Loading...
HomeMy WebLinkAboutRieth-Riley Construction Co, Inc/Eng/CO #2/96th and Hazel Dell RAB – Project #16-ENG-35City of Carmel Project 16 -ENG -35 96th Street and Hazel Dell RAB CHANGE ORDER #2 As part of the City of Carmel's Right -of -Way negotiations with Martin Marietta (American Aggregates Corporation). It is being required that Martin Marietta, the property owner on the Northwest corner, be added as an additional insured to the contractors (Rieth-Riley) insurance policy for project 16 -ENG -35 (96`, Street and Hazel Dell RAB). This change order will be a zero dollar / zero time change order, but is being generated to document the request. Contract Price prior to this Change Order $1,584,344.14 Contract Price will be increased/decreased by this Change Order $0.00 New Contract Price including this Change Order $1,584.344.14 Amount Adjusted Contract Price Cumulative % Change from Original Contract Original Contract ; $1,588,508.79 $1,588,508.79 N/A C01— Const Chng 1 $(4,164.65) $1,584,344.14 (0.3%) CO2 — MM Add Insured $0.00 $1,584,344.14 (0.3%) CITY OF CAR�1,,iEL TO: CONTRACT CHANGE ORDER NO.: 2 Chris Ogg DATE: 1/3/2018 One Civic Square PROJECT NAME.~ 16 -ENG 3�; Carmel, IN 46032 CITY REQ. NO.: N/A CITY PO NO.: 100624 - General Oblieation Bond CITY PO DATE: 812/2017 I. You are directed to make the following changes in this Contract: (Brief Description) As part of the City of Carmel's Right -of -Way negotiations with ?Vlartin Marietta (American Aggregates Corporation). It is being required that Martin -Mar etta, the property owner on the Northwest corner, be added as an additional insured to the contractors (Rieth-Riley) insurance policy for project 16 -ENG -36 (96'h Street and Hazel Dell RAB). This change order will be a zero dollar/ zero time change order, but is being generated to document the request. SCHEDULED ADJUSTMENT ITEM A110UNIT (+) OR (_) DAYS N/A 50.00 0 11. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: R.F.P.: N/A W.D.C. No.: N/A Other: The chan-es result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order S1.584.344.14 Contract Price will be increased/decreased by this Change Order $ 0.00 New Contract Price including this Change Order V S 1.58=1.3=1=1.14 Contract Time Prior to this Change Order 74 Days 12/13/17 Completion Date Net inereased/decreased resulting from this Change Order 0 Days Current Contract Time including this Change Order 74 Days 12/13/17 Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. AR -6 Vemitrn 2016.08-:31 The Above Changes Are Recommended CHA ENGINEER 300 S. Meridian Street The Above Changes Are Accepted: Rieth-Riley Construction CONTRACTOR 1751 W. Minnesota Street Approved: ard, Address Address Nlary n r • , hI r Indianapolis, hit 46225 Indianapolis, hN 46721 _ _ Lori W, tso , lember City/State/Zip City/State/Zip Jererp. fRasiuTZIn, , City Phone: 10 - 07.3 7 4 0 Date: 1/ 3 /2e 18 Date: AR -6 Versim -V 16-18-31 . �A Christine S. Pa ley, Clerk - Treasurer Date: Memo To: Doug Haney, Corporation Counsel From: Lisa Scott CC: Jeremy Kashman Date: 01/23/18 Re: C.O. #2 — Project 16 -ENG -35 9e and Hazel Dell RAB Doug, please find attached 1 original of same change order for project #16 -ENG -35 96th Street & Hazel Dell RAB Project. Please review & initial for the next BPW Meeting. Change Order #1 - Original Contract Amount: $1,588,508.79 Increase: $0- Additional Insured Added New Contract Amount $1,584,344.14 Thank you, Lisa Scott 0 Page 1