionContinuous
4. Verify placement locations and
plumbness, confirm type and size of
hammer, record number of blows per
foot of penetration, determine
required penetrations to achieve
design capacity, record tip and butt
elevations and document any
damage
to foundation element
Field inspectionContinuous
5. For steel elements, perform
additional inspections per Section
1705.2
See Section 1705.2See Section 1705.2
6. For concrete elements and
concrete-filled elements, perform
additional inspections per Section
1705.3
See Section 1705.3See Section 1705.3
7. For specialty elements, perform
additional inspections as determined
by the registered design
professional
in responsible charge
Field inspection In accordance with
construction
documents
8. Perform additional inspections
and
tests in accordance with the
construction documents
Field Inspection and testing
In accordance with
construction
documents
1705.8 Cast-in-Place Deep
Foundations
1.Observe drilling operations and
maintain complete and accurate
records for each element
Field inspectionContinuous
2. Verify placement locations and
plumbness, confirm element
diameters, bell diameters (if
applicable), lengths, embedment into
bedrock (if applicable) and adequate
end-bearing strata capacity. Record
concrete or grout volumes
Field inspectionContinuous
3. For concrete elements, perform
additional inspections in accordance
with Section 1705.3
See Section 1705.3See Section 1705.3
4. Perform additional inspections and
tests in accordance with the
construction documents
Field Inspection and testing
In accordance with
construction
documents
1705.9 Helical Pile Foundations
1. Verify installation equipment, pile
dimensions, tip elevations, final depth,
final installation torque and other data
as required.
Field inspectionContinuous
2. Perform additional inspections and
tests in accordance with the
construction documents
Field Inspection and testing
In accordance with
construction
documents
1705.10.1 Structural Wood
Special Inspections For Wind
Resistance
1. Inspection of field gluing operations
of elements of the main
windforce-resisting system
Field inspectionContinuous
2. Inspection of nailing, bolting,
anchoring and other fastening of
components within the main
windforce-resisting system
Shop (3) and field inspection Periodic
SCHEDULE OF SPECIAL INSPECTIONS
PROJECT
APPLICABLE TO THIS PROJECT
MATERIAL / ACTIVITYSERVICEY/N EXTENT AGENT*DATE COMPLETED
1705.10.2 Cold-formed Steel
Special Inspections For Wind
Resistance
1.Inspection during welding
operations of elements of the main
windforce-resisting system Shop (3) and field inspection Periodic
2.Inspections for screw attachment,
bolting, anchoring and other fastening
of components within the main
windforce-resisting system
Shop (3) and field inspection Periodic
1705.10.3 Wind-resisting
Components
1. Roof cladding Shop (3) and field inspection Periodic
2. Wall cladding Shop (3) and field inspection Periodic
1705.11.1 Structural Steel
Special Inspections for Seismic
Resistance
Inspection of structural steel in
accordance with AISC 341 Shop (3) and field inspection In accordance with
AISC 341
1705.11.2 Structural Wood
Special Inspections for Seismic
Resistance
1. Inspection of field gluing operations
of elements of the seismic-force
resisting system
Field inspectionContinuous
2. Inspection of nailing, bolting,
anchoring and other fastening of
components within the
seismic-force-resisting system
Shop (3) and field inspection Periodic
1705.11.3 Cold-formed Steel
Light-Frame Construction
Special Inspections for Seismic
Resistance
1. Inspection during welding
operations of elements of the
seismic-force-resisting system Shop (3) and field inspection Periodic
2. Inspections for screw attachment,
bolting, anchoring and other fastening
of components within the
seismic-force-resisting system
Shop (3) and field inspection Periodic
1705.12.1 Concrete
Reinforcement Testing and
Qualification for Seismic
Resistance
1. Review certified mill test reports for
each shipment of reinforcement used
to resist earthquake-induced flexural
and axial forces in reinforced concrete
special moment frames, special
structural walls, and coupling beams
connecting special structural walls
Review certified mill test reportsEach shipment
2. Verify reinforcement weldability of
ASTM A615 reinforcement used to
resist earthquake-induced flexural and
axial forces in reinforced concrete
special moment frames, special
structural walls, and coupling beams
connecting special structural walls
Review test reportsEach shipment
1705.12.2 Structural Steel
Testing and Qualification for
Seismic Resistance
Test in accordance with the quality
assurance requirements of AISC 341 Shop (3) and field testing Per AISC 341
1705.12.3 Seismic Certification
of Nonstructural Components
Review certificate of compliance for
designated seismic system
components.
Certificate of compliance reviewEach submittal
1705.12.4 Seismic Isolation
Systems
Test seismic isolation system in
accordance with ASCE 7 Section
17.8
Prototype testingPer ASCE 7
1705.13 Sprayed Fire-resistant
Materials
1. Verify surface condition preparation
of structural members Field inspectionPeriodic
2. Verify application of sprayed
fire-resistant materials Field inspectionPeriodic
3. Verify average thickness of sprayed
fire-resistant materials applied to
structural members
Field inspectionPeriodic
4. Verify density of the sprayed
fire-resistant material complies with
approved fire-resistant design
Field inspection and testing Per IBC Section
1705.13.5
5. Verify the cohesive/adhesive bond
strength of the cured sprayed
fire-resistant material
Field inspection and testing Per IBC Section
1705.13.6
1705.14 Mastic and Intumescent
Fire-Resistant Coatings
Inspect mastic and intumescent
fire-resistant coatings applied to
structural elements and decks
Field inspectionPeriodic
1705.15 Exterior Insulation and
Finish Systems (EIFS)
1. Verify materials, details and
installations are per the approved
construction documents
Field inspectionPeriodic
2. Inspection of water-resistive barrier
over sheathing substrate Field inspectionPeriodic
1705.16 Fire-Resistant
Penetrations and Joints
1. Inspect penetration firestop systemsField testingPer ASTM E2174
2. Inspect fire-resistant joint systemsField testingPer ASTM E2393
1705.17 Smoke Control Systems
1. Leakage testing and recording of
device locations prior to concealment Field testingPeriodic
2. Prior to occupancy and after
sufficient completion, pressure
difference testing, flow
measurements, and detection and
control verification
Field testingPeriodic
* INSPECTION AGENTS
FIRM ADDRESS TELEPHONE NO.
