Loading...
Globe Asphalt Paving Co., Inc/Eng/ CO #3/40,055.60/Mulit Use Trail Along Towne Road – Project #16-SW-18City of Carmel Project 16 -SW -18 Multi Use Trail along Towne Road CHANGE ORDER # 3 Additional work was required for remobilization, borrow, and balance existing Items. Contract Price prior to this Change Order ------------------------------------------------------------------------------------------ Contract Price will be increased/decreased by this Change Order ---------------•------------------....----------------..----------------------------..... $564,482.56 $40,055.60 New Contract Price inClUding this Change Order $604,538.16 Amount Adjusted Contract Price Cumulative % Change from Original Contract Original Contract $503,892.58 $503,892.58 N/A C01 $39,871.98 $543,764.56 7.91% CO2 $20,718.00 $564,482.56 12.02% CO3 $40,055.60 $604,538.16 19.97% TO: Globe Asphalt Paving Co., Inc. P.O. Box 19168 Indianapolis, IN 46219 ATTN: Tim Toby CITY OF CARMEL CONTRACT CHANGE ORDER NO.: 3 (Final) DATE: 9/27/2017 PROJECT NAME: Towne Road Trail CITY REQ. NO.: CITY PO NO.: 100180 CITY PO DATE: February 16, 2017 �eROL� I. You are directed to make the following changes in this Contract: 1. This change order will add two new items, and balance the existing items for this contract. See page 2 through 5 for additional information. This is the final change order. SCHEDULED ADJUSTMENT ITEM AMOUNT (+) OR (-) DAYS 52 - Remobilization $5,150.00 + 0 Day 53 - Borrow $5,220.00 + 5 Day 1 — 51 Existing Contract Items $29,685.60 + 10 Day II. The following referenced Documents further describe the changes outlined in Paragraph 1, and are to be considered a part of this Change Order: R.F.P.: W.D.C. No.: Other: The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $ 564 482.56 Contract Price will be increased/deereased by this Change Order $ 40,055.60 New Contract Price including this Change Order $ 604,538.16 Contract Time Prior to this Change Order 100 Days 7/13/2017 Completion Date Net increased/decreased-resulting from this Change Order 15 Days Current Contract Time including this Change Order 115 Days 7/28/2017 Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are Recommended: USI Consultants, Inc. ENGINEER 8415 East 5601 Street Address Indianapolis, IN 46216 ,( City/State/ Ip By: Phone: z 7 YY/ 3751 Date: 1 D Z 201 The Above Changes Are Accepted: Globe Asphalt Paving Co., Inc. CONTRACTOR P.O. Box 19168 Address Indianapolis, IN 46219 Date 27/Zal-) Approved: USI Consultants, Inc. ❑ Change Order Details cc)nsultants Towne Road Trail Description: City of Carmel Project No. 16 -SW -18, Towne Road Trail and Culvert 1,092.00 Replacement 96th Street to 106th Street Change Order: 3 Date Created: 09/27/2017 Status: Pending Approval Date Approved: Type: Changed Conditions Summary: Remobilization, Borrow, and Minor Overrruns Change Order Description: Hemobilization - Now Item 52 2,943.00 Three subcontractors on this project were required to suspend their work due to utility conflicts, and Right of Way that was not acquired prior to construction activities. When the issues were resolved they returned to the site and resumed work. Through negotiations with the contractor the amount was reduced to $5,150.00 Awarded Project Amount: Authorized Project Amount: Change Order Amount: Revised Project Amount: Increases/Decreases Line Number Item Section: 1 - Default Section 4 Towne Road Item 4 EXCAVATION, COMMON Reason: Balancing Change Order 6 Towne Road Item 6 TEMPORARY SILT FENCE Reason: Balancing Change Order Borrow - New Item 53 Unsuitable common excavation was removed from the project site, and could not be used for back fill against the trail. The quantity undercut was 42 percent of the common excavation quantity. Assuming 42 percent of the material was unsuitable the amount of borrow required would equal 332 CYS. The contractor agreed to accept 180 CYS as payment for the completed work. Balance Existing Items Item 1 - 51 The existing items were completed substantially as planned. Due to slight changes required during construction these items exceeded the previously approved contract by $29,685.60. $503,892.58 $564,482.56 $40,055.60 $604,538.16 Unit Unit Price Current Change Revised Quantity Amount Quantity Amount Quantity Amount C.Y. $26.510 1,092.00 $28,948.92 378.00 $10,020.78 1,470.00 $38,969.70 L. F. $2.100 3,066.00 $6,438.60 -123.00 -$258.30 2,943.00 $6,180.30 Change Order Details: Towne Road Trail Pagel of 4 09/27/2017 ,Line Numberr Item Unit •; Uuit Price Current Change Revised $81.380 i 1 . Quantity Amount Quantity Amount Quantity ` �nountl STRUCTURE BACKFILL, TYPE 5 8 Towne Road Item 8 C.Y. $42.000 143.00 $6,006.00 4.99 $209.58 147.99 $6,215.58 V STRUCTURE BACKFILL, TYPE I Reason: Balancing Change Order 9 Towne Road Item 9 C.Y. $42.000 56.00 STRUCTURE BACKFILL, TYPE 2 Reason: Balancing Change Order $2,352.00 -0.30 -$12.60 55.70 $2,339.40 10 Towne Road Item 10 C.Y. $81.380 101.00 $8,219.38 55.75 $4,536.94 156.75 $12,756.32 STRUCTURE BACKFILL, TYPE 5 Reason: Balancing Change Order 13 Towne Road Item 13 TON $88.000 791.00 $69,608.00 45.75 $4,026.00 836.75 $73,634.00 l" HMA FOR SIDEWALK (MULTI -USE PATH) Reason: Balancing Change Order 14 Towne Road item 14 SYS $52.500 23.00 $1,207.50 9.11 $478.28 32.11 $1,685.78 SIDEWALK, CONCRETE Reason: Balancing Change Order 15 Towne Road Item 15 SYS $152.250 93.00 $14,159.25 -1.22 -$185.74 91.78 $13,973.51 CURB RAMP, CONCRETE Reason: Balancing Change Order 18 Towne Road Item 18 L.F. $36.750 86.00 $3,160.50 ----------•---------•--------- 61.50 $2,260.13 - 147.50 $5,420.63 CURB AND GUTTER, CONCRETE Reason: Balancing Change Order 19 - Towne Road Item 19 L.F. $31.500 74.00 $2,331.00 -0.20 -$6.30 73.80 $2,324.70 CURB AND GUTTER ROLL CURB Reason: Balancing Change Order 21 Towne Road Item 21 SYS $13.590 82.00 $1,114.38 9.33 $126.79 91.33 $1,241.17 GEOTEXTILES Reason: Balancing Change Order 22 Towne Road Item 22 TON $84.000 62.00 $5,208.00 21.82 $1,832.88 83.82 $7,040.88 RIPRAP, REVETMENT Reason: Balancing Change Order 23 Towne Road Item 23 SYS $3.680 4,000.00 $14,720.00 8 00. 00 $2,944.00 4,800.00 $17,664.00 MULCHED SEEDING U Reason: Balancing Change Order 24 Towne Road Item 24 C.Y. $52.500 4.00 $210.00 4.00 -$210.00 0.00 $0.00 TOPSOIL Reason: Balancing Change Order 25 Towne Road Item 25 EACH $498.750 13.00 $6,483.75 1.00 $498.75 14.00 $6,982.50 PLANT, DECIDUOUS TREE, SINGLE STEM, OVER 2 IN. TO 2.5 IN, Reason: Balancing Change Order 27 Towne Road Item 27 EACH $262.500 1.00 $262.50 1.00 $262.50 2.00 $525.00. VALVE BOX (ADJUST TO GRADE) Reason: Balancing Change Order 30 Towne Road Item 30 L.F. $47.880 419.00 $20,061.72 -79.00 -$3,782.52 340.00 $16,279.20 PIPE, TYPE 2, CIRCULAR, 12 1N, Reason: Balancing Change Order Change Order Details: Towne Road Trail Page 2 of 4 09/27/2017 `L,iete'it+larsugor It9m' ...Unit + 31 Towne Road Item 31 L. F. PIPE, TYPE 2, CIRCULAR, 15 IN, Reason: Balancing Change Order ^ +'unit Price $50.660 Cuitent Quantity Amount 40.00 $2,026.40 a Change 'Quantity "bunt 31.00 $1,570.46 ReA ed Quantity + Amount 71.00 $3,596.86 32 Towne Road Item 32 L.P. $309,750 -14.00- $4,336.50 3.00 $929.25 17,00 $5,265.75 PIPE, TYPE 1, DEFORMED, MIN. AREA 15.6 SFT Reason. Balancing Change Order Reason: Balancing Change Order 33 Towne Road Item 33 TON $125.000 �""'""--•'""_""""•`•••__ 59,00 $7,375.00 ,..