HomeMy WebLinkAbout323459 03/29/18 L,�,CNgyFf
CITY OF CARMEL, INDIANA VENDOR: 372119
ONE CIVIC SQUARE BRANDT CONSTRUCTION INC CHECK AMOUNT: $*****7,136.00*
CARMEL, INDIANA 46032 330 EAST ST.JOSEPH STREET CHECK NUMBER: 323459
INDIANAPOLIS IN 46202 CHECK DATE: 03/29/18
DEPARTMENT ACCOUNT PO NUMBER INVOICE NUMBER AMOUNT DESCRIPTION
902 R4460807 101054 6 7,136.00 ICE RINK CENTER GREEN
Prescribed by State Board of Accounts City Form No.201(Rev.1995)
VOUCHER NO:. WARRANT NO. .
ALLOWED 20 ACCOUNTS PAYABLE VOUCHER
Vendor#. 372119
IN' UM OF$ CITY.OF.CARMEL
BRANDT.CONSTRUCTION.INC.
330 EAST ST'. JOSEPH STREET . . . . . An invoice or bill to be properly itemized must show:kind of service,where performed,dates service
rendered;by whom,rates per day,number.of.hours,rate per hour,number of units;price per.unit,etc.
INDIANAPOLIS,.IN 46202
Payee
$7136.00
Purchase Order#
ON ACCOUNT OF:APPROPRIATION FOR '.
Terms
Redevelopment Commission
Date Due'
PO# ACCT# :DATE INVOICE#: . : DESCRIPTION:
DEPT# INVOICE# Fund#. AMOUNT Board Members DEPT:4 . FUND# (or note attached inVoice(s)or bill(s)) AMOUNT
101054 6 44-608.07. $7,136.00I hereby certify that the attached invoice(s),or 2/27/18 61 _ Pay app:§for Center Green/Ice Rink $7;136.00
902 Encumbered 902 902 902 improvements
bill(s)is(are),true and correct and that the.
e .
materials orservic s itemized:thereon for
which charge is made were ordered and
received except
.Tuesday, March 27,2018
Mestetsky, Henry.
I hereby certify that.the attached invoice(s),or-bill(s),is(are)true and correct and I have
-
audited.same.in accordance w5-11ith.IC 10.1 6
. ,20
Cost distribution ledger classification if claim paid motor vehicle highway fund.. Clerk-Treasurer
TM
1@111-AIA
Document G702 - 1992
Application and Certificate for Payment
TO OWNER: PROJECT: 17-0030 APPLICATION NOV ..6' Distribution to:
Carmel Redevelopment Commission Carmel Center Green02/27/2018
PERIOD TO:. OWNER ❑
of the City of Carmel, Indiana 3 Center Green
30 W.Main Street,Suite 220 Carmel, IN 46032 CONTRACT FOR: Carmel Center Green ARCHITECT
FRORMVIAN& VIA ARCHITECT: CONTRACT DATE: CONTRACTOR ❑
Brandt Construction Inc Rundell Ernstberger Associates 'PROJECT NOS: 1710030 / FIELD ❑
330 East St.Joseph Street 611 West Main Street,Suite 201
Indianapolis, IN 46202 Louisville, KY 40202 OTHER ❑
CONTRACTOR'S APPLICATION FOR PAYMENT The undersigned Contractor certifies that to the best of the Contractor's knowledge, information
Application is made for payment,as shown below,in connection with the Contract. and belief the Work covered by this Application for Payment has been completed in accordance
AIA Document G703TM,Continuation Sheet,is attached. with the Contract Documents, that all amounts have been paid by the Contractor for Work for
4,266,000.00 Which previous Certificates for Pay nt re issued and payments received from the Owner, and
1.ORIGINAL CONTRACT SUM............ ......... .:,...................... $ that current payment sho rein ow due.