1.
2.
3.
4.
Notes: 1. The inspection and testing agent(s) shall be engaged by the Owner or the Owner's Agent, and not by the Contractor or Subcontractor whose work is to be inspected or
tested. Any conflict of interest must be disclosed to the Building Official prior to commencing work. The qualifications of the Special Inspector(s) and/or
testing agencies may be subject to the approval of the Building Official and/or the Design Professional.
2. The list of Special Inspectors may be submitted as a separate document, if noted so above.
3. Special Insepctions as required by Section 1704.2.5 are not required where the fabricator is approved in accordance with IBC Section 1704.2.5.2
4. Observe on a random basis, operations need not be delayed pending these inspections. Perform these tasks for each welded joint, bolted connection, or steel element.
5. NDT of welds completed in an approved fabricator's shop may be performed by that fabricator when approved by the AHJ. Refer to AISC 360, N7.
Are Requirements for Seismic Resistance included in the Statement of Special Inspections ?Yes No
Are Requirements for Wind Resistance included in the Statement of Special Inspections ?Yes No
DATE: 7/1/15
Y
Y
Y
Y
Y
6. See sheet S0.2 for Statement of Special Inspections
NOTE: DENOTES "NOT APPLICABLE"
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
2
:
1
5
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S0.3
SCHEDULE OF
STRUCTURAL
INSPECTIONS
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
GD
GA
G1 G8
FOUNDATION PLAN NOTES:
1) SLAB ON GRADE & FOUNDATIONS/TURNDOWNS INDICATED
ARE DESIGNED BASED ON A CONVENTIONAL 12" NW
CONCRETE SLAB. SEE PLAN AND 1/S3.1 FOR SLAB JOINT
LAYOUT AND DETAILING.
2) ELEVATIONS ARE BASED ON LEVEL 1 T/SLAB DATUM EL OF 0'-0"
(ACTUAL ELEVATION = 864'-0"). SEE PLAN FOR TOP OF SLAB
ELEVATIONS AND SLAB STEPS/RAMPS. COORD. w/ARCH &
PRECAST DRAWINGS FOR ACTUAL ELEVATIONS.
3) FOR DESIGN CRITERIA AND GENERAL NOTES, SEE SHEET
S0.1.
4) FOR ELEVATIONS, WALL SECTIONS AND DIMENSIONS, SEE
ARCHITECTURAL AND PRECAST.
5) FOR REINFORCEMENT AT FOOTING CORNERS, SEE DETAIL
4/S3.1.
6) FOR PIPE PENETRATIONS AT FOOTINGS, SEE DETAIL 2&3/S3.1.
7) FOR BRICK LINTEL, SEE DETAIL 3/4.1.
8) FOR REINF AT WALL CORNERS, SEE 10/S3.1.
9) F#.# & WF#.# DENOTE FTG TYPE, SEE SECTIONS, DETAILS AND
FOOTING SCHEDULE SHOWN ON SHEETS S1.1.
10) SLAB SLOPES AT RAMPS AND DRAINS SHALL BE COORDINATED
WITH ARCH AND PRECAST PRIOR TO SLAB ON GRADE
CONSTRUCTION.
11) SEE 4/S3.2 FOR RETAINING WALL JOINT DETAIL.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
2
:
2
2
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S1.1
FOUNDATION &
GROUND FLOOR
PLAN - GARAGE
OVERALL
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/16" = 1'-0"S1.1
1 FOUNDATION PLAN - Overall
FOOTING SCHEDULE
TYPELENGTHWIDTHTHICKNESS
BOTTOM
REINF (LONG
WAY)
BOTTOM
REINF (SHORT
WAY)
TOP REINF
(LONG WAY)
TOP REINF
(SHORT WAY)REMARKS
F8.08'-0"8'-0"2'-1"14 #614 #6
F9.09'-0"9'-0"2'-4"12 #612 #6
F10.010'-0"10'-0"2'-7"14 #614 #6
F11.011'-0"11'-0"2'-9"17 #617 #6
F12.012'-0"12'-0"2'-11"15 #715 #7
WF2.02'-0"1'-0"#6 @ 12" O.C.#6 @ 12" O.C.
WF3.03'-0"1'-6"#5 @ 10" O.C.#5 @ 10" O.C.
WF3.53'-6"1'-6"#6 @ 12" O.C.#6 @ 12" O.C.
WF4.04'-0"1'-6"#6 @ 12" O.C.#6 @ 12" O.C.
WF4.54'-6"1'-6"#6 @ 12" O.C.#6 @ 12" O.C.
WF6.0#5 @ 6" O.C.#5 @ 6" O.C.
CONTINUOUS
CONTINUOUS
1'-6"CONTINUOUS
CONTINUOUS
CONTINUOUS
CONTINUOUS 1'-6"6'-0"
RA
M
P
U
P
TO
L
E
V
E
L
3
(6
%
S
L
O
P
E
)
RA
M
P
D
N
TO
L
E
V
E
L
1
(6
%
S
L
O
P
E
)
156 TOTAL PARKING ON
LEVEL 2 (INCLUDED
RAMPED PARKING)
UP
STAIR 3
THIRD FLOOR
x-stair 3-3
lobby
A
A
ST
A
I
R
5
-
SE
C
O
N
D
FL
O
O
R
x-
s
t
a
i
r
5
-
2
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
6
S4.1
___________
6
S4.1
___________
DRILLED & EPOXY
#4 DOWELS W/ 3"
EMBED @ 24" O.C.
