HomeMy WebLinkAboutSub-Surface of Indiana/ENG/CO 3/-6,798.44/bridleboure drainageTO: Sub -Surface of Indiana, Inc. 7225 West 700 South Morgantown, IN 46160 CITY OF CARMEL CONTRACT CHANGE ORDER NO.: #3 (Final) DATE: October 16, 2015 PROJECT NAME: Bridlebourne Drainage Modifications Project No.13-07 CITY REQ. NO.: CITY PO NO.: 25291 CITY PO DATE: You are directed to make the following changes in this Contract: (Brief Description) ITEM AMOUNT (+) OR (-) DAYS See Attached Sheets II. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: R.F.P.: NA W.D.C. No.: NA Other: The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $ 364,315.52 Contract Price will be decreased by this Change Order $ 6,798.44 New Contract Price including this Change Order $ 357,517.08 Contract Time Prior to this Change Order NA Days NA Completion Date Net increased/decreased resulting from this Change Order NA Days Current Contract Time including this Change Order NA Days NA Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are Recommended Department of Engineering ENGINEER One Civic Square Address Carmel IN, 46032 City/State/Zip Phone: (317) 571-2441 Date: /e r @ • /tj The Above Changes Are Accepted: CONTRACTOR 3-22-C Gees- ¥oo 500.1-1.. Address ma .".1-ton%/s,-' / Li‘ t 6 o City/State/Zip/� By: Si fM PLA -a -j' ( int nArtj ($mature) Phone: 31+ 01 oq 2-G Date: IL) /16/ tS Diana Cordraylr Jerk -Treasurer Date: /I Lti City Engineer Date: BRIDLEBOURNE DRAINAGE MODIFICATIONS (PROJECT NO. 13-07) CHANGE ORDER #3 Item No. Item 10 Pipe, 15" RCP, Remove - Two feet of additional pipe quantity was added to balance the final quantity — Substantially as planned. (Overrun 2 Lft, x 10.00 = $20.00) 11 Pipe, 18" RCP, Remove - Two feet of additional pipe quantity was added to balance the final quantity — Substantially as planned. (Overrun 14 Lft. x 10.00 = $140.00) 12 Pipe, 24" RCP, Remove - Two feet of additional pipe quantity was added to balance the final quantity — Substantially as planned. (Underrun 7 Lft. x 15.00 = $105.00) 13 Curb, Concrete Remove - Additional curb was removed to the nearest concrete joint to include cracked curbs. (Overrun 10 Lft. x $ 18.00 = S180.00) 14 Curb, Concrete - Additional curb was poured to the nearest concrete joint to include cracked curbs. (Overrun 10 Lft. x $57.00 = S570.00) 15 Coarse Aggregate, #2 Stone - Substantially as planned. (Overrun 0.70 Tons x $20.00 = 514.00) 18 Pipe, Circular, RCP, 30 In. - Less 30" RCP was required than was shown on the plans. (Underrun 7 Lft. x $57.00 = 5399.00) 24 Compacted Aggregate, No. 8 - 68.72 of additional stone quantity was added to balance the final quantity. The plans did not account for backfill for all the RCP to the springline of the storm pipes as required by the Hamilton County Surveyor's Office. Additional stone was required to backfill the storm pipes than was estimated in the plans. (Overrun 68.72 x $18.00 = $1,236.96) 29 Silt Fence - Less silt fence was used than was shown on the plans because existing grades did not required silt fence. (Underrun 1,020 Lft x 51.33 = 51,356.60) r 31 Riprap , Class 2 - Less riprap was required than was shown on the plans. (Underrun 120.64 Tons x $45.00 = S5,428.80) 32 Rock Check Dam - Less rock check dams were required than was shown on the plans due to construction sequence. (Underrun 2 Each x $825.00 = $1,650.00) There was an multiplication error in the original Contract Items and Unit Prices in Item #10 - Pipe 15" Remove. The original total was $2,220. The correct total is $2,200. $20 was deducted from the original total cost of the contract. ($348,000.00 — $20 = $347,980.00)