2.NET CHANGE BY CHANGE ORDERS ..... PA
$ 164,411.00 CONTRALTO atel
3.CONTRACT SUM TO DATE(Line 1 f 2) ............................... $ 4,430,411.00 By: Date: 02/27/2018
4.TOTAL COMPLETED&STORED TO DATE(Column G on G703) ...... $ 4,311,471.00 State of: I is a slEAL
He ri ks 4 STACI WOODYARD
5.RETAINA •po County of: = `• Slate or loo Public
�v�o „"oMy Commission Expires January 04,
a. %of Completed Work Subscribed and sworn to before 2024
F&(Cohm�izs D+`E on G703) $ 431,148.00 me this ,2�] day of F&CU4--rr �l
b. %of Stored Material 0/ _• �
(Column F on G703) $ Notary Public: Staci Woodyard j°`a'
My commission expires: January 4,2024
Total Retainage(Lines 5a+5b,or Total in Column I of G703)...... $ 431,148.00
6.TOTAL EARNED LESS RETAINAGE .................................... $ 3,880,323.00 ARCHITECT'S CERTIFICATE FOR PAYMENT
(Line 4 minus Line 5 Total) In accordance with the Contract Documents,based on on-site observations and the data comprising
7.LESS PREVIOUS CERTIFICATES FOR PAYMENT ...................... $ 3,873,187.00 this application,the Architect certifies to the Owner that to the best of the Architect's knowledge,
information and belief the Work has progressed as indicated, the quality of the Work is 'in
(Line 6 from prior Certificate) accordance with the Contract Documents, and the Contractor is entitled to payment of the
8.CURRENT PAYMENT DUE ...................... .:.................... Is 7,136.00 AMOUNT CERTIFIED.
9.BALANCE TO FINISH,INCLUDING RETAINAGE AMOUNT CERTIFIED ...............................
(Line 3 minus Line 6) $ 550,088.00 (Attach explanation if amount certified d ffers fu onu the amount applied.Initial all fzgu res on this
Application and on the Continuation Sheet that are changed to conform with the amount certified.)
CHANGE ORDER SUMMARY ADDITIONS DEDUCTIONS ARC ITEC
Total changes approved in previous months by Owner $ 156,925.0 0.00A C-21 Date: �?7.
Total approved this month $ 7,486.OD$ 0.00 Tis Certificate is not negotiable.The AMOUNT CERTIFIED is payable only to the Contractor
TOTAL $ 164,411.03$ 0.00 named herein.Issuance payment and acceptance of payment are without prejudice to any rights of
NET CHANGES by Change Order $ 164,411.00 the Owner or Contractor under this Contract.
CAUTION:You should sign an original AIA Contract Document,on which this text appears in RED.An original assures that changes will not be obscured.
AIA Document G702 TM–1992.Copyright 0 1953,1963,1965,1971,1978,1983 and 1992 by The American Institute of Architects.All rights reserved.WARNING:This AIA® Document is protected by U.S.Copyright Law
and International Treaties.Unauthorized reproduction or distribution of this AIA® Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent
possible under the law.Purchasers are permitted to reproduce ten(10)copies of this document when completed.To report copyright violations of AIA Contract Documents,e-mail.The American Institute of Architects'legal
counsel,copyright@aia.org. 010711AC�4
AFFIDAVIT AND WAIVER OF LIEN
Final X Partial X_Payment to Follow
State of Indiana, County of Marion.
Chirag P. Patel, being duly sworn states he is an Authorized Representative for Brandt Construction, Inc.
having contracted with Carmel Redevelopment Commission, furnish certain materials and/or labor as
Follows: General Construction located at Carmel. IN and owned by Carmel Redevelopment
Commission and does hereby further state on behalf of Brandt Construction,Inc.
(PARTIAL WAIVER)that the balance due the contractor is the sum of
Seven Thousand One Hundred Thirty-Six and 00/100 Dollars ($ 7,136.00)
[ ] receipt of which is hereby acknowledged; or
[X] the payment of which has been promised as sole consideration for this Affidavit and Partial
Waiver of Lien which is given to and for said amount, effective upon receipt of such
payment.
(FINAL WAIVER)that the final balance due the contractor is the sum of
[ ] receipt of which is hereby acknowledged; or
[ ] the payment of which has been promised as sole consideration for this Affidavit and Final
Waiver of Lien which shall become effective upon receipt of such payment.