5'
-
1
1
"
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
2
:
2
8
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S1.2
SECOND LEVEL
FRAMING PLAN -
GARAGE
OVERALL
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1" = 20'-0"S1.2
1 2ND FRAMING PLAN - Overall
RA
M
P
U
P
TO
L
E
V
E
L
4
(6
%
S
L
O
P
E
)
RA
M
P
D
N
TO
L
E
V
E
L
2
(6
%
S
L
O
P
E
)
156 TOTAL PARKING ON
LEVEL 3 (INCLUDED
RAMPED PARKING)
UP
STAIR 3THIRD FLOOR
x-stair 3-3
ST
A
I
R
5
-
TH
I
R
D
F
L
O
O
R
x-
s
t
a
i
r
5
-
3
lobby
A
A
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
DRILLED & EPOXY
#4 DOWELS W/ 3"
EMBED @ 24" O.C.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
2
:
3
4
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S1.3
THIRD LEVEL
FRAMING PLAN -
GARAGE
OVERALL
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1" = 20'-0"S1.3
1 3RD FRAMING PLAN - Overall
RA
M
P
D
N
TO
L
E
V
E
L
3
(6
%
S
L
O
P
E
)
156 TOTAL PARKING ON
LEVEL 4 (INCLUDED
RAMPED PARKING)
STAIR 3FOURTHFLOOR
x-stair 3-4
x-
s
t
a
i
r
5
-
4
1'-7 5/8"
lobby
A
A
UP
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
DRILLED & EPOXY
#4 DOWELS W/ 3"
EMBED @ 24" O.C.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
2
:
4
0
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S1.4
FOURTH LEVEL
FRAMING PLAN -
GARAGE
OVERALL
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1" = 20'-0"S1.4
1 4TH FRAMING PLAN - Overall
OS
1
DS
1
OS
2
DS
2
OS
3
DS
3
OS
4
DS
4
RA
M
P
D
N
TO
L
E
V
E
L
3
(6
%
S
L
O
P
E
)
156 TOTAL PARKING ON
LEVEL 4 (INCLUDED
RAMPED PARKING)
DN
STAIR 3FOURTH FLOOR
x-stair 3-4
x-
s
t
a
i
r
5
-
4
1'-7 5/8"
lobby
A
A
UP
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
DRILLED & EPOXY
#4 CMU WALL
DOWELS W/ 3" EMBED
@ 24" O.C.
14'-5 9/16"
11
'
-
1
1
5
/
8
"
5'
-
8
5
/
8
"
PRECAST SLAB
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
2
:
4
6
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S1.5
ROOF PLAN -
GARAGE
OVERALL
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1" = 20'-0"S1.5
1 ROOF PLAN - Overall
dog spa
(219 SF)
maintenance
office
(241 SF)
maintenance
(1537 SF)
trash compactor / recycling
lobby
elev 1
stair 5
crawl
space/void
RAMP UP
(6% SLOPE)
RAMP DN
RAMP DN
1:12
eye wash
dual ht
drinking ftns
service sink
riser room
space provided for
future booster pump
room
LVL 1
98 PARKS TOTAL
(91 STANDARD / 1 ACC
/ 2 VAN / 2 FUTURE RES
/ 2 MAIL SHORT TERM)
mech equip for
maintance
room located in
niche
work
bench
trash
STAIR 5 -
FIRST FLOOR
A
G1.5
G2
G3
GDGCGBGA
G1
23
'
-
9
3
/
4
"
35
'
-
3
1
/
4
"
36
'
-
0
"
63'-4 1/2"62'-8"62'-11"
8'
-
0
"
22'-0 1/8"21'-11 7/8"
44'-0"
8'
-
0
"
22'-0"22'-0"
44'-0"
8" CMU WALL. COORD LOCATION &
HEIGHT W/ ARCH
2
S3.3
___________2
S3.3
___________
2
S3.3
___________
3
S3.3
___________
3
S3.3
___________
3
S3.3
___________
3
S3.3
___________
3
S3.3
___________
3
S3.3
___________
3
S3.3
___________
3
S3.3
___________
3
S3.3
___________
2
S3.3
___________
F 1 2 .0 (1 '-6 ")
F 1 2 .0 (1 '-6 ")
F 8 .0 (-1 '-6 ")
F 1 1 .0 (-1 '-6 ")
F 1 1 .0 (-1 '-6 ")
5
S3.3
___________
3
S3.3
___________
3
S3.3
___________
2
S3.3
___________
2
S3.3
___________78" FOOTING THICKNESS W/ 16#8 LONG. ON
THE BOTTOM AND 15#8 LONG. ON THE TOP.
#6@12" O.C. TRANS. TOP AND BOTTOM
42.5" FOOTING THICKNESS W/ 16#8 LONG
ON THE BOTTOM AND 15#8 LONG ON THE
TOP. #6@12" O.C. TRANS. TOP AND
BOTTOM
2
S3.3
___________
T/FTG EL. +0'-4"
T/FTG EL. +1'-6"
T/FTG EL +2'-0"
1
S3.3
___________
1
S3.3
___________
T/FTG EL. -2'-8"
T/FTG EL.+2'-0"
T/FTG EL. +2'-0"
T/FTG EL. +2'-0"
T/FTG EL. +1'-4"T/FTG +0'-4"
4
S3.2
___________
4
S3.2
___________
4
S3.2
___________
WF
3
.
5
WF
6
.
0
WF
6
.
0
WF2.0
WF
2
.
0
WF
2
.
0
WF2.0
WF2.0
WF2.0
WF
2
.
0
WF
4
.
0
WF3.0
WF
2
.
0
WF2.0
WF
3
.
5
WF3.0
WF3.0
WF
3
.
0
WF
4
.
5
WF3.0
4
S3.3
___________
T/FTG EL. -1'-6"
2
S3.3
___________
2
S3.3
___________
5
S3.3
___________
PROVIDE ADDITIONAL
REINFORCEMENT. #5
@ 4" O.C.
PROVIDE ADDITIONAL
REINFORCEMENT. #5
@ 4" O.C.
35
'
-
3
1
/
4
"
36
'
-
0
"
T/FTG EL. +1'-6"
T/FTG EL. +1'-6"
T/FT EL. +1'-6"
T/FTG EL. -2'-8"
S
S
S
T/FTG EL +2'-0"
S
T/FTG EL. -0'-6"
S
T/FTG EL. +1'-6"
S T/FTG EL. -0'-6"
4
S3.3
___________
4
S3.3
___________
4
S3.3
___________
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
2
:
5
3
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S2.A1
FOUNDATION &
GROUND FLOOR
PLAN - GARAGE
SEGMENT A
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/8" = 1'-0"S2.A1
1 FOUNDATION PLAN - SEGMENT A
NOTES:
1.SEE SHEET S1.1 FOR FOUNDATION PLAN NOTE
RAMP DN
TO LEVEL 1
(6% SLOPE)
156 TOTAL PARKING ON
LEVEL 2 (INCLUDED
RAMPED PARKING)
A
STAIR 5 -
SECOND
FLOOR
x-stair 5-2
G1.5
G2
G3
GDGCGB
G1
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
DRILLED & EPOXY #4 DOWELS W/ 3"
EMBED @ 24" O.C.
