RE: Contract Change Order #2
16 -ENG -16, 126th St and Gray Road Roundabout — PO# 100148
16 -ENG -54, 136th St and Gray Road Roundabout — PO# 100148S��v
16 -SW -107, Gray Road Culvert Replacement (Culvert #165) — PO# 1OQ149 nc�
.hl
Dear Mr. Kashman,
Please find the enclosed Change Order #2 for work associated with the 136th and Gray Rd
Roundabout project, PO# 100148. Below is a quick summary of the entire contract to date:
AMOUNT % of ORIGINAL CONTRACT
Original Contract $3,205,200.00.
Change Order #1 $87,364.65 2.73%
Change Order #2 $14,870.68 3.19%
A more complete Change Order Summary is included in these change order documents. Please
contact me if you need more information or have questions.
1
Manager
CC: Chris Ogg, American Structurepoint
Documentl
357 E flary!and St, Indianapolis, IN 46204-3608 � OFFICE 37?. 33.G12p I ONLINE WtVVJ.GLZ.t'Of4
!Akron Burns Harbor Chicago Cincinnati Cleveland Columbus Detroit Fort Wayne Frankfort Indianapolis Joliet Kalamazoo Lansing
Louisville iladison Melvindale Munster Pittsburgh Saint Joseph South Send Toledo
ata �!
1,11MOVATIVEIDEAS
EXCEPTIONAL DESIGN
SSkRCNITBCTurE.
jJj
ENGINERING • PLATn" � UNMATCHED CLIENT SERVICE
SURVEYING • CONSTRUCTION SERVICES
May 22, 2017
Mr. Jeremy Kashman
City Engineer
City of Carmel
One Civic Square
Carmel, IN 46032
RE: Contract Change Order #2
16 -ENG -16, 126th St and Gray Road Roundabout — PO# 100148
16 -ENG -54, 136th St and Gray Road Roundabout — PO# 100148S��v
16 -SW -107, Gray Road Culvert Replacement (Culvert #165) — PO# 1OQ149 nc�
.hl
Dear Mr. Kashman,
Please find the enclosed Change Order #2 for work associated with the 136th and Gray Rd
Roundabout project, PO# 100148. Below is a quick summary of the entire contract to date:
AMOUNT % of ORIGINAL CONTRACT
Original Contract $3,205,200.00.
Change Order #1 $87,364.65 2.73%
Change Order #2 $14,870.68 3.19%
A more complete Change Order Summary is included in these change order documents. Please
contact me if you need more information or have questions.
1
Manager
CC: Chris Ogg, American Structurepoint
Documentl
357 E flary!and St, Indianapolis, IN 46204-3608 � OFFICE 37?. 33.G12p I ONLINE WtVVJ.GLZ.t'Of4
!Akron Burns Harbor Chicago Cincinnati Cleveland Columbus Detroit Fort Wayne Frankfort Indianapolis Joliet Kalamazoo Lansing
Louisville iladison Melvindale Munster Pittsburgh Saint Joseph South Send Toledo
The Above Changes Are
Recommended:
DLZ Indiana, LLC,
Engineer
157 E. Maryland St.
Indianapolis, 13�L462
433.4f/Zo
Date � o
The Above Changes Are
Accepted:
Rieth-Riley Construction
Company, Inc
1751 W. Minnesota St.
Indianapolis, IN 46221
Approved:
Date �f� i
Jer y I as an, P , City
Engineer
ATTEST:
Christine S. Paul , Clerk
Treasurer
Date:
CITY OF CARMEL
TO: Rieth Riley Construction Co. CONTRACT CHANGE ORDER NO.: -2
1751 W. Minnesota St. DATE: May 16, 2017
Indianapolis, IN 46221 PROJECT NAME: 126th St and Gray Road Roundabout
136th St and Gray Road Roundabout
Gray Rd Culvert Replacement, Culvert 165
CITY P.O. NO.: 100148 and 100149 ����
CITY P.O. DATE: March 1, 2017
DCS'
I. You are directed to make the following changes in this Contract:
ITEM
For Project 16 -ENG -54, 136' and Gray Rd Roundabout, PO #100148, replace all 10" water line related
items for 136th and Grey Road with 12" items. Per the City of Carmel Water Department, Insta Valves
will be allowed in place of Team Valves for the 136th St. project only.
