HomeMy WebLinkAboutRieth-Riley Construction Co, Inc/Eng/CO #5/28,938.48/Rangeline Road & City Center RAB - Project #16-ENG-50CITY OF CARMEL TO: CONTRACT CHANGE ORDER NO.: 05 �4ROt� Rieth-Riley, Inc. DATE: February 20, 2018 1751 W. Minnesota St. PROJECT NAME: Range Line/City Center Roundabout Indianapolis, IN 46221 CITY REQ. NO.: 16 -ENG -50 CITY PO NO.: 100273: 2016 COIT Bond CITY PO DATE: March 15, 2017 I. You are directed to make the following changes in this Contract: FINAL Change Order to close out the contract. SCHEDULED ADJUSTMENT ITEM AMOUNT H OR (-) DAYS FINAL CO - Final Quantities $28,938.48 (0) II. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: R.F.P.: N/A W.D.C. No.: N/A Other: The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $J1,785,111.13 Contract Price will be increased/decreased by this Change Order $_ 28,938.48 New Contract Price including this Change Order $_1,814,049.61 Contract Time Prior to this Change Order July 15, 2017 Open to Traffic Net increased/decreased resulting from this Change Order 0 Days Current Contract Time including this Change Order July 15, 2017` Open to Traffic This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are The Above Changes Are Recommended Accepted: American Structurepoint, Inc. Rieth-Riley, Inc. ENGINEER CONTRACTOR ,*J260 Shadeland Station Address Indianapolis, IN 46256 City/State/Zip By: �,& �sl Phone: 317-547-5580 1751 W. Minnesota St. Indianapolis,Address I Phone: 317-634-5561 Approved: Je ash an, Ci Christine S. Pauley, Clerk- Treasurer '/b/ Date: Lz1 -1 $ Date: l Date: CHANGE ORDER SUMMARY SHEET Project No.: 16 -ENG -50 Project Name: Range Line and City Center Dr Roundabout Contractor: Rieth-Riley Contractors RPR: Caleb Edwards, CPII - American Structurepoint Bid Date: March 15, 2017 Bid Amount: $1,516,487.52 Original PO#: 100273, 2016 COIT Bond C.O. # Total Total Foreseen Unforeseen Amount Amount Total Change Order Amount Running s Orders Change Orders Description of Change Order Date Board Approval Intermediate Calendar Days +/- Substantial Calendar Days +/- Final Calendar Days New Contract Amount Foreseen Unforeseen 1 $69,419.74 $69,419.74 $69,419.74 Time Extension and Design Changes 05/16/17 0 14 14 $1,585,907.26 4.58% 0.00% 2 $126,448.87 $126,448.87 $195,868.61 Item Balances and Claims 02/07/18 0 0 0 $1,712,356.13 8.34% 0.00% 3 $7,755.00 $7,755.00 $203,623.61 Carmel Communications Request 02/07/18 0 0 0 $1,720,111.13 0.51% 0.00% 4 $65,000.00 $65,000.00 $268,623.61 116th and Hazel Dell Ditch grading per Cit 02/07/18 0 0 0 $1,785,111.13 4.29%1 0.00% 5 $28,938.48 $28,938.48 $297,562.09 FINAL CO $1,814,049.61 1.91% 0.00% $297,562.09 $0.00 $297,562.09 $297,562.09 0 14 14 19.62% 0.00% Original Bid Amount $1,516,487.52 Total Change Orders Amount $297,562.09 Total Foreseen Change Orders 19.62% Total Unforeseen Change Orders 0.00% Total %Change from Bid Amount 19.62% rev 4/11/2016 ■ STRUCTUREPOINT American Structurepoint, Inc. Change Order Details Rangeline and City Center Way Roundabout Description: Converting the existing signalized four-way intersection at Rangeline Road and City Center Drive to a multi -lane roundabout. Change Order: 6 Date Created: 02/09/2018 Status: Draft Date Approved: Type: Summary: FINAL Change Order #5 Change Order Description: FINAL Change Order for project quantities with final waivers accepted. Awarded Project Amount: $1,516,487.52 Authorized Project Amount: $1,785,111.13 Change Order Amount: $28,938.48 Revised Project Amount: $1,814,049.61 Increases/Decreases Line Number Item Unit Unit Price Current Change Revised Quantity Amount Quantity Amount Quantity Amount Section: 01 - Default 10 10 SYS $16.740 374.00 $6,260.76 4.00 $66.96 378.00 $6,327.72 SUBGRADE TREATMENT, TYPE II 18 18 SYS $2.970 4,415.00 $13,112.55 -10.00 -$29.70 4,405.00 $13,082.85 ASPHALT SURFACE MILLING, 1-1/2 IN 20 20 TON $73.750 HMA INTERMEDIATE, TYPE C, 19.0 MM Reason: Balancing Change Order 24 24 TON $97.830 HMA INTERMEDIATE, TYPE B Reason: Balancing Change Order 25 25 TON $85.460 HMA WEDGE AND LEVEL, TYPE C Reason: Balancing Change Order 29 29 SYS $148.740 CENTER CURB, D, CONCRETE Reason: Balancing Change Order 596.11 $43,963.11 0.83 $61.22 596.94 $44,024.33 178.00 $17,413.74 1.97 $192.73 179.97 $17,606.47 160.30 $13,699.24 19.02 $1,625.45 179.32 $15,324.69 5.33 $792.78 0.67 $99.66 6.00 $892.44 Change Order Details: Rangeline and City Center Page 1 of 2 02/20/2018 Way Roundabout Line Number Item Unit Unit Price Current Change Revised Quantity Amount Quantity Amount Quantity Amount 32 32 LFT $21.930 2,764.00 $60,614.52 396.10 $8,686.47 3,160.10 $69,300.99 STRAIGHT CONCRETE CURB Reason: Balancing Change Order 35 35 SYS $81.840 342.17 $28,003.19 PCCP FOR APPROACHES, 8 IN Reason: Balancing Change Order 25.01 $2,046.82 367.18 $30,050.01 45 45 SYS $3.500 3,583.50 $12,542.25 -100.00 -$350.00 3,483.50 $12,192.25 SODDING Reason: Balancing Change Order 50 50 CYS $41.600 99.94 $4,157.50 AGGREGATE FOR UNDERDRAINS Reason: Balancing Change Order 58 58 EA $200.000 8.00 $1,600.00 ROAD CLOSURE SIGN ASSEMBLY 59 59 EA $70.000 104.00 $7,280.00 DETOUR ROUTE MARKER ASSEMBLY 60 60 EA $150.000 25.00 $3,750.00 CONSTRUCTION SIGN, A 61 61 EA $50.000 9.00 $450.00 CONSTRUCTION SIGN, B 62 62 EA $150.000 7.00 $1,050.00 CONSTRUCTION LANE RESTRICTION LANE SIGNS 71 71 EA $1,100.000 7.00 $7,700.00 HANDHOLE 72 72 LFT $11.000 818.00 $8,998.00 CONDUIT, 1 -IN IN TRENCH WITH WIRING 79 79 LFT $14.000 1,366.00 $19,124.00 PVC SCHEDULE 40 - 4" INTERDUCT 92 92 EA $750.000 2.00 $1,500.00 SNOWPLOWABLE RAISED PAVEMENT MARKING (BLUE) 0109 604-07823 SYS $97.200 502.00 $48,794.40 STAMPED CONCRETE SIDEWALK Reason: Balancing Change Order 114* 805-01844 LFT $15.400 250.00 $3,850.00 CONDUIT, STEEL, GALVANIZED, 2 IN Reason: Balancing Change Order (21 Items) Totals $304,656.04 Change Order Details: Rangeline and City Center Page 2 of 2 Way Roundabout 35.85 $1,491.36 135.79 $5,648.86 -1.00 -$200.00 7.00 $1,400.00 -7.00 -$490.00 97.00 $6,790.00 2.00 $300.00 27.00 $4,050.00 1.00 $50.00 10.00 $500.00 3.00 $450.00 10.00 $1,500.00 5.00 $5,500.00 12.00 $13,200.00 332.00 $3,652.00 1,150.00 $12,650.00 60.00 $840.00 1,426.00 $19,964.00 1.00 $750.00 3.00 $2,250.00 32.39 $3,148.31 534.39 $51,942.71 68.00 $1,047.20 318.00 $4,897.20 $28,938.48 $333,594.52 02/20/2018 Memo To: Doug Haney, Corporation Counsel From: Lisa Scott CC: Jeremy Kashman Date: 03/26/18 Re: C.O. #5 Range Line & City Center RAB Project #16 -ENG -50 Doug, please find attached 1 original of same change order for project #16 -ENG -50 Range Line & City Center RAB Project #16 -ENG -50. Please review & initial for the next BPW Meeting. Change Order #5- Original Contract Amount: $1,516,487.42 Increase: $28,938.48 New Contract Amount $1814,049.61 Thank you, Lisa Scott • Page 1