6
S4.1
___________
6
S4.1
___________
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
2
:
5
9
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S2.A2
SECOND LEVEL
FRAMING PLAN -
GARAGE
SEGMENT A
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/8" = 1'-0"S2.A2
1 2ND FRAMING PLAN - SEGMENT A
RAMP DN
TO LEVEL 2
(6% SLOPE)
156 TOTAL PARKING ON
LEVEL 3 (INCLUDED
RAMPED PARKING)
STAIR 5 -
THIRD FLOOR
x-stair 5-3
A
G1.5
G2
G3
GDGCGB
G1
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
DRILLED & EPOXY #4 DOWELS W/ 3"
EMBED @ 24" O.C.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
3
:
0
5
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S2.A3
THIRD LEVEL
FRAMING PLAN -
GARAGE
SEGMENT A
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/8" = 1'-0"S2.A3
1 3RD FRAMING PLAN - SEGMENT A
RAMP DN
TO LEVEL 3
(6% SLOPE)
15
6
T
O
T
A
L
P
A
R
K
I
N
G
O
N
LE
V
E
L
4
(
I
N
C
L
U
D
E
D
RA
M
P
E
D
P
A
R
K
I
N
G
)
x-stair 5-4
A
G1.5
G2
G3
GDGCGB
G1
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
DRILLED & EPOXY #4 DOWELS W/ 3"
EMBED @ 24" O.C.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
3
:
1
1
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S2.A4
FOURTH LEVEL
FRAMING PLAN -
GARAGE
SEGMENT A
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/8" = 1'-0"S2.A4
1 4TH FRAMING PLAN - SEGMENT A
OS1
DS1
OS2DS2
RAMP DN
TO LEVEL 3
(6% SLOPE)
156 TOTAL PARKING ON
LEVEL 4 (INCLUDED
RAMPED PARKING)
x-stair 5-4
A
G1.5
G2
G3
GDGCGB
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
DRILLED & EPOXY #4 DOWELS W/ 3"
EMBED @ 24" O.C.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
3
:
1
8
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S2.A5
ROOF FRAMING
PLAN - GARAGE
SEGMENT A
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/8" = 1'-0"S2.A5
1 ROOF PLAN - SEGMENT A
10'-0"
VAN
VAN
electrical mailroom:
REQ'D: 303T/31P
PROV: 304T/32P
(19) 4C09D-16
(8) 4C09D-4P
27 total boxes
stair 3
RAMP UP
TO LEVEL 2
(6% SLOPE)
ELECTRIC
VEHICLE
MAILBOX
SHORT-TERM
PARKING
MAILBOX
SHORT-TERM
PARKING
FUTURE
RESIDENT
FUTURE
RESIDENT
ELECTRIC
VEHICLE
4C09D-164C09D-164C09D-164C09D-164C09D-164C09D-164C09D-164C09D-164C09D-164C09D-16
4C09D-16
4C09D-16
4C09D-16
4C09D-16
4C09D-16
4C09D-164C09D-164C09D-164C09D-164C09D-4P4C09D-4P
4C09D-4P4C09D-4P4C09D-4P
4C09D-4P
4C09D-4P
4C09D-4P
windows above mailboxes
slope at 1:20
STAIR 3
FIRST FLOOR
x-stair 3-1
lobby
A
G4
G5
G6
G7
GDGCGBGA
G7.9
COORD T/WALL W/ PRECAST DETAILS
COORD T/WALL W/
PRECAST DETAILS
COORD T/WALL &
T/SLAB @ RAMP W/
ARCH & PRECAST
LAYOUT
62'-11"62'-8"63'-4 1/2"
36
'
-
0
"
36
'
-
0
"
24
'
-
0
"
35
'
-
0
"
2
S3.2
___________
1
S3.2
___________
1
S3.2
___________
F 1 1 .0 (-1 '-6 ")
F 1 1 .0 (-1 '-6 ")
F 1 0 .0 (-1 '-6 ")
F 9 .0 (-1 '-6 ")
F 1 2 .0 (-2 '-8 ")
F 1 2 .0 (4 ")
F 1 0 .0 (1 '-6 ")
5
S3.3
___________
5
S3.3
___________
3
S3.3
___________
3
S3.3
___________
3
S3.3
___________
___________
S3.1
4
2
S3.3
___________
2
S3.3
___________
T/FTG EL. +1'-6"
T/FTG EL. +1'-6"
T/FTG EL. +1'-6"
T/FTG EL. -2'-0"
1
S3.3
___________
1
S3.3
___________
T/FTG -2'-8"
4
S3.2
___________
4
S3.2
___________
WF3.5 WF3.5
WF2.0WF
2
.
0
WF
3
.
5
WF2.0
WF
2
.
0
WF2.0
WF
2
.
0
WF
2
.
0
S L A B
WF
3
.
0
WF3.0
WF
3
.
0
S L A B
WF3.0
WF
4
.
5
T/FTG EL. -4'-0"
WF
4
.
0
WF
3
.
0
F1
0
.
