Loading...
HomeMy WebLinkAboutRieth-Riley Construction Co, Inc/Eng/CO #1/2,580/96th and Gray Road RAB – Project #16-ENG-34City of Carmel Project 15 -ENG -33 96th Street and Delegates Row RAB CHANGE ORDER #1- INLINE BMP STRUCTURE TS 58 — Stormwater Quality Structure BNIP notes as a standard specification that all units are to be placed off-line. Due to utility conflicts with BMP Str 130A located at 40*30 Lt, the plans show it as an in-line structure. No questions were asked by any of the contractors prior to bid, whether this structure should be off-line vs. in-line. Rieth-Riley stated that their submitted bid price of 522,959.48 was for an offline structure and that there would be additional material costs associated with an inline structure. Efforts were taken to see if the structure could be changed to an off-line but was determined due to utility constraints the structure needed to remain in-line. Several in-line structure options and prices were submitted by Rieth- Riley and it was determined that the Contech CDS3035-6-C was acceptable as an in-line structure. The costs associated with this change order is for the material difference only between Rieth-Riley's original submitted quote from Ferguson Waterworks and Contech's new price. This Change Order I will result in an increase of $2,580.00 to the project. Contract Price prior to this Change Order Contract Price will be increased/decreased by this Change Order New Contract Price including this Change Order $1,480,798.49 $2,580.00 $1,483,378.49 Amount Adjusted Contract Cumulative % Change Price from Original Contract Original Contract $1,480,798.49 $1,480,798.49 N/A --��-� ]CO1-- In -Line OMP $2,580.00 $1,483,378.49 0.17% CITY OF CARMEL `� G� TO: CONTRACT CHANGE ORDER NO.: t Chris Ogg DATE: 1/23/2018 One Civic Square PROJECT NAME: 16 -ENG -33 Carmel, W 46033 CITY REQ. NO.: N/A CITY PO NO.: 100569 — 2016 Storm Water Bond CITY PO DATE: 7/15/2017 I. You are directed to make the following changes in this Contract: (Brief Description) TS 58 — Stormwater Quality Structure BNIP notes as a standard Specification that all units are to be placed off -tine. Due to utility conflicts with BNIP Str 130A located at 40+30 Lt, the plans show it as an in-line structure. No questions were asked by any of the contractors prior to bid, whether this structure should be off-line vs. in-line. Rieth-Riley stated that their submitted bid price of S22,959.48 was for an offline structure and that there would be additional material costs associated with an inline structure. Efforts were taken to see if the structure could be changed to an off-line but was determined due to utility constraints the structure needed to remain in-line. Several in-line structure options and prices were submitted by Rieth-Riley and it was determined that the Contech CDS3035-6-C was acceptable as an in-line structure. The costs associated with this change order is for the material difference only between Rieth-Riley's original submitted quote from Ferguson Waterworks and Contech's new price. This Change Order I will result in an increase of $2,580.00 to the project. SCHEDULED ADJUSTMENT ITEM AMOUNT (+) OR (-) DAYS 59 — BMP, Water Quality - (S22,959.48) 0 112 — BMP, Water Quality 525,539.48 0 In -Line 1I. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: R.F.P.: N/A W.O.C. No.: N/A Other: The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order S 1.480.798.49 Contract Price will be increased/decreased by this Change Order S 2.580.00 New Contract Price including this Change Order y S 1,483.378.49 AR -6 version 2016-08-31 Contract Time Prior to this Change Order 74 Days 10/13/17 Completion Date Net increased/decreased resulting from this Change Order 0 Days Current Contract Time including this Change Order 74 Days 10/13/17 Completion Date This. Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at anv time resulting from the performance of the changed work. The Above Changcs Are The Above Changes Are Approved: Recommended Accepted: CHA Rieth-Riley Construction ENGINEER CONTRACTOR J BrainMa 300 S. Meridian Street 1751 W. Minnesota Street `? Address Address Mary n B NJamber Indianapolis, IN 46225 Indianapolis, IN =1623 l �City/State/Zip Lo i W• M ber �my City/State/Zip J ashman, PE, City neinee r BY: Phone: ZWT - 40-r- 37 60 Date: it 30116 ,• _" ATT "ristine Treasurer Date: Date: AR -6 version 20164}8-31 C*#qNTECH` ENGINEERED SOLUTIONS A Q1l/NRETE® cOM'PA' NY Quotation Page# 1/3 Quote # QUO-303451-GOC9F8 DRAFT DOCUMENT Date 1/16/2018 Account Name All Bidder - Marko Popovich Quote # QUO-303451-GOC91`8 Contact Name Marko Popovich Contech Rep. Scott Foy Phone (513) 857-9836 Address 200 John Williams Ave, Mitchell, IN, 47446 Project Name Carmel IN Roundabouts Fax Phone 812-583-2303 96th & Gray, 96th & Delegates Project # 580909 Email Mpopovich@Conteches.com Fax 812-849-5974 r� Project Carmel, IN Emall SFoy@contadhes com'x City/State 1:J contech's offer to sell the products described In this quotation Is expressly conditioned upon Buyer's assent to the Contech conditions of Sale ("Contech CCSjl included here}vlth�andlor viewable et www,conteches.cornkos. A valid tax exemption certificate must be Issued to Contech or sales tax will be added. ly' Item e•n,. Price CD53035-6-C - Site Designation: 130A, Screen Aperture Size: 1.00 1.00 $1t3 7'00.00 EA $16,700 00 2400, Rim Elev : 743.67, Outlet 1 Invert: 736.10, Heaviest Pick Weight: Est. HPW = 18,000 lbs, Notes for Quote : 44x28 ERCP " pipe. lz�, CDS3035-6-C - Site Designation: 224A, Screen Aperture Size: 1.00 1.00 $16 700 00, EA $16,700.00 2400, Rim Elev : 738.72, Heaviest Pick Weight: Est. WPW = 18,000 lbs 'v Total $33,400.00 (Tax not Incded)W . NeE Total $33,400.00 1.A fuel surcharge will be added to the invoices for each shipment amounting to $ ' :1 and Buyer agreesio, pay for these cljarges. 