THEREFORE, the undersigned waives and releases unto the Owner of said premises, and all
lien or claim whatsoever on the above-described property and improvements thereon on account of labor
or material or both, furnished by the undersigned thereto, and further certifies that no other party has
claim or right to a lien on account of any w rk p o d or material furnished to the undersigned for
said project, and within the scope of t da a �a/i�v
Brandt Construction,Inc., by " V
Chirag P el,Alice President
WITNESS MY HAND AND NOTARY SEAL,this c2 7 day ofFEnita.fy , 2018
' w
Staci Woodyard
STACI SEAL
Notary Public
My commission Expires: January 4, 2024; Residing in Hendricks County State of Indiana
MY Commission Expires January 04,2024
CONTINUATION SHEET
APPLICATION NO.: 6
APPLICATION DATE: 02/27/2018
PERIOD TO: 02/27/2018
ARCHITECTS PROJECT NO:
A B C D E F G H I
WORK COMPLETED MATERIALS TOTAL BALANCE
PRESENTLY COMPLETED TO RETAINAGE
ITEM SCHEDULED FROM PREVIOUS STORED AND STORED % FINISH (IF VARIABLE
NO. DESCRIPTION OF WORK VALUE APPLICATION THIS PERIOD (NOT IN TO DATE (G/C) (C-G) RATE)
(D+E) D OR E) (D+E+F)
1 Bonds/insurance 67,939 67,939 0 0 67,939 100% (0) 6,794
2 Supervision/Management 213,077 206,685 0 0 206,685 97% 6,392 20,669
3 General Conditions 190,997 185,267 0 0 185,267 97% 5,730 18,527
4 Audio Sound Equipment Allowance 50,000 50,000 0 0 50,000 100% (0) 5,000
5 Earthwork, Site Utilities, Erosion Control, Site Demo 160,290 160,290 0 0 160,290 100% 0 16,029
6 Selective Demolition 11,405 11,405 0 0 11,405 100% 0 1,141
7 Storage of Winter Items in March 9,973 0 0 0 0 0% 9,973 0
8 Storage Containers 31,200 31,200 0 0 31,200 100% (0) 3,120
9 Dumpster Gates/Chain Link Fencing 21,239 19,115 0 0 19,115 90% 2,124 1,912
10 Temporary Wood Fencing 22,950 22,950 0 0 22,950 100% 0 2,295
11 Landscaping 82,239 65,792 0 0 65,792 80% 16,447 6,579
12 Unit Paving 846,350 829,423 0 0 829,423 98% 16,927 82,942
13 Site Furnishings-Tables, Chairs, High Tables, 31,831 31,831 0 0 31,831 100% 0 3,183
14 Site Furnishings-Tables, Chairs, High Tables, 3,356 3,356 0 0 3,356 100% 0 336
15 Site Furnishings-Temp Winter Fire Pits 20,129 20,129 0 0 20,129 100% (0) 2,013
16 Site Furnishings-Temp Winter Fire Pits Labor 2,342 2,342 0 0 2,342 100% (0) 234
17 Site Furnishings-Removeable Bollard 6,370 6,370 0 0 6,370 100% (0) 637
18 Site Furnishings-Removeable Bollard Labor 1,014 1,014 0 0 1,014 100% 0 101
19 Site Furnishings-Tree Grates,Victor Stanley 44,105 44,105 0 0 44,105 100% 0 4,411
20 Site Furnishings-Tree Grates, Victor Stanley 10,883 10,883 0 0 10,883 100% 0 1,088
21 Site Furnishings- Ramps 4,162 4,162 0 0 4,162 100% (0) 416
22 Site Furnishings- Ramps Labor 3,356 3,356 0 0 3,356 100% 0 336
23 Site Furnishings- Portable Event Fencing 4,315 4,315 0 0 4,315 100% (0) 432
24 Site Furnishings- Portable Event Fencing Labor 2,237 2,237 0 0 2,237 100% 0 224
25 Site Furnishings- Heavy Duty Stanchion with Chain 6,702 6,702 0 0 6,702 100% 0 670
26 Site Furnishings-Heavy Duty Stanchion with Chain 4,133 4,133 0 0 4,133 100% 0 413
27 Concrete 648,353 641,869 0 0 641,869 99% 6,484 64,187
28 Masonry 62,364 62,364 0 0 62,364 100% 0 6,236
29 Structural Steel Chiller and Embeds 104,628 104,628 0 0 104,628 100% 0 10,463
30 Aluminum Diamond Plate Decking/Geotextile Wrap 16,278 16,278 0 0 16,278 100% (0) 1,628