0
(
-
4
'
-
0
"
)
SS
4
S3.3
___________
2
S3.3
___________
2
S3.3
___________
2
S3.3
___________
5
S3.3
___________
3
S3.3
___________
3
S3.3
___________
36
'
-
0
"
36
'
-
0
"
24
'
-
0
"
T/FTG EL. -1'-6"
T/FTG EL. -0'-6"
T/FTG EL.-4'-0"
T/FTG EL. -2'-0"
T/FTG EL. +1'-6"
T/FTG EL. +0'-4"
S
T/FTG EL. -2'-6"
S
4
S3.3
___________
4
S3.3
___________
S
S
T/FTG EL. -2'-0"
T/FTG EL. -1'-6"
T/FTG EL. +1'-6"
S S
T/FTG EL. -1'-6"
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
3
:
2
4
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S2.B1
FOUNDATION &
GROUND FLOOR
PLAN - GARAGE
SEGMENT B
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/8" = 1'-0"S2.B1
1 FOUNDATION PLAN - SEGMENT B
NOTES:
1.SEE SHEET S1.1 FOR FOUNDATION PLAN NOTE
RAMP UP
TO LEVEL 3
(6% SLOPE)
UP
STAIR 3
THIRD FLOOR
x-stair 3-3
lobby
A
G4
G5
G6
G7
GD
GCGB
GA
G8
G7.9
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
3
:
3
2
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S2.B2
SECOND LEVEL
FRAMING PLAN -
GARAGE
SEGMENT B
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/8" = 1'-0"S2.B2
1 2ND FRAMING PLAN - SEGMENT B
RAMP UP
TO LEVEL 4
(6% SLOPE)
UP
STAIR 3
THIRD FLOOR
x-stair 3-3
lobby
A
G4
G5
G6
G7
GCGB
G8
G7.9
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
3
:
4
3
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S2.B3
THIRD LEVEL
FRAMING PLAN -
GARAGE
SEGMENT B
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/8" = 1'-0"S2.B3
1 3RD FRAMING PLAN - SEGMENT B
STAIR 3
FOURTH
FLOOR
x-stair 3-4
1'-7 5/8"
lobby
A
UP
G4
G5
G6
G7
GD
GCGB
G8
G7.9
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
3
:
5
5
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S2.B4
FOURTH LEVEL
FRAMING PLAN -
GARAGE
SEGMENT B
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/8" = 1'-0"S2.B4
1 4TH FRAMING PLAN - SEGMENT B
OS3
DS3
OS4 DS4
DN
STAIR 3
FOURTH FLOOR
x-stair 3-4
1'-7 5/8"
lobby
A
UP
G5
G6
G7
GB
G8
G7.9
PRECAST PARKING GARAGE.
SUPERSTRUCTURE BY OTHERS.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
A B
Key Plan N
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
4
:
0
1
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S2.B5
ROOF FRAMING
PLAN - GARAGE
SEGMENT B
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 1/8" = 1'-0"S2.B5
1 ROOF PLAN - SEGMENT B
STOP REINF (IF REQ'D)
EACH SIDE OF JOINT
PREMOLDED EXP
JOINT MATERIAL
CRACK CONTROL JOINT CONSTRUCTION JOINT EXPANSION JOINT AT WALL
NOTES:
1) USE CONSTRUCTION JOINT INSTEAD OF CRACK CONTROL
JOINT WHEREVER CONSTRUCTION IS STOPPED OR WHERE
CALLED FOR ON PLAN.
2) PROVIDE CRUSHED STONE OR GRAVEL UNDER SLAB AS
RECOMMENDED BY GOETECHNICAL REPORT FOR THE PROJECT.
"T
"
/
2
1/8" CONTROL JNT
"T
"
/
4
"T
"
CONT VAPOR
BARRIER, TYP
BREAK BOND W/
CURING COMPOUND
"T
"
I1/2"
SAW CUT JOINT, CUT
BETWEEN 4&12 HOURS
AFTER CONC IS PLACED PROVIDE FULL DEPTH
BULKHEAD HELD FIRMLY
IN A VERTICAL POSITION
T/FTG EL,
SEE PLAN
1
1
1
1
NOTE:
FOR PIPES RUNNING PARALLEL TO
STRIP FTGS, FTG DEPTH & PIPE
LOCATION SHALL BE COORDINATED
SO THAT THE PIPE IS NOT WITHIN
FTG LOAD DISTRIBUTION INFLUENCE
LINE AS ILLUSTRATED.
TYP PIPE PARALLEL TO WALL
T/FTG EL,
SEE PLAN
11/2" COMPRESSIBLE MATERIAL
AROUND PIPE OR PROVIDE PIPE
SLEEVE, TYP
NO
P
I
P
E
T
O
B
E
P
L
A
C
E
D
WI
T
H
I
N
F
O
O
T
I
N
G
AT EXISTING PIPES WRAP
W/ 2" STYROFOAM OR SLICE
PVC PIPE 2"ø LARGER & PLACE
AROUND PIPE (SEAL SLIT W/
DUCT TAPE)
CONCRETE FILL IS TO BE PLACED
BEFORE FOOTING IS POURED AND
TO BE THE SAME WIDTH AS FTG,
POUR FULL WIDTH OF PIPE TRENCH
MI
N
6"
MA
X
4'
-
0
"
9" MIN
TYP PIPE PENETRATION THRU WALL
T/SLAB EL,
SEE PLAN
1
1 1
1
NOTE:
FOR PIPES RUNNING PARALLEL TO FTGS,
FTG DEPTH & PIPE LOCATION SHALL BE
COORDINATED SO THAT THE PIPE IS NOT
WITHIN FTG LOAD DISTRIBUTION INFLUENCE
LINE AS ILLUSTRATED.
TYP PIPE PARALLEL TO FOOTING
T/SLAB EL,
SEE PLAN
1 1/2"COMPRESSIBLE MATERIAL AROUND PIPE
OR PROVIDE PIPE SLEEVE, TYP. MAX PIPE
SIZE ALLOWED THROUGH FOOTING IS 3".
AT EXISTING PIPES WRAP W/
2" STYROFOAM OR SLICE PVC
PIPE 2"Ø LARGER & PLACE
AROUND PIPE (SEAL SLIT W/
DUCT TAPE).
CONCRETE FILL IS TO BE PLACED
BEFORE FOOTING IS POURED AND
TO BE THE SAME WIDTH AS FTG,
POUR FULL WIDTH OF PIPE TRENCH.
TYP PIPE PENETRATION AT FOOTING
MIN
9"
6"
M
I
N
4'
-
0
"
M
A
X
2'
-
0
"
2'-0"
CONT FTG, SEE
PLAN OR SCHED
ADD CORNER BAR
TO MATCH FTG REINF
TYPICAL CORNER FOOTING REINF
STEPS TO BE MADE IN
BRICK OR BLOCK
COURSING FOR
MASONRY WALLSMIN
2 "S"
"T
"
"S
"
"S
"
"T"
40ø
40ø
NOTE:
"T" = FTG THICKNESS,
SEE FTG SCHEDULE.
