HomeMy WebLinkAboutSPP - Kirsh Plot PLan 3R.L.S. # LS20500017 DATE:
FOR: OLD TOWN DESIGN GROUP
BY: JD HALL LAND SURVEYING
803 S. OHIO STREET
SHERIDAN, INDIANA 46069
Ph: 317-696-3594
Fx: 317-758-5510
JOB NO: 18-005 SHEET 3 OF 3
SITE PLAN
NOTE:
Erosion and sediment plan, for this lot, shall, at a minimum, includes the following measures and at all times follow the
guidelines for Individual residential lots and the previously approved SWPPP for CARMEL, INDIANA:
1) Install and maintain a stable construction site access at the location of the proposed drive.
2) Install and maintain an appropriate perimeter erosion and sediment control measures prior to land disturbance, ie silt
fence.
3) Minimize sediment discharge and tracking from the lot.
4) Clean-up sediment that is either tracked or washed onto roads. Bulk clearing of sediment shall not include flushing
the area with water. Cleared sediment must be redistributed or disposed of in a manner that is in compliance with all
applicable statutes and rules.
5) Adjacent lots disturbed by an individual lot operator must be repaired and stabilized with temporary or permanent
surface stabilization.
6) Self-monitoring program plan and procedures per the previous approved SWPPP shall be followed all individual lot
construction.
7) Additional erosion/sediment control measures may be required upon inspection by local planning authority.
THEN 2T/AC MULCH WILL BE USED TO ENSURE GROUND STABILIZATION REQUIREMENTS ARE MET.
STABILIZATION APPLIED. WHEN WEATHER CONDITIONS PREVENT RAPID GERMINATION OF GRASS,
RULE 5 REQUIRES ALL DISTURBED AREAS LIKELY TO BE IDLER FOR 15 DAYS SHALL HAVE SURFACE
THE SOIL 2-4 INCHES DEEP WITH A DISK OR A RAKE OPERATED ACROSS THE SLOPE.
4. TILL TOP SOIL TO OBTAIN A UNIFORM SEEDBED, WORKING THE FERTILIZER AND LINE INTO
APPLYING 400-600 lbs/ACRE OF 12-12-12 ANALYSIS, OR EQUIVALENT, FERTILIZER.
3. FERTILIZE AS RECOMMENDED BY THE SOIL TEST. IF TESTING WAS NOT DONE, CONSIDER
TO TEST RECOMMENDATIONS.
2. IF SOIL pH IS UNSUITABLE FOR THE SPECIES TO BE SEEDED, APPLY LIME ACCORDING
SOILS INFORMATION, INCLUDING AVAILABLE TESTING SERVICES.)
(CONTACT COUNTY SWCD OR COOPERATIVE EXTENSION OFFICE FOR ASSISTANCE AND
1.TEST SOIL TO DETERMINE pH AND NUTRIENT LEVELS.