HomeMy WebLinkAboutRieth-Riley Construction Co, Inc/Eng/CO #2/96th and Hazel Dell RAB – Project #16-ENG-35City of Carmel Project 16 -ENG -35
96th Street and Hazel Dell RAB
CHANGE ORDER #2
As part of the City of Carmel's Right -of -Way negotiations with Martin Marietta (American Aggregates
Corporation). It is being required that Martin Marietta, the property owner on the Northwest corner, be
added as an additional insured to the contractors (Rieth-Riley) insurance policy for project 16 -ENG -35 (96`,
Street and Hazel Dell RAB). This change order will be a zero dollar / zero time change order, but is being
generated to document the request.
Contract Price prior to this Change Order $1,584,344.14
Contract Price will be increased/decreased by this Change Order $0.00
New Contract Price including this Change Order
$1,584.344.14
Amount
Adjusted Contract
Price
Cumulative % Change
from Original Contract
Original Contract ; $1,588,508.79
$1,588,508.79
N/A
C01— Const Chng 1 $(4,164.65)
$1,584,344.14
(0.3%)
CO2 — MM Add Insured $0.00
$1,584,344.14
(0.3%)
CITY OF CAR�1,,iEL
TO: CONTRACT CHANGE ORDER NO.: 2
Chris Ogg DATE: 1/3/2018
One Civic Square PROJECT NAME.~ 16 -ENG 3�;
Carmel, IN 46032 CITY REQ. NO.: N/A
CITY PO NO.: 100624 - General Oblieation Bond
CITY PO DATE: 812/2017
I. You are directed to make the following changes in this Contract:
(Brief Description)
As part of the City of Carmel's Right -of -Way negotiations with ?Vlartin Marietta (American
Aggregates Corporation). It is being required that Martin -Mar etta, the property owner on the
Northwest corner, be added as an additional insured to the contractors (Rieth-Riley) insurance
policy for project 16 -ENG -36 (96'h Street and Hazel Dell RAB). This change order will be a zero
dollar/ zero time change order, but is being generated to document the request.
SCHEDULED ADJUSTMENT
ITEM A110UNIT (+) OR (_) DAYS
N/A 50.00 0
11. The following referenced Documents further describe the changes outlined in Paragraph I, and
are to be considered a part of this Change Order: R.F.P.: N/A W.D.C. No.: N/A
Other:
The chan-es result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order S1.584.344.14
Contract Price will be increased/decreased by this Change Order $ 0.00
New Contract Price including this Change Order V S 1.58=1.3=1=1.14
Contract Time Prior to this Change Order 74 Days 12/13/17 Completion Date
Net inereased/decreased resulting from this Change Order 0 Days
Current Contract Time including this Change Order 74 Days 12/13/17 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
AR -6
Vemitrn 2016.08-:31
The Above Changes Are
Recommended
CHA
ENGINEER
300 S. Meridian Street
The Above Changes Are
Accepted:
Rieth-Riley Construction
CONTRACTOR
1751 W. Minnesota Street
Approved:
ard,
Address Address Nlary n r • , hI
r
Indianapolis, hit 46225 Indianapolis, hN 46721 _ _
Lori W, tso , lember
City/State/Zip City/State/Zip Jererp.
fRasiuTZIn, , City
Phone: 10 - 07.3 7 4 0
Date: 1/ 3 /2e 18
Date:
AR -6
Versim -V 16-18-31
.
�A
Christine S. Pa ley, Clerk -
Treasurer
Date:
Memo
To: Doug Haney, Corporation Counsel
From: Lisa Scott
CC: Jeremy Kashman
Date: 01/23/18
Re: C.O. #2 — Project 16 -ENG -35 9e and Hazel Dell RAB
Doug, please find attached 1 original of same change order for project #16 -ENG -35 96th Street & Hazel Dell RAB
Project. Please review & initial for the next BPW Meeting.
Change Order #1 - Original Contract Amount: $1,588,508.79 Increase: $0- Additional Insured Added New
Contract Amount $1,584,344.14
Thank you,
Lisa Scott
0 Page 1