FTG SIZE & REINF,
SEE PLAN, TYP
1
2
REINF TO MATCH
WALL FTG REINF
T/FTG EL,
SEE PLAN
WALL FTG COL FTG
40 BAR ø
40 BAR ø 40 BAR ø
40 BAR ø
VERT REINF IN
GROUT FILLED CELL
PER PLAN & NOTES
FIN FLOOR
SURFACE
WWF, SEE PLAN
2-#5 CONT W/
#3@36" TRANSV
NOTE:
TYPICAL FOR ALL WALLS 8" OR MORE
NOT SUPPORTED ON WALL FOOTINGS
1'
-
0
"
1'-6" MIN
SE
E
PL
A
N
3"
CL
R
EQ EQ
SEE
ARCH
TYPICAL LOAD BEARING
WALL THICKENED SLAB
8"
*
8"
6"
8"
7'-4"
8"
ADD #5 T&B
EA SIDE OF OPNG
24"x24"x24"
SUMP PIT
2-#4x3'-0" T&B
@ EACH CORNER
*VERIFY w/ EQUIP
PURCHASED
9
S3.1
___________
OR
A
S
N
O
T
E
D
O
N
P
L
A
N
1'
-
6
"
TYP
8"
6"
T
Y
P
8"
SEE PLAN
VE
R
I
F
Y
W
/
M
A
N
U
F
EQ
U
I
P
M
E
N
T
P
U
R
C
H
A
S
E
D
SEE DETAIL "A"
#5@12" EW T&B
2'-0" SQUARE HOLE LOCATE
AS REQ'D BY ELEV MANUF FILL
HOLE W/ NON-SHRINK GROUT
AFTER ELEVATOR IS ERECTED.
SUMP PIT
W/ GRATE
WATERSTOP
(TYP)
SLAB REINF,
SEE PLAN
#5@12" EW
CTR'D
#5@12" EW CTR'D
2
1
/
2
"
L6x31/2x1/4 (LLV) x
DOOR WIDTH + 4" W/
1/2"øx3" STUDS @ 2'-0"
DETAIL "A"
3/162-12
1/224
NOTES:
1) SEE SPECS FOR WATERPROOFING.
2) PROVIDE WATERSTOP @ EACH
JOINT-SEE SPECS.
T/FTG EL
SEE PLAN
NOTE:
ALL HOOKS ARE
STANDARD ACI HOOKS
TYPICAL CONCRETE WALL CORNERS & INTERSECTIONS
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
4
:
0
8
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S3.1
FOUNDATION
SECTIONS &
DETAILS
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 3/4" = 1'-0"S3.1
1 TYP SLAB ON GRADE JOINTS
SCALE: 3/16" = 1'-0"S3.1
2 DETAIL
SCALE: 3/8" = 1'-0"S3.1
3 DETAIL
SCALE: 3/4" = 1'-0"S3.1
4 DETAIL
SCALE: 3/4" = 1'-0"S3.1
5 TYPICAL STEP IN WALL FOOTING
SCALE: 3/4" = 1'-0"S3.1
6 WALL FTG TO COL FTG
SCALE: 3/4" = 1'-0"S3.1
7 DETAIL
SCALE: 1/4" = 1'-0"S3.1
8 TYPICAL ELEVATOR PIT PLAN
SCALE: 3/4" = 1'-0"S3.1
9 TYPICAL ELEVATOR PIT SECTION
SCALE: 3/4" = 1'-0"S3.1
10 DETAIL
SEE SCHED
PARKING GARAGE
SLAB ON GRADE,
SEE PLAN
SE
E
S
C
H
E
D
PRECAST PANEL,
BY OTHERS
T/FTG EL,
SEE PLAN
PARKING GARAGE
SLAB ON GRADE,
SEE PLAN
T/SLAB EL,
SEE PLAN
13" THICK CONC WALL
REINF w/#7@9" VERT EF
& #5@12" HORIZ EF
T/SLAB EL,
SEE PLAN
NOTE:
REFER TO PRECAST ENGR'G
DRAWINGS FOR ALL DETAILS
RELATING TO THE CONNECTION
OF THE PRECAST ELEMENT TO
CAST-IN-PLACE CONCRETE
FOUNDATION (TYP UON).
3'-6" TO 5'-6"
1'-0" TO 3'-6"
WALL HT
RETAINING WALL SCHEDULE
3'-0"
A
12"
B
3'-0"
C
2'-6"
D "E" BARS "F" BARS "G" BARS
#6@6"
"H" BARS
#6@6"#6@12"#6@12"
3'-0"12"3'-0"2'-6"#6@6"#6@6"#6@12"#6@12"
WA
L
L
H
T
A B C
'E' BARS
'F' BARS
D
'H' BARS
'G' BARS
'E' BARS
'F' BARS
EQ
EQ
9"9"
3/4"ø SMOOTH
BAR @ 1'-6"
WRAP W/ 2 LAYERS OF OILED
HEAVY WEIGHT KRAFT PAPER,
TWIST END CLOSED
1/2" PREMOLDED EXP
JT MATERIAL
EXPANSION JOINT - RETAINING WALL
EQ
EQ
9"9"
3/4"ø SMOOTH
BAR @ 1'-6"
CONTRACTION JOINT - RETAINING WALL
3/4" CHAMFER
NOTES:
1) STOP HORIZ REINF 11/2" EA
SIDE OF JOINT.
2) PROVIDE CONTRACTION JOINT
@ 15' MAX-PROVIDE EXP JNT
@ 30' MAX.
WWF, SEE PLAN1-#4 TOP
2-#4 CONT W/
#3@36" TRANSV
1'
-
4
"
1'-0"
SE
E
PL
A
N
T/SLAB EL,
SEE PLAN
TYPICAL TURNDOWN
5'-0"
T/FTG EL,
SEE PLAN
1'
-
2
"
#5@ 12" O.C. MAX LONG TOP
1'-0"1'-0"
#6@9" DOWELS LAP WITH
VERT WALL REINF
SLAB ON GRADE,
SEE PLAN
#5 @ 12"
#5@ 12"
1'
-
0
"
#5@ 12" O.C.