2Allowable unloading time for delivery trucks Is one (1) hour. Demurrage chargesof $7v,5.00 per houf thereafter will Ue added. 3.Pdces are f.o.b. origin with freight allowed to the jobsile hop acing by others at a trucil,accessible location ,='" 4.Product-Specific Terms & Conditions: Price Prices are` bt3 plent,wlth freight allowed g-j6bsile and unloading by others. Order Cancellation For Stormwater Treatment product only. Supercedes cancellation terms oh company T&C a Purchaser may cancel this order due to project cancellation. In the event of such cancellation, Purchaser will -be liable for payment as follows: 15% of the quoted amount If the order is cancelled prior to approval of submittals; 25% of the quoted amount If the *Wis cancelled after the.approvai of submlttals,,,50% of the quoted amount if the order has been released to manufacture, plus any amounts Seller incurs1{om outside vendors (precasters, fabricators -Orders cancelled for reasons other than project cancellation may be billed at greater amounts at the sole 4iQretion of Seller 'Seller ssecurity interest snail survive any cancellation or termination of this agreement. Submittal Approval Purchaser acknowledges tfik Seller or his agent shall. accomplish produgtton of ordered products In accordance with approved submittals signed by Purchaser. Producdon't f eald,produ- t% -,.-VIII commence onjy"upon receipt of purchase order and receipt by Seller of approved submittals. Delivery and Installation Purchaser agrees to;provide suitable access' (of Seller's delivery trucks, traffic control and labor, and at least two people to assist in the unloading of the, products Price`l-gd'udes one-hour waiting time"and one hour off-load time. Delays caused by the Purchaser, which are over and above the two hour period, will be billed,,a ecost of no less than $125 per hour and based upon vendor charges to Seller. Unit price does not Include lifting ,egtilprrent. Customer Is "responsiblefor supplying acrane of sufficient lift and reach capacity and rigging for lifting system(s) and/or system componehts,off delivery trucks setting In place and WLrelated construction and site activity to and from the system including bed preparation of crushed orfs oC other. Seller will under no circ4rnstances accept back -charges without prior written approval. Should problems arise during delivery/t 1 ailon, Seller must be notified by Purchaser immedl.ately. Failure to do so may result in additional costs to Purchaser that cannot be credited. further hold Purchasaro s to provide a safe deliverysite and comply with all' Federal, State and local safety requirements. Purchaser agrees to Seller harmless an igXdefend any and all actions, clallnsAsuits, and proceedings that may subject Seller to liability due to Purchaser's failure to provide a safe delivery sites. ' r - h:. V% FERGUSON- Page 3 of 4 FERGUSON WATERWORKS #1934 Waterworks Price Quotation 16:52:50 JUN 19 2017 Reference No: 8149199 Item Description Fax: 317-546-2318 Quantity Net Price UM Total ADS WQU SP-DOWNSTREAM6 DOWNSTREAM DEFENDER 6' WQU 1 14120.000 EA 14120.00 SUBTOTAL 14120.00 (16-1NG-33) 96TH ST. & DELEGATES ROW & (16 -ENG -34) 96TH ST. & GRAY RD. BMP MATERIAL COST DIFFERENCE OFF-LINE STR VS. INLINE STR. 6/19/2017 ORIGINAL OFF-LINE PROPOSED ADS IN-LINE UNITS QUOTE DENIED DATE MATRIAL DESCRIPTION ITEM UNIT $ UNIT UNIT $ UNIT $ DIFFERENCE 9/19/2017 ADS (IN-LINE 8' FIRST DEFENSE HC) SP-FIRSTDEF8HC 1 $28,258.001 1 EA $14,120.001 1 EA $14,138.00 PROPOSED AQUA SWIRL IN-LINE UNITS 6/19/2017 ORIGINAL OFF-LINE QUOTE DENIED DATE MATRIAL DESCRIPTION ITEM UNIT $ I UNIT UNIT $ UNIT $ DIFFERENCE 9/19/2017 AQUA SWIRL PCS IN-LINE UNITS SP-AS7BMP $21,900.00 1 EA 1 1 $14,120.00 1 EA $7,780.00 9/19/2017 AQUA SWIRL HDPE IN-LINE UNITS SP-AS7BMP $24,641.001 1EA 1 $14,120.00 1 EA $10,521.00 1/17/2018 ORIGINAL OFF-LINE PROPOSED AQUA SWIRL IN-LINE UNITS QUOTE APPROVED DATE I MATRIAL DESCRIPTION ITEM UNIT $ UNIT UNIT $ UNIT $ DIFFERENCE 1/16/20181 CONTECH CDS3035-6-C 1 $16,700.001 1 EA $14,120.001 1 EA $2,580.00 * Note - The difference in price is for 1 unit will have to multiply by 2 for total cost * Memo To: Doug Haney, Corporation Counsel From: Lisa Scott CC: Jeremy Kashman Date: 03/09/2018 Re: C.O. #1 9e and Delegates Row RAB Project #16 -ENG -33 Doug, please find attached 1 original of same change order for project #16 -ENG -33 96th & Delegates Row RAB Project. Please review & initial for the next BPW Meeting. Change Order #1 - Original Contract Amount: $1,480,798.49 Increase: $2,580.0 New Contract Amount $1,483,378.49 Thank you, Lisa Scott 0 Page 1