HomeMy WebLinkAboutYardberry/Eng/CO 4/4620/Shred Use Path 136thTO:
CITY OF CARMEL
CONTRACT CHANGE ORDER NO.: 4
DATE: 8/5/15
PROJECT NAME: Shared Use Path 136th Street
CITY REQ. NO.:
CITY PO NO.:
CITY PO DATE:
1. You are directed to make the following changes in this Contract:
Install Class 1 rip rap for erosion control at the outlet of structure 9.
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+) OR (-) DAYS
0074 Class 1 Rip Rap $4,620.00
II. The following referenced Documents further describe the changes outlined in Paragraph I,
and are to be considered a part of this Change Order: R.F.P.: W.D.C. No.:
Other: Force Accout Stunmary
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $_691 912.50
Contract Price will be increased/decreased by this Change Order $ 4,620.00
New Contract Price including this Change Order $ 696,532.5
Contract Time Prior to this Change -Order Days 6/10/15 Completion Date
Net increased/decreased resulting from this Change Order 19 Days
Current Contract Time including this Change Order Days _6/10/15 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are
Recommended
CHA
ENGINEER
Union Station
Address
Indianapolis
City/State/Zip
By: Tom Gentry
Phone _317-503-5250
Date: 8-5-15
The Above Changes Are
Ac
C / G C(TOR
EA-
Address5/60 )2
City/State/Zip
By:
6 •
Phone:
Date:
Approved:
urk
embe
Lori at
ATT
, Member
✓144-12-1,-->
15iana Cordray,
Treasurer
Date: / -air
FORCE ACCOUNT DAILY FIELD RECORD
Contract Id R36889 136th Street Pathway
Work Performed By: Yarberry
County: Hamilton
Day:
Date:
Prime Contractor
Project No:
Sub -Contractor
Route:
CLASS OF WORK CLASS OF WORK REG. HRS Hourly Rate
Totals DESCRIPTION OF DUTIES
Laborer
Laborer
7.00
$65.00
$455.00
Labor
Laborer
Laborer
7.00
$65.00
$455.00
Labor
EQUIPMENT
TIME USED
Hourly Rate Totals
REMARKS
Excavator
7
$200.0
$1,400.00
Installed Rip Rap
Dump Truck
7
$110.0
$770.00
Transported Rip Rap
MATERIALS USED
QUANTITY
PRICE Totals REMARKS
Class 1 Rip Rap
40
$38.50
$1,540.00
Total Force Account Work =
Total Cost Per Ton =
$4,620.00
b
$4,620.00/40 Tons = $115.5 Per Ton