MAX LONG
BOT
6"
1
1
/
4
"
5"
KOROLATH SHIM STACK
1 1/16" X 4" X 6" @ 48"
O.C.4"8"
DRY PACK SOLID 7,000 PSI
NON SHRINK GROUT
#5 @ 12" O.C.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
4
:
1
6
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S3.2
FOUNDATION
SECTIONS &
DETAILS
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 3/4" = 1'-0"S3.2
1 RETAINING WALL SCHEDULE
SCALE: 3/4" = 1'-0"S3.2
3 DETAIL
SCALE: 3/4" = 1'-0"S3.2
4 TYP TURNDOWN
SCALE: 3/4" = 1'-0"S3.2
2 RAMP SECTION
ANCHOR RODS BY
PRECAST MANUF.
PRECAST COL
BY PRECAST
ENGINEER
T/FTG EL
SEE PLAN
SEE FND SCHED
FOR SIZE & REINF.
NOTE:
REFER TO PRECAST ENGR'G
DRAWINGS FOR ALL DETAILS
RELATING TO THE CONNECTION
OF THE PRECAST ELEMENT TO
CAST-IN-PLACE CONCRETE
FOUNDATION (TYP UON).
..
SLAB REINF, SEE PLAN
T/SLAB EL
SEE PLAN
#3 @ 12" x
5'-6" LONG
3-TIES w/IN TOP
5" OF PEDESTAL
SEE SCHED
EQ EQ
TYP
2"
SCHED
SEE
SEE GENERAL NOTES (TYP)
SEE SCHEDULE &
PLAN
PRECAST LIGHTWALL
OR PRECAST PANEL
IF EXPOSED STEEL
CONNECTIONS, PROVIDE
3" CONC. COVER ALL
AROUND CONNECTION TYP
NOTE:
REFER TO PRECAST ENGR'G
DRAWINGS FOR ALL DETAILS
RELATING TO THE CONNECTION
OF THE PRECAST ELEMENT TO
CAST-IN-PLACE CONCRETE
FOUNDATION (TYP UON).
SLAB REINF, SEE PLAN
T/SLAB EL
SEE PLAN
1/2" EXP JOINT
MATERIAL
T/SLAB EL
SEE PLAN
HEADED STUDS OR
ANCHOR BOLTS BY
PRECAST ENGINEER
SLAB AND WWF IS TO BE
CONTINUOUS THROUGH
OPENINGS IN PRECAST
LIGHTWALL
6"
#3@12"
#3@12" x 5'-6" LONG
OR AS NOTED ON PLAN
3'-0"
SEE SCHED
SEE GENERAL NOTES (TYP)
EQ EQ
8"
TYP
3"CLR
TYP
3"CLR
1'-0"
SEE FT SCHEDULE
SEE
PLAN
CMU WALL,
SEE ARCH
FOR WALL REINF,
SEE GEN NOTES
SEE FT SCHEDULE
WWF, SEE PLAN
T/SLAB EL,
T/FTG EL,
CMU WALL
BEYOND
WWF, SEE PLAN
TYPICAL FOOTING SLAB @ OPENING
SEE PLAN
SEE PLAN
8"
SEE PLAN
PRECAST PANEL
TOP OF SLAB
SEE PLAN
#6 @ 12" O.C.
# 6@ 12" O.C.
#6 @ 12" O.C.
#6 @ 12" O.C.
SEE SCHEDULE &
PLAN
PRECAST PANEL
IF EXPOSED STEEL
CONNECTIONS, PROVIDE
3" CONC. COVER ALL
AROUND CONNECTION TYP
NOTE:
REFER TO PRECAST ENGR'G
DRAWINGS FOR ALL DETAILS
RELATING TO THE CONNECTION
OF THE PRECAST ELEMENT TO
CAST-IN-PLACE CONCRETE
FOUNDATION (TYP UON).
SLAB REINF, SEE PLAN
T/SLAB EL
SEE PLAN
1/2" EXP JOINT
MATERIAL
T/SLAB EL
SEE PLAN
HEADED STUDS OR
ANCHOR BOLTS BY
PRECAST ENGINEER
SLAB AND WWF IS TO BE
CONTINUOUS THROUGH
OPENINGS IN PRECAST PANEL
3 3/4"
#3@12"
#3@12" x 5'-6" LONG
OR AS NOTED ON PLAN
3'-0"
SEE SCHED
STUD WALL,
SEE PLAN
SEE GENERAL NOTES
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
4
:
2
3
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S3.3
FOUNDATION
SECTIONS &
DETAILS
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 3/4" = 1'-0"S3.3
1 SECTION
SCALE: 3/4" = 1'-0"S3.3
2 SECTION
SCALE: 3/4" = 1'-0"S3.3
3 DETAIL
NOTES:
1. SLAB WHERE APPLICABLE
SCALE: 3/4" = 1'-0"S3.3
4 STEM WALL
SCALE: 3/4" = 1'-0"S3.3
5 SECTION
TYP WALL OPENING
NOTE:
TRUSS TYPE JOINT REINFORCEMENT SHALL BE STOPPED
EACH SIDE OF JOINT. BOND BEAM REINFORCEMENT
SHALL BE CONTINUOUS THROUGH CONTROL JOINT.
OPENING
CL CONTROL JOINT
DOWELS TO MATCH
VERT REINF, TYP, UON
PRE-FORMED NEOPRENE
GASKET FULL HEIGHT
OF WALL
FTG, SEE PLAN
CLEANOUT HOLE AS
REQUIRED
JOINT REINF @
16" OC, UON
HORIZ JOINT REINF
COORD W/ ARCH
FILL ALL CELLS
WITH VERTICAL
REINFORCING SOLID
MASONRY
CONTROL JOINT
T/SLAB EL,
SEE PLAN
DOWELS TO MATCH VERT REINF
NOTES:
1) 5' MAX IF LOW LIFT GROUTING IS USED.
2) IF HIGH LIFT GROUTING IS USED,
REINFORCING SHALL BE FULL HEIGHT & A
CLEANOUT HOLE IS REQ'D @ CELLS
W/REBAR. GROUT SHALL BE PLACED IN
LIFTS TO PREVENT BLOWOUTS.
3) SEE GENERAL NOTES FOR BAR LAPS.
4) JOINT REINF SHALL CONSIST OF @ LEAST
TWO WIRES OF W1.7 OR GREATER.