__.w._.w._..___......__..___.__.._.._____.._._.__ 6.47 $808.75 65.47 $8,183.75 HMA FOR STRUCTURE INSTALLATION, TYPE B 42 Towne Road Item 42 EACH $194,250 2.00 $388.50 2.00 $386.50 Reason: Balancing Change Order $777.00 ROAD CLOSURE SIGN ASSEMBLY 34 Towne Road Item 34 EACH ^^$866.250 6.00 $6,930.00 2.00 $1,732.50 -10.00 $8,662,50 PIPE END SECTION, DIAMETER 12 IN. ..._,.__...._...._......- ... __._._._............___-_.___....... 43 Towne Road Item 43 EACH $120,750 ... __ 21.00 Reason: Balancing Change Order �_.... _..._ 3.00 _...._.__... $362.25 _ _.__.._ 24.00 _._.... _ $2,898.00 DETOUR ROUTE MARKER ASSEMBLY 38 Towne Road Item 38 EACH $1,417.500 3.00 $4,252.50 -1,00 •$1,417.50 2.00 $2,835.00 / PIPE CATCH BASIN, 24 IN. Reason: Balancing Change Order $420.000 4.00 $1,680.00 -2.00 -$840.00 2.00 $840.00 40 Towne Road Item 40 S.F. $18.680 193.00 $3,605.24 43.60 $814.45 235.60 $4,419.69 MODULAR BLOCK WALL Reason: Balancing Change Order v/ Reason: Balancing Change Order 0490 Towne Road item 49 SYS $6.500 1,500.00 $9,750.00 60.61 41 -- Towne Road Item 41 S.F. $50.500 _ 193.00 $9,746.50-- 43.60 $2,201.80 236.60 $11,948.30 MODULAR BLOCK WALL ERECTION Reason. Balancing Change Order 42 Towne Road Item 42 EACH $194,250 2.00 $388.50 2.00 $386.50 4.00 $777.00 ROAD CLOSURE SIGN ASSEMBLY Reason: Balancing Change Order ..._,.__...._...._......- ... __._._._............___-_.___....... 43 Towne Road Item 43 EACH $120,750 ... __ 21.00 ............... $2,535.75 �_.... _..._ 3.00 _...._.__... $362.25 _ _.__.._ 24.00 _._.... _ $2,898.00 DETOUR ROUTE MARKER ASSEMBLY Reason: Balancing Change Order 48 Towne Road Item 48 EACH $420.000 4.00 $1,680.00 -2.00 -$840.00 2.00 $840.00 SIGN, SHEET, RELOCATE Reason: Balancing Change Order 0490 Towne Road item 49 SYS $6.500 1,500.00 $9,750.00 60.61 $393.97 1,560.61 $10,143.97 Geogrid for Subgrade Stabilization Reason: Balancing Change Order 17 1 89 $112,663;491 ,..,ibtAls ,' ;i .. a4311 New Items Line Nuinber It + Unit;• „' ;, ' Pending Quanifty',. .XPriit p.-��e DolfarAmopn ` n . Sijction 1 -Defaults ctlon a P;. s.;.y •;+ :,. %;.t . !taifi;U•".,, "•$p ,j ., . 0520 Towne Road Item 52 LSUM 1.00 $5,150.000 $5,150.00 Remobilization for Subcontractors Reason: Contractors were delayed by utilities and right of way issues. Change Order Details: Towne Road Trail Page 3 of 4 09/27/2017 ;Lino Number Item Unit Pending Quantity Unit PriceDollar Amount' 0530 Towne Road Item 53 CYS 18 0. 00 $29.000 $5,220.00 Borrow Reason: Backfill Trail with Suitable Material (2 Items) , Total: +S�0,370.00I _._ .. of . This Change Order is Approved For Construction. / 0/ Z/0-0.1-7 Cameron Meredit - USI Consultants Inc. Date be Asphalt Paving Date i City of Carmel Date Change Order Details: Towne Road Trail Page 4 of 4 09/27/2017 Memo To: Doug Haney, Corporation Counsel From: Lisa Scott CC: Jeremy Kashman Date: 10/10/17 Re: C.O. #3 Project #16 -SW -18 Multi -Use Path along Towne Road Doug, please find attached 2 originals of same change orders for project #16 -SW -18 Multi -Use Path along Towne Road. Please review & initial for the next BPW Meeting. Change Order #3 - Original Contract Amount: $503,892.58 Increase: $40,055.60 New Contract Amount: $604,538.16 Thank you, Lisa Scott 0 Page 1