HomeMy WebLinkAboutRieth-Riley Construction Co, Inc/Eng/CO #5/61,754.48/Rangeline Road and 4th Street RAB - Project #16-ENG-31r City of Carmel Project 16 -ENG -31 Range Line Road and 4t" St. RAB CHANGE ORDER #5 Change order represents inefficiencies caused by delays in ROW acquisition, added paver inlay for raised pedestrian crossing and additional archway electrical items for the Range Line and 4th Street SW RAB. Contract Price prior to this Change Order $7,643,740.63 Contract Price will be increased by this Change Order $61,754.48 New Contract Price including this Change Order $7,705,495.11 PO # PO -100472 PO -100473 PO -100473 Adjusted Contract Price Project Veterans Way RL & 4th RAB 4th SW West of Monon Original $2,797,315.57 $654,132.69 $501,298.89 $5,378,409.93 Contract Change Order 1 $1,605,251.69 $6,983,661.62 Change Order 2 $51,521.68 $7,035,183.30 Change Order 3 $52,244.51 $7,087,427.81 Change Order 4 $556,312.82 $7,643,740.63 Change Order 5 $61,754.48 $7,705,495.11 Adjusted Amount $5,010,401.76 $768,131.68 $501,298.89 $7,705,495.11 TO: Rieth Riley Construction Co. Inc. 1751 West Minnesota Street Indianapolis. IN 46221 CITY OF CARMEL CONTRACT CHANGE ORDER NO 3/8/2018 PROJECT NAME: 16 -ENG -31 CITY REQ. NO.: CITY PO NO.: 100473 CITY PO DATE. 6/1/2017 I. You arc directed to make the following changes in this Contract: 5 Odd additional items items due to modifications in the field and requests from Carmel Utility Departments, SCHEDULED ADJUSTMENT ITEMMA OUNT (+) OR (-) DAYS ' See detail of items and summary of changed costs in attached Table TOTAL OF CHANGE ORDER ITEMS $61,754.48 0 Days ....... ..... . 1I. The following referenced Documents further describe the changes outlined in Paragraph 1. and are to be considered a part of this Change Order: R.F.P.: _nil—W.D.C. NO.: n/a Other: _ By Request from the Citi of Carmel rer rrorosals included herein vROy� d OCtI The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $7.643.740.63 Contract Price will be increased by this Change Order 10_754.48 New Contract Price including this Change Order 57.705.495.11 Contract Time prior to this Change Order 150 Days October 12017 Completion Date Net increased resulting from this Change Order 0 Days Current Contract Time including this Change Order October 12017 Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are Recommended The Above Changes Are Accepted Approved CROSSROAD ENGINEERS ENGINEER 3417 Sherman Drive Address Beech Grove, IN 46107�� City/State/Zip By: Ali Phone: 317/-,7790--1555 Date:�.L 7/V Rieth-Riley Construction Co. Inc. CONTRACTOR 1751 West Minnesota Street Address Indian lis IN 4§221 f James Brainard,,Mayor 16 -ENG -314th and Range Line RAB CHANGE ORDER MI TABLE Item N0. Description Unit Usk Price Origiul Orkinal Qaaathy Amount �� Qaaatlty Fuel Aasaet OverJUtler 159 Ranee Line RAS T&M Tickets M2 LS IS 9,353.73 o S 1 S 9,353.73 , S 9,353.73 153 Paver Inlav for Raised Pedestrian Crossing SYD 1 S 215.00 0 $ 146.05 S 31,400.73 S 31,400.75 160 Rami Line RAS Arch%vnc Addiliorml Cost LS S 21.000.00 0 S 1 3 21,000.00 S 21.000.00 TOTAL OF CHANGE ORDER rmls Is 61,73A48 ORIGINAL CONTRACT PRICE S 7,643,740.63 FINAL CHANGE ORDER 41 S 61,754.48 NEW CONTRACT AMOUNT INCLUDING APPROVED CHANGE ORDERS S 7,705A95.11 95.11 16 -ENC -31 4TH AND RANGE LINE RAB EXHIBIT A have been directed to make the following changes in this Contract. Na Description Reason For Change ? T&M tickets for inneficiencies due to construction phasing and added work at Miller 159 Range Line RAB T&M Tickets 42 Auto Parking Lot. Mobilization of archway. Added conduits, handholes, electrical boxes. and cameras per Carmel Communications. 153 PPaver Inlav for Raised Pedestrian Crossing Additional cost due raised •destrian crossings being added to the project, 160! Range Line RAB Archway Additional Cost Mobilization ofarchway. Added conduits, bandholes, electrical boxes, and cameras rcr Carmel Communications.