HomeMy WebLinkAboutE&B Paving/Eng/CO #10/3,073.21/Hawthorne Drive & Carey Road RAB #16-ENG-09CITY OF CARMEL
TO: CONTRACT CHANGE ORDER NO.: 10
E&B Paving, Inc. DATE: December 7, 2016
17042 Middletown Ave. PROJECT NAME: Hawthorne Dr. & Carey RAB
Noblesville, IN 46060 CITY REQ. NO.: 16 -ENG -09
CITY PO NO.:
CITY PO DATE:4D LG
I. You are directed to make the following changes in this Contract:
Landscape Wall Sign and Light for Foster Ridge, neighborhood sign and light item
added to the contract as reauested by City of Carmel.
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+) OR (-) DAYS
EW Item #2087 Landscape Wall Sign 1 Lsum (& $2,750.00 = $2,750.00 0 Days
EW Item #2088 Landscape Sign Uplight 1 Lsum (ii� 323.21= 323.21 0 Days
II. The following referenced Documents further describe the changes outlined in Paragraph I, and
are to be considered a part of this Change Order: R.F.P.: N/A W.D.C. No.: N/A
Other: Attached itemized change order documents from E&B. Inc., Broadv/Campbell
and Hoosier Compan
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $ 683,598.52
Contract Price will be increased/decreased by this Change Order $ 3,073.21
New Contract Price including this Change Order $_686,671.73
Contract Time Prior to this Change Order 45 Days _ Open to Traffic
Net increased/decreased resulting from this Change Order_ 0 Days
Current Contract Time including this Change Order 45 Days Open to Traffic
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are
Recommended
American Structurepoint, Inc.
ENGINEER
7260 Shadeland Station
Address
Indianapolis, IN 46256
City/State/Zip
By:
Phone: 317-547-5580
The Above Changes Are
Accepted:
E&B Paving, Inc.
CONTRACTOR
17042 Middletown Ave.
Address
Noblesville, IN 46060
City/State/Zip
B/(3
Phone: 317-773-4132
Approved:
Jeer
, City Eng.
CG '�-C�
ey, lerk-
Treasurer
Date:/,� f ?�G Date: Date:.?//// -7
To: City of Carmel
One Civic Square
Carmel, IN 46032
Attn: John Cox
x:5 & t P y^ r .: +:,.... rni
World -Class Solutions fit a Local Level
ADDITIONAL WORK AUTHORIZATION # 7
Phone: 317-285-9459
Fax:
Project: 136th -Carey -Hawthorne RAB's
Location: Carey Rd and Hawthorne Dr
City: Carmel
Date: 11/16/2016
Job No: 02163505
The following quoted prices are for additional work that is not a part of our original contract scope of work:
DESCRIPTION:
The following pricing is for the fabrication and installation of the additional masonry wall for the Foster Ridge subdivision sign.
Description Quantity
EWA Subdivision Entrance Sign at Foster Ridge 1
Unit Unit Price Extension
LS $ 2,500.00 $ 2,500.00
Subtotal $ 2,500.00
10% of first $3,000.00 $ 250.00
7% of remainder
TOTAL $ 2,750.00
ADDITIONAL CHARGE FOR THE ABOVE WORK IS: $ 2,750.00
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date: Owner or Contractor Signature
(Authorized Representative)
We hereby agree to furnish labor and materials - complete in accordance ith. thea ve specifications, at the above stated price.
E & B Paving, Inc., Authorized Signature /./l�r�.. �--- Date: 11/16/16
Steve fl oermann
THIS IS ADDITIONAL WORK AUTHORIZATION NO. 7
AN EQUAL OPPORTUNITY EMPLOYER
17042 Middletown Ave. • Noblesville, IN 46060
PHONE: 317.773.4132 • r-Ax317.773.4137
www.ebpaving.com
p t ASF Nd4trA ft 4Odtt+C� N i ttATQ RS ,"u
BROADY/CAMPBELL COST ESTIMATE FOR WALL AT FOSTER RIDGE ENTRANCE
Description
Quantity
Unit
Unit Cost
Fabrication of Sign
1
EA
$
1,130.00
$
1,130.00
Delivery of Sign/Coping
1
EA
$
150.00
$
150.00
Remobilize to Install Sign
1
EA
$
300.00
$
300.00
Sign Installation Cost
1
EA
$
250.00
$
250.00
Cold Weather and MOT Cost
1
LS
$
500.00
$
500.00
Overhead and Profit
1
LS
$
170.00
$
170.00
Total
$
2,500.00
11/16/2016
IMI Mail - Re: FW: Carmel Roundabout: Carey and Hawthorn Sign
Steven Broermann <steve.broermann@ebpaving.com>
G/0111) of Comiumicti
Re: FW: Carmel Roundabout: Carey and Hawthorn Sign
1 message
Broadycampbell@aol.com <Broadycampbell@aol.com>
To: steve.broermann@ebpaving.com
Cc: broadycampbell@aol.com
Mon, Nov 14, 2016 at 5:17 PM
Well, the cost of a two sided brick wall is $459.67 a lineal foot(per contract) x 6.5 If which equals $2988, the sign is
$1130. Then we have to pick it and the coping for it up at plant $150. Then we will have to remobilize since the stone
will not be here until 3 or 4 weeks after we are gone that costs $300, then we have to install it $250 add O/H and profit of
$170. That's $2000. This doesn't even take into consideration that its going to be in December and will probably be
cold. So the bid for this is $4,988, and probably should be at least $500 higher given that the road will be open and we
will be fighting traffic.
