Loading...
HomeMy WebLinkAboutRieth-Riley/Eng/CO #3/52,244.51/Rangeline Road & 4th Street ConstructionCity of Carmel Project 16 -ENG -31 CCHANGE ORDER #3 T&M tickets for Carmel Utility repairs, requested over time work to meet requested schedule to open Range Line and 4' Street intersection, and mobilization of archway. Contract Price prior to this Change Order $7,035,183.30 Contract Price will be increased by this Change Order $52,244.51 New Contract Price including this Change Order $7,087,427.81 ------------------------------------------------------------------------------------------- PO -100472 Veterans Way PO -100473 RL & 4"' RAB PO -100473 4`h SW West Contract Price Cumulative % Change from Original Contract Original Contract $2,797,315.57 $654,132.69 $501,298.89 $5,378,409.93 N/A Change Order 1 $1,605,251.69 $6,983,661.62 30% Change Order 2 $51,521.68 $7,035,183.30 1% Change Order 3 $52,244.51 1% Adjusted Amount $4,454,088.94 $706,377.20 $7,087,427.81 CITY OF CARMEI. TO: Rieth Rile% Construction Co. Inc. ('ON 1 RAC I C'l IANGF ORDLI( NO.: 1751 West Minnesota Street DATE: 11 16 17 Indianapolis. IN 46221 PROJECT NA\IF: I6-ENCi-31 C'IT Y REQ. No.: CH Y PO NO.: 100.173 CI Il' PO ix.vm: 61%211 17 L You arc directed to make the ti)llot%ing change- in thk Contract: Add additional item, item.. du-- w moklifications in the field and re,luests Isom C armel l lility Departments. �( I II IWI.1.D ADJUS1\I1::NT ITLXI \IO "I t-) OR t - 1 DAYS See detail of items and etmmar\ of changed costs in attached Table To FAL OF CI1 \\( 11 (IR I)FR Il"E\IS I 552.244.51 0 Dacs IL "fhe f)llotcin. rel�nmced Documents lbrther describe the ehan_cs outlined in Paragraph I. and are to be considered a part of this Change Order: R.F.P.: n_jW.D.C. NO.: n'a Other: _ lh Reuue.t from the Cit% of.'amtcl Per Proposals included herein the changes result in the Iiilloaing adjustment of Contract Price and Contract "Tillie Contract Pricc prior to this Change Order 57,1135.183.30 Contract Price %%ill be increased M this Change OrderS52,244.51 lie%% Contract Price including this Chance Order -087.427 81 Contract 1 ime prior to this Change Order 150 Da%s October 1 2017 Completion Dale Nei increased resulting Dont this Change Order 0 Dass Current Contract I ime including this Change Order October 1 3017 Completion Dale 'chis Change Order is for full and final settlement of all direct. indirect. impact costs and time extensions incurred at am time resulting Lotti the performance of the changed cork. The Aho\ e Change: Are Recommended The Above Changes Are .Accepted Approved Cltt ►SSROAD FN( ill Ir. 1 P FN61NEER 3417 Sherman Dri\e Address Bccch Ciro e. l\ 4h,107 Cil State:'7.ip B\: ze0i;"VL1� Phone: 317-780-1555 Dalc: Rieth-Rilev Construction Co. Inc C'ON"TRACTOR 1751 Melt \linnc.,wt, Street Address Indianapolis. IN 46221 A I a r,—E James Brainard.-la%or 17 -ENG -01 - Veteran's Way Construction CHANGE ORDER #1 TABLE Item No. Description Unit Original Unit Price Quantity Original Amount Final Quantity Final Amount Over/Undtr 156 Range Line RAB T&RI Tickets LFT S 52,244.51 0 S 1 S 5:.244.51 S 52,244.51 TOTAL OF CHANGE ORDER ITEMS S 52,24451 ORIGINAL CONTRACT PRICE 5 7,035,183.30 FINAL CHANGE ORDER #1 S 52,244 51 NEW CONTRACT AMOUNT INCLUDING APPROVED CHANGE ORDERS S 7,087,427.81 17 -ENG -01 - VETERAN'S WAY CONSTRUCTION EXHIBIT A You have been directed to make the following changes in this Contract: Item Description Reason For Change No. 156 Ran a Line RAB T&M Tickets IT&M tickets for Carmel Utility repairs. requested OT work, Archway mobilization