Upon excavation of the existing water mains for valve installation, it was discovered that the mains
were 12" in diameter and not 10" in diameter as shown on the plans and listed in the itemized proposal.
As 10" valves had been ordered and 12" valves would take up to 3 weeks to be delivered, Carmel
Water was asked if Insta Valves could be substituted for Team Valves as Culy Construction had Insta
Valves in stock. Carmel Water approved the substitution for 136th St and Grey Road only.
AMOUNT
See Attached
SCHEDULED ADJUSTMENT
(+) OR (-) DAYS
11. The following referenced documents further describe the changes outlined in Paragraph I, and are to be
considered a part of this Change Order:
R.F.P.: W.D.C.: #1
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Sum prior to this Change Order $3,292,564.65
Contract Sum will be increasedAWereased by this Change Order $14,870.68
New Contract Sum including this Change Order $3,307,435.33
Contract Time Prior to this Change Order 5/20/2017 Substantial Completion Date Days
Net increased/decreased resulting from this Change Order
Current Contract Time including this Change Order
6/20/2017 Final Completion Date Days
0 Days
5/20/2017 Substantial Completion Date Days
6/20/2017 Final Completion Date Days
This Change Order is for full and final settlement of all direct, indirect, impact costs and time extension incurred at
any time resulting from the performance of the changed work.
Quantity Adjustment 16-ENG-54,136th And Grey Road
Item
Unit Price Planned Otv
Revised
Otv Difference Cost
115, 10" DI Watermain
Lowering/Relocation
$347.07/LFT
200.0
0
<200.0>
<$69,414.00>
118, 10" Connections
$4,405.25/EA
2.0
0
<2.0>
<$8,810.50>
119, 10"x 10" Tapping
Saddle and 10"
Tapping Valve (Undist) $6,484.83/EA
1.0
0
<1.0>
<$6,484.83>
120, 10" Team Inserta
Valves (Undist)
$16,480.63/EA
2.0
0
< 2.0>
<$32,961.26>
EWA, 12" DI Watermain
Lowering/Relocation
$384.21/LFT
0
200.0
200.0
$76,842.00
EWA, 12" Connections
$4,735.64/EA
0
2.0
2.0
$9,471.28
EWA, 12"x12" Tapping
Saddle and 12"
Tapping Valve
(Undistributed)
$7,572.99/EA
0
1.0
1.0
$7,572.99
EWA, 12" Insta-Valve 250
(Undistributed)
$12,885.00/EA-
0
3.0
3.0
$38,655.00
TOTAL $14,870.68
IE TH IL E Y CONSTRUCTION CO., INC.
May 16, 2017 100% Quality • 100% Employee Owned • Over 100 Years
Mike Smith SENT VIA ELECTRONIC MAIL ONLY:
DLZ
Construction Observer Manager
157 E. Maryland Street
Indianapolis, IN 46204
RE: Gray Road at 136th Street RAB: City of Carmel Project No. 16 -ENG -54
Rieth-Riley Project No. 3200696
Dear Mr. Smith,
See new proposed pay item pricing based on our findings in the field. Please note that EWA-4 is to use a
12" Insta-Valve 250 rather than a Team Inserta Valve. This pricing is based on Carmel Water Utility
allowing the 12" Insta-Valve 250 substitution.
