HomeMy WebLinkAboutMillennium Contractors/Eng/CO #1/26,704.90/Multi Use Path Along Ditch RoadCity of Carmel Project 16 -ENG -20
Multi Use Path along Ditch Road
CHANGE ORDER #1
Extra work for Subgrade Treatment for new multi -use path.
Contract Price prior to this Change Order
------------------------------------------------------------------------------------------
Contract Price will be increased/decreased by this Change Order
------------------------------------------------------------------------------------------.
New Contract Price including this Change Order
-------------------------------------------------------------------------------------
$1,205,628.00
$26,704.90
$1,232,332.90
Amount Adjusted Contract
Price
Cumulative % Change
from Original Contract
Original Contract $1,205,628.00 $1,205,628.00
N/A
C01 $26,704.90 $1,232,332.90
2.22%
CITY OF CARMEL
TO: CONTRACT CHANGE ORDER NO.: 1
DATE: 6/28/2017
Millennium Contractors PROJECT NAME: Ditch Road Path
1401 South Holt Road CITY REQ. NO.:
Indianapolis, IN 46241 CITY PO NO.: 100284
ATTN: Andrew Closser CITY PO DATE: April 5, 2017 _
You are directed to snake the following changes in this Contract:
I. Where subgrade is not suitable to construct the trail, remove unsuitable material and
install geogrid with No. 53 compacted aggregate.
ITEM
5 - Excavation, Common
21 - Compacted Aggregate No. 53 Base
49 - Geogrid for Subgrade Stabilization
SCHEDULED ADJUSTMENT
AMOUNT (+) OR (-) DAYS
$15,183.00 + 7 Day
56,575.40 + 7 Day
$4,946.50 + 7 Day
The following referenced Documents further describe the changes outlined in Paragraph I, and
are to be considered a part of this Change Order: R.F.P.:
W.D.C. No.:
Other:
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order
$ 1,205,628.00
Contract Price will be increased/decreased by this Change Order
$ 26 704.90
New Contract Price including this Change Order
$ 1,232,332.90
Contract Time Prior to this Change Order 100 Days 7/14/2017
Completion Date
�
Net increased/deed-resulting from this Change Order 14
Days
Current Contract Time including this Change Order 114 Days
7/28/2017 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are
Recommended:
USI Consultants, Inc.
ENGINEER
8415 East 56` Street
Indianapolis, IN 46216
City/State/Zip
By:
Phone: 3 1-7-Ycf f- 3 7 sl
Date: (0/V- 13 Zol
The Above Changes Are
Accepted:
Millennium Contractors
CONTRACTOR
1401 South Holt Road
Indianapolis, IN 46241
Cit tate/Zip
133t
Phone: 3 07 S - rr - I
Date: (e I ag I n
Approved:
Treasurer
Date: 1
P Ed, a � ar USI Consultants, Inc.
4W1W [J Change Order Details
c-onsultants Ditch Road Path
Description: City of Carmel Project No. 16 -ENG -20 Multi Use Path Along Ditch Road
Change Order: 1 Date Created: 06/28/2017
Status: Pending Approval Date Approved:
Type: Changed Conditions
Summary: Subgrade Treatment for Trail Subgrade
Change Order Description: The subgrade for the path on Ditch Road was proofrolled, and extra work will
be required from STA 25+00 to the South (BOP).
Geogrid for the area from the first drive south, and 6" to 12" of undercutting
from the 5 Aces drive to STA 25+00 just north of the two structures, along with
geogrid and No. 53 compacted aggregate.
This is an unforeseen site condition, and will be completed using existing pay
items with the exception of a new item for geogrid.
Awarded Project Amount:
$1,205,628.00
Authorized Project Amount:
$1,205,628.00
Change Order Amount:
$26,704.90
Revised Project Amount:
$1,232,332,90
Increases/Decreases
Line Number Item Unit Unit Price Current Change Revised
Quantity Amount Quantity Amount Quantity Amount
Section: 1 - Default Section
5 Ditch Rd Path 5 CYS $70.000 960.00 $67,200.00 216.90 $15,183.00 1,176.90 $82,383.00
EXCAVATION, COMMON
Reason: Stabilize Subgrade for Trail
21 Ditch Rd Path 21 TON
COMPACTED AGGREGATE NO. 53 BASE
Reason: Stabilize Subgrade for Trail
(2 Items)
$42.340 1,940.00 $82,139.60 155.30 $6,575.40 2,095.30 $88,715.00
Totals $149,339.60 $21,758.40 $171,098.00
Change Order Details: Ditch Road Path Page 1 of 2 06/28/2017
New Items
Line Number item
Section: 1 • Default Section
0920 Ditch Road Path 92
Geogrid for Subgrade Treatment
Reason: Stabilize Subgrade for Trail
(1 Item)
Time Limits
"Type Original Deadline
Completion Date 07/14/2017
Substantial Completion
Reason: Additional Work Added
(1 Tlnae Limit)
Unit Pending Quantity Unit Price
SYS 11522.00 $3.250
Total:
Authorized Deadline
07/14/2017
This change order is approved for construction,
Dollar Amount
$4,946.50
+54,946.50
Pending'Extension Pending Deadline!
14 Days 07/28/2017
20
i v
Scott Dick - USI Consultants Inc. Date
& "'N. (a eZ3 -71911%
Millennium Co actors, LLC Date
City of Carmel Date
Change Order Details: Ditch Road Path Page 2 of 2 07/05/2017