SEALANT TYP
BOTH FACES
FTG, SEE PLAN KNOCK-OUT
BLOCK W/ #5 EF
TYP VERTICAL REINF
EACH SIDE OF JOINT
CMU CONTROL JOINT
DOOR OPNG
WINDOW OR
ADD 1-#5 FULL HEIGHT
WHEN OPENING
EXCEEDS 5'-4"
ADD 1-#5 FULL HEIGHT WHEN
OPENING EXEEDS 10'-0"
TYP WALL REINF,
SEE GENERAL NOTES
FOR SIZE & SPACING
PLAN
WALL SECTION
& SECT
SEE PLAN
& SECT
SEE PLAN
T/FTG EL,
SEE PLAN
T/WALL EL,
SEE PLAN
VERT WALL REINF,
SEE NOTES
LINTEL,
2/S3.01
MASONRY
BOND BEAM
AS
R
E
Q
'
D
NO
T
E
1
NO
T
E
1
LA
P
LA
P
LA
P
1/2"
JOINT ALLOWED
NO VERT
1-#5 FULL HEIGHT,
GROUT CELL FULL
1-#5 FULL HEIGHT,
GROUT CELL FULL,
TYP @ CORNER
TYP WALL CORNER
NOTES:
1) FOR OPNG LOCATIONS SEE ARCH DWGS.
2) PROVIDE 8" BEARING EACH SIDE OF OPNG.
MASONRY OPNG LESS THAN 5'-0"
1-#5 EF CONT
FILL CELLS
W/ CONC
PRECAST OR
CMU U-BLOCK
VERT REINF, SEE
GENERAL NOTES
CMU
8"
TYP LINTEL DETAIL
4" BRICK LINTEL SCHEDULE
OPENING
< 6'-0"
LINTEL
L3 1/2x3 1/2x5/16
< 8'-0"L5x3 1/2x5/16 (LLV)
> 8'-0"
(MAX OPNG = 9'-6")
WOOD MASONRY
L5x5x5/16 W/ 1/2"ø
LAG SCREW INTO
HEADER @ 24"
L5x5x5/16 W/ 1/2"øx5" LG
EXP BOLT INTO
HEADER @ 24"
NOTES:
1) PROVIDE 4" MIN BEARING EACH SIDE OF OPENING.
2) CURVE ANGLE AS NECESSARY.
OPNG < 8'OPNG > 8'
BENT PL & EXP
BOLTS @ 48", SEE
DETAIL 6/S3.01
SOLID BLOCK
@ TOP
8" U BLOCK
W/2-#4 CONT
BETWN STEMS
1" CLEAR TO CONC BEAM
& DECK ABOVE
PARKING GARAGE
CONC BEAM STEM BY
PRE-ENGINEERED
CMU WALL W/VERT
REINF IN GROUTED
CELLS, SEE GEN
NOTES FOR SIZE &
SPACING
CONT U BLOCK
W/2-#4 & CONC
GROUT FILL
WALL EXTENDS
TO DECK ABOVE,
SEE ARCH
CMU WALL AT CONC
BEAMS (PERPENDICULAR)
1"CLR
CMU WALL AT CONC BEAMS (PARALLEL)
U BLOCK
W/2-#4 CONT
SOLID BLOCK
@ TOP
1" CLEAR TO CONC
BEAM & DECK ABOVE
BENT PL10"x6"x5/16"x0'-6" LG
(LLV) @ 48" OC MAX.
2-3/4"ø EXP BOLTS
2-3/4"ø EXP BOLTS W/WASHERS IN
2" LG SLOTTED VERT HOLES (DO
NOT TIGHTEN TO ALLOW
DEFLECTION OF CONC BEAM)
PARKING GARAGE
CONC BEAM BY
PRE-ENGINEERED
CMU WALL
W/VERT REINF IN
GROUTED CELLS,
SEE GEN NOTES
FOR SIZE & SPCG.
E
N
G
I
N
E
E
R
I
N
G
I
N
C
e
m
a
i
l
:
m
a
i
l
@
M
c
V
e
i
g
h
M
a
n
g
u
m
.
c
o
m
En
g
.
o
f
R
e
c
o
r
d
:
Li
c
e
n
s
e
N
o
.
:
1
6
1
0
E
a
s
t
M
o
r
e
h
e
a
d
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
C
h
a
r
l
o
t
t
e
,
N
o
r
t
h
C
a
r
o
l
i
n
a
2
8
2
0
7
P
h
:
(
7
0
4
)
5
4
7
-
9
0
3
5
F
a
x
:
(
7
0
4
)
5
4
7
-
9
0
3
6
F
i
r
m
L
i
c
e
n
s
e
N
o
.
:
C
-
3
3
9
1
M
V
E
I
G
H
M
A
N
G
U
M
C
GA
R
A
G
E
CA
R
M
E
L
,
I
N
D
I
A
N
A
client logo
revision dates
333 West Trade Street, Suite 300
Charlotte, NC 28202
T: 704.333.7862 F: 704.343.9380
Project No:
Issue Date:
Issued For:
1412
GR
A
N
D
&
M
A
I
N
7/
3
1
/
2
0
1
5
1
:
5
4
:
2
8
P
M
C
:
\
U
s
e
r
s
\
y
f
a
n
g
\
D
o
c
u
m
e
n
t
s
\
1
4
5
9
9
-
G
r
a
n
d
at
M
a
i
n
A
p
a
r
t
m
e
n
t
s
P
A
R
K
I
N
G
G
A
R
A
G
E
-
S
t
r
u
c
t
-
2
0
1
5
_
y
f
a
n
g
.
r
v
t
S4.1
MASONRY
SECTIONS &
DETAILS
JULY 1, 2015
PERMIT SET
??
?
?
?
?
?
Do
u
g
l
a
s
R
.
S
w
e
e
n
e
y
SCALE: 3/4" = 1'-0"S4.1
1 SECTION
SCALE: 3/4" = 1'-0"S4.1
2 SECTION
SCALE: 3/4" = 1'-0"S4.1
3 SECTION
SCALE: 3/4" = 1'-0"S4.1
5 SECTION
SCALE: 3/4" = 1'-0"S4.1
6 SECTION