Municipal & Contractors Sealing Products/ENG/1,400/Carmel Culvert 101 Pipe Liner ProjectCITY OF CARMEL
TO: CONTRACT CHANGE ORDER NO.: 1
Drew O'Connor DATE: - December 18, 2015
Municipal & Contractors PROJECT NAME: Carmel Culvert 101 Pipe Liner Proj.
Sealing Products CITY REQ. NO.: 250-4350900
7740 Reinhold Drive CITY PO NO.: 32911
Cincinnati, Ohio 45237 CITY PO DATE: 10/15/2015
lb
I. You are directed to make the following changes in this Contract:
This change order compensates the contractor for the additional soil stabilization
application (gallons) over the original quoted amount. MCSP used 15 gallons resulting in a 14
gallon overrun at $100/gal or $1,400.00.
SCHEDULED ADJUSTMENT
ITEM AMOUNT-- - (+)- OR (-) DAYS
Soil Stab. Application (Addtl) $1,400.00 0
II. The following referenced Documents further describe the changes outlined in Paragraph I, and
are to be considered a part of this Change Order: R.F.P.: W.D.C. No.:
Other:
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $ 47,100.00
Contract Price will be increased/decreased by this Change Order $ 1,400.00
New Contract Price including this Change Order $ 48,500.00
Contract Time Prior to this Change Order Days Completion Date
Net increased/decreased resulting from this Change Order Days
Current Contract Time including this Change Order Days Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are The Above Changes Are
Recommended Accepted:
Nw C E NG(a IEe R w G MUNICIPAL & CONTRACTORS SEALING PRODUCTS
ENGINEER
[51 til. DLE AwAaE SS. 800
Address
IONANAPOLIS,21r1 46204
City/S /Z' gilti.�y�-t"
By:
Phone/isa`
: 3/7-
Date:
CONTRACTOR
7740 REINHOLD DRIVE
Address
CINCINNATI, OHIO 45237
BCity/Stater
D
Phone: (513) 482-3300
Date: 01/04/2016
AR -6
A nnrnved
k y X ashman, City
Engineer