Item
Description
Quantity
Unit
Unit Price
Extension
315
10"
Di Water main Lowering/Relocation
-200.00
LF
$347.07
-$69,414.00
EWA -1
12"
DI Water main Lowering/Relocation
200.00
LF
$384.21
$76,842.00
318
10"
Connections
-2.00
EA
$4,405.25
-$8,810.50
EWA-2
12"
Connections
2.00
EA
$4,735.64
$9,471.28
319
10"x10" tapping saddle & 10" tapping valve (Undistributed)
-1.00
EA
$6,484.83
-$6,484.83
EWA-3
12"x12" tapping saddle & 12" tapping valve (Undistributed)
1.00
EA
$7,572.99
$7,572.99
320
10"
team inserta valves (Undistributed)
-2.00
EA
$16,480.63
-$32,961.26
EWA-4
12"
Insta-Valve 250 (Undistributed)
3.00
EA
$12,885.00
$38,655.00
The approximate cost of this contract adjustment based on unit prices is $14,870.68.
Please call with any questions.
Thanks
Lucas S. Clark
Project Manager
RIETH-RILEY CONSTRUCTION CO., INC.
cc: Gary Davis
Mike Jaskela
P.O. Box 276 -1751 W. Minnesota St. • Indianapolis, IN 46206
TOTAL 514,870.68
Phone: (317) 634-5561 • www.rieth-riley.com
CITY OF CARMEL
TO: Lucas Clark WORK DIRECTIVE CHANGE NO.: 1
Rieth Riley Construction Co DATE: May 2, 2017
1751 W. Minnesota St PROJECT NAME: 136th St and Gray Rd Roundabout
Indianapolis, IN 46221 PROJECT NO.: 16 -ENG -54
Specification Reference: Project TS #s 92
Drawing Reference: N/A
DESCRIPTION OF WORK COVERED BY THIS DIRECTIVE CHANGE: Replace all 10" water line
related items for 13e St with 12" items. Per the Carmel Water Department, Insta Valves will be
allowed in place of Team Valves for 1360' St only.
REASON FOR THIS ORDER: Upon excavation of the existing water mains for valve installation, it
was discovered that the mains were 12" in diameter and not 10" as shown on the plans and as listed in
the itemized proposal. As 12" items had been ordered and 10" valves would take up to 3 weeks to be
delivered, Carmel Water was asked if Insta Valves could be substituted for Team Valves as Culy
Construction had Insta Valves in stock. Carmel Water approved the substitution for 136th St only.
AUTHORIZATION:
THIS WORK DIRECTIVE CHANGE AUTHORIZES THE WORK TO BE COMPLETED AS
OUTLINED. A Contract Change Order in the amount of $14,870.68_(est) will be issued to you in the
near future to cover this Work Directive Change.
PROJECT COMPLETION DATE: ADD/DEDUCT/UNCHANGED -01 DAYS.
LIA
Project Manager (Engineering)
IM
Representative
PROJECT NO: 16 -ENG -16, 16 -ENG -54, 16 -SW -1 07
CONTRACTOR: Rieth Riley Construction Co.
INSPECTION CONSULTANT: DLZ Indiana
BID AMOUNT: E3.205.200.00
BID DATE:
02101/17
7;- q—DE5CRIP.,TIQWO CONTRACT- �"—'--'E0RESEEN"- TO*rA1:Z-:r RUNNING ORA :-
NGE, -_7 tHANG5
4:�Z. .7=.—FORESEEN--� --UNF -,CHANGE ORDER:-
ORESEEN-:�� —Z7f.
---XVVSER�=FSAMQUNT=7== MQUNTCHANGEQRDERS-.
rAPPROVED, 7�=,AMOUNT-E
001
FORESEEN
Owner directed changes at
$87,364.65 87,364.65 Get -N Go, Project 16 -SW-
I7, PO# 100149
05/17/17 $3,292,564.65 2.73%
2
UNFORESEEN
Replace 19'watermain
$14,870.68 102.235.33 relocation items with 12"
items, Project 16-ENG54,
PO# 100148
$3,307,435.33 0.46%
3.19
$87,364.65 $14,870.68 102,235.33 $3,307,435.33 2.73% 0.46%
Original Bid Amount
$3,205,200.00
Total Change Order(s) Amount
$102,235.33
Total Foreseen Change Orders
$87,364.65
Total Unforeseen Change Orders
$14,871
Total % Change Orders vs. Bid Amt.
3.19