31 Rough Carpentry Material 4,853 4,853 0 0 4,853 100% 0 485
32 Rough Carpentry Labor 8,343 8,343 0 0 8,343 100% (0) 834
33 Waterproofing&Joint Sealants 15,743 15,743 0 0 15,743 100% (0) 1,574
34 Metal Coping 1,213 1,213 0 0 1,213 100%• 0 121
35 Stain Wood Fence 1,570 1,570 0 0 1,570 100% (0) 157
36 Appendix A Winter Decorations 72,715 72,715 0 0 72,715 100% (0) 7,272
CONTINUATION SHEET
APPLICATION NO.: 6
APPLICATION DATE: 02/27/2018
PERIOD TO: 02/27/2018
ARCHITECTS PROJECT NO:
A B C D E F G H I
WORK COMPLETED MATERIALS TOTAL BALANCE
PRESENTLY COMPLETED TO RETAINAGE
ITEM SCHEDULED FROM PREVIOUS STORED AND STORED % FINISH (IF VARIABLE
NO. DESCRIPTION OF WORK VALUE APPLICATION THIS PERIOD (NOT IN TO DATE (G/C) (C-G) RATE)
(D+E) D OR E) (D+E+F)
37 Temporary Ice Skating Rink 444,226 408,688 0 0 408,688 92% 35,538 40,869
38 Mechanical 728,579 714,007 0 0 714,007 98% 14,572 71,401
39 Electrical 304,541 304,541 0 0 304,541 100% 0 30,454
40 CHANGE ORDER#1 0 0
41 Replace Winter Wood Screen Fence w/PVC Lattice (28,674) (28,674) 0 0 (28,674) 100% 0 (2,867)
42 Hydroexcavation&Chiller Pad Changes 14,084 14,084 0 0 14,084 100% 0 1,408
43 Trench Conduit& Electric to Fire Pit 15,100 15,100 0 0 15,100 100% 0 1,510
44 Upsize Transformer& Panel Boards 20,577 20,577 0 0 20,577 100% 0 2,058
45 Relocate Fiber Optic Panel in Tunnel 12,447 12,447 0 0 12,447 100% 0 1,245
46 Butterfly Valves for Sump Pumps in Tunnel 11,309 11,309 0 0 11,309 100% 0 1,131
47 Revised Ice Rink Header Trench (20,824) (20,824) 0 0 (20,824) 100% 0 (2,082)
48 Revised Irrigation System 6,337 1,584 0 0 1,584 25% 4,753 158
49 Reinstall Electric Outlet for Farmers Market 849 849 0 0 849 100% 0 85
50 CHANGE ORDER#2 0 0
51 Cottage Connectors 32,714 32,714 0 0 32,714 100% 0 3,271
52 Audio Cost 33,176 33,176 0 0 33,176 100% 0 3,318
53 Water Line to Cottages 8,338 8,338 0 0 8,338 100% 0 834
54 2"to 1 1/2"Water Line (444) (444) 0 0 (444) 100% 0 (44)
55 Glycol Trench Wider and Deeper 3,968 3,968 0 0 3,968 100% 0 397
56 Relocate Alarm Panel 2,806 2,806 0 0 2,806 100% 0 281
57 Conduit for Future Wireless 1,485 1,485 0 0 1,485 100% 0 149
58 Butterfly Valve Pump 3/4 9,663 9,663 0 0 9,663 100% 0 966
59 CHANGE ORDER#3 0 0
60 Unsuitable Soil 19,370 19,370 0 0 19,370 100% 0 1,937
61 Hydrovac South Row 2,709 2,709 0 0 2,709 100% 0 271
62 Rubber Ramps 1,781 1,781 0 0 1,781 100% 0 178
63 Eliminate 2 Ramps (1,769) (1,769) 0 0 (1,769) 100% 0 (177)
64 Hydrovac/Signs/Benches 5,656 5,656 0 0 5,656 100% 0 566
65 CHANGE ORDER#4 0 0
66 Fire Pit Toggle Switches 2,709 1,683 1,026 0 2,709 100% 0 271
67 Chiller Isolator Bracket 1,875 1,875 0 0 1,875 100% 0 188
68 Hydrovac Dumpster Area 1,683 2,266 (583) 0 1,683 100% 0 168
69 CHANGE ORDER#5 0
70 Additional Audio Work 4,694 0 4,694 0 4,694 100% 0 469
71 Rubber Mats (Labor) 2,209 0 2,209 0 2,209 100% 0 221
72 Hydro Excavate Dumpster Area (correction) 583 0 583 0 583 100% 0 59
CONTINUATION SHEET
APPLICATION NO.: 6
APPLICATION DATE: 02/27/2018
PERIOD TO: 02/27/2018
ARCHITECTS PROJECT NO:
A B C D E F G H I
WORK COMPLETED MATERIALS TOTAL BALANCE
PRESENTLY COMPLETED TO RETAINAGE
ITEM SCHEDULED FROM PREVIOUS STORED AND STORED % FINISH (IF VARIABLE
NO. DESCRIPTION OF WORK VALUE APPLICATION THIS PERIOD (NOT IN TO DATE (G/C) (C-G) RATE)
(D+E) DOR E) (D+E+F)
73
74
4,430,411 4,303,542 7,929 0 4,311,471 97% 118,940 431,148