HomeMy WebLinkAboutOLCO Inc/Eng/CO5/Shared Use Path Main StreetCITY OF CARMEL 2 TO: CONTRACT CHANGE ORDER NO.: 5 DATE: 6/5/15 PROJECT NAME: Shared Use Path Main Street CITY REQ. NO.: CITY PO NO.: CITY PO DATE: I. You are directed to make the following changes in this Contract: Adjust Intermediate Completion Date due to delays imposed by the City of Carmel SCHEDULED ADJUSTMENT ITEM AMOUNT (+) OR (-I.DAYS I1. The following referenced Documents further describe the changes outlined in Paragraph 1, and are to be considered a part of this Change Order: R.F.P.: W.D.C. No.: Other: INDOT Change Order 5 The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $ 890 008.01 Contract Price will be increased/decreased by this Change Order $ 0.00 New Contract Price including this Change Order $ 890 008.01 Contract Time Prior to this Change Order Days 11/30/15 Intermediate Completion Date Net increased/decreased resulting from this Change Order 47 Days Current Contract Time including this Change Order Days 6/5/15 Intermediate Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are Recommended CHA Companies ENGINEER 300 S Meridian Address Indianapolis, In 46225 City/State/Zip By:Thomas Gentry Phone:_317-503-5250 Date: -6-5-15 The Above Changes Are Accepted: CON�TI CTOR L V„+� ,ppAddress 9iC,le&ag � �11-4 City/State/Zip B Mone: S(0- 33-0 )oL( Date: ;Zoi Approved: r ames Brainard, Mayor Jere y Kashman PE Contract No:R -36869 Change Order No.: 005 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -36869 Letting Date:08106/2014 District:GREENFIELD DISTRICT AE:Nierman, Chad PE/S:Gregg, Michael Status:Pending Change Order Information Change Order No.: 005 EWA: N or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: INCENTIVE/DISINCENT, Intermediate Compl Description: Intermediate Completion Extension Due to Delays By Owner Original Contract Amount $ 821,339.94 Current Change Order Amount $ 0.00 Percent: 0.000 % Total Previous Approved Changes $ 71,930.32 Percent: 8.758 % Total Change To -Date $ 71,930.32 Percent: 8.758 % Modified Contract Amount $ 893,270.26 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension Previous Time Approved SS Days 0 SP Days 0 SP Days Value $ 0.00 SS Days by AE: DCE: SCE: DDCM: SS Days SP Days Value $ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -36869 INDIANA Department of Transportation Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority ($ per Change Order) (Days per Contract) Verbal Approval Required? Total Change To-Date>5%? Scope/Design Recommendation Required? Change Order No.: 005 Page: 2 AE: DCE: SCE: * DDCM: (-LE$250K-)(-LE$750K-)(--LE$2M--)(--GT$2M--) ( 50 SS days) ( 100 SS days) ( 200 SS Days) ( GT 200 SS days) Y / N If Y, by Date Issued Y / N If Y , Copy to Program Budget Manager Y / N If Y, Referred to Project Manager(PM) Date to PM Approval Authority Concurs with PM? Y / N If Y, Concurrence by If N,Resolution: Approved LPA Signatures Required? Resolved by Y / N If Y, Date to LPA Date Returned Date Disapproved Date Date Returned FHWA Signatures Required? Y / N If Y, Date to FHWA Date Returned * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer Date Comments: Contract NOIR -36869 INDIANA Change Order No:005 Department of Transportation Contract: Project: Change Order Nbr: R -36869 State: 138316600LC3 005 Change Order Description: Intermediate Completion Extension Due to Delays By Owner Reason Code: INCENTIVE/DISINCENT, Intermediate -Comp) - Date:01 /08/2016 Page: 3 CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change Total Value for Change Order 005 = $ 0.00 Milestone Time Adjustment Milestone Nbr: 01 Milestone Description: INTERMEDIATE COMPLETION DATE Original Completion dt: 11/30/2014 Adj comp) dt 06/05/2015 Adj No. of Days 47 Explanation: Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation This change order extends the intermediate completion date 47 day to June, 6th 2015. The delays are due to the Owner considering scope changes during construction. The city put the railing installation on hold to explore the possibility for placing the rail between the trail and the road instead of on the outside of the trail. And ultimately, this approach was rejected and not pursued by the city, but as the railing installation was the controlling operation at the time, the work suspended by the city delayed the completion of the project. While this delay is not anticipated to result in added costs to the project, this time extension is non -participating. Change Order Explanation for Specific Line Item It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor: (OLCO. he Signed By: 1 Date: 16 (_, c?7l h ffilHlf!!ff ##ltlf!!fflf!!ff!!1f f f f f #1f f f!f f!!if f!!11l1flf f f f #fHtflflHlNlflfff f!!f f!f!##f H#!f#!!N!f!!!f Hf 11f f!f!!1flf NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Contract No:R -36869 INDIANA Date:01/08/2016 Change Order No:005 Department of Transportation Page: 4 »rrrww»»wr»wr»wa»rrw:w»rww rrr»r»»rrwwr»*rr»»rrrwrwrr»rr»rr»rrr»ri:»»rrr»wrr»rrrrrrr»»»»+»rr»rwrrw APPROVED FOR LOCAL PUBLIC AGENCY (SIGNATURE) (TITLE) (SIGNATURE) (TITLE) PE/S (DATE) (DATE) SUBMITTED FOR CONSIDERATION APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status Project Engineer/Supervisor Gentry, Thomas 00/00/0000 Action Pending Area Engineer Nierman, Chad 00/00/0000 Action Pending