Greg Broady
In a message dated 11/11/2016 10:33:59 A.M. Eastern Standard Time, steve.broermann@ebpaving.com writes:
Greg - have you had a chance to get any more detail on the cost for this? The City is wanting to see more
breakdown on the cost.
Thanks.
Steve Broermann
Project Manager/ Estimator
E&B Paving, Inc.
17042 Middletown Rd
Noblesville, IN 46060
M- 317-771-2717
0 - 317-773-4132
F - 317-773-4137
On Tue, Nov 1, 2016 at 1:25 PM, <Broadycampbell@aol.com> wrote:
If they use the If price of $459.67 x 6.5 = $2,987.86 + sign cost of $2000 it will work. Total is $4987.86
Steve, FYI the length of the circular wall at 136 th street roundabout is about 44 If not 31 feet as shown on
the bid form. How long does it take them to adjust the contract price after completion. Greg
In a message dated 10/31/2016 3:42:01 P.M. Eastern Daylight Time, steve.broermann@ebpaving.com writes:
All - Please see the attached sheets for revisions to the plans for the project at Carey Rd and
Hawthorne Dr. A new section of masonry wall has been added and plant quantities adjusted to
accommodate the walls.
Greg and Scott - please note that the wall has a sign that will need to be manufactured and installed
as a part of the wall. They are hoping that they can pay the extra linear ft of wall at the existing wall
unit price and then add in whatever extras are needed for the sign and anything else that is. different.
Let me know if you are OK with that or if anything needs changed price wise.
Thanks.
Steve Broermann
Project Manager / Estimator
E&B Paving, Inc.
17042 Middletown Rd
Noblesville, IN 46060
M- 317-771-2717
0 - 317-773-4132
F - 317-7734137
https://mail.google.com/mail/u/0/?ui=2&ik=d30e59b302&view=pt&search=inbox&th=l5864eadbd4l4413&siml=M64eadbd4l4413 1/3
To: City of Carmel
One Civic Square
Carmel, IN 46032
Attn: John Cox
DESCRIPTION:
B PAVINGinc
;I I-Vorld-ClassSolutionsat a Local Level""
ADDITIONAL WORK AUTHORIZATION # 9
Phone: 317-285-9459
Fax:
Project: 136th -Carey -Hawthorne RAB's
Location: Carey Rd and Hawthorne Dr
City: Carmel
Date: 12/1/2016
Job No: 02163505
The following quoted prices are for additional work that is not a part of our original contract scope of work:
The following pricing is for the installation of an up light fixture on the Foster Ridge Subdivision sign.
Description Quantity Unit Unit Price Extension
EWA Purchase and Install Uplight at Entrance Sign 1 LS $ 293.83 $ 293.83.
Subtotal $ 293.83
10% of first -$3,000.00 $ 29.38
7% of remainder
TOTAL $ 323.21
ADDITIONAL CHARGE FOR THE ABOVE WORK IS: $ 323.21
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date: Owner. or Contractor Signature
(Authorized Representative)
We hereby agree to furnish labor and materials - complete in accordance th th ve specifications, at the above stated price.
E & B Paving, Inc., Authorized Signature C- Date: 12/01/16
Steve Kroermann
THIS IS ADDITIONAL WORK AUTHORIZATION NO. 9
AN EQUAL OPPORTUNITY EMPLOYER
17042 Middletown Ave. • Noblesville, IN 46060
PHONE. 317.773.4132 - FAx• 317.773.4137
www.vbpaving.com
X.
R*'
rr`AN4taCDtGti , e d
.; a t M'i ° 4
Change Request
The Hoosier Company
5421 W. 86th St.
Indianapolis, IN 46268
Description
'roposed New Signage Uplight in Island East Side Hawthorne Drive Roundabout
Equipment
$
Labor
Total
Foreman Truck 1 $ 23.87
Type
#
Manhours
Rate
29.58
Total
Foreman
1
1
$52.94
$
52.94
Operator
1
1
$54.74
$
54.74
Laborer
1
1
$40.23
$
40.23
Teamster
$
-
Total Labor
$
147.91
Equipment
$
Description Days Day Rate
Total
Foreman Truck 1 $ 23.87
$ 23.87
Material
OH&P @ 20%
$
29.58
OH&P @ 12%
$
2.86
OH&P @ 12%
Total Labor
$
177.49
$ -
Total Equipment
$ 23.87
Job/Contract #
Date:
Change Request #
753993
11/30/2016
1
Material
Desciption Quantity Unit Unit Price Total
New Light Fixture 1 LF $ 80.00 $ 80.00
$ -
$ -
$ -
Total Material $ 80.00
Subcontractors
Description Quantity Unit Unit Price Total
$
Total Subcontractor $ -
Labor
$
147.91
Equipment
$
23.87
Material
OH&P @ 20%
$
29.58
OH&P @ 12%
$
2.86
OH&P @ 12%
Total Labor
$
177.49
Total Equip.
$
26.73
Total Material
Total Price Summary
Unit Quantity 1.00 LS
Total Price $ 293.83
Unit Price $ 293.83
$
80.00 Subcontractor
$ -
$
9.60 1st $3000 @ 10%
$ -
$
89.60 Remaining @ 7%
$ -
Total Subs.
$ -
nternal Use Only: HCI Job # HCI Item #
,abor: $ 147.91 Equipment: $ 23.87 Burden: $
Jlaterial: $ 80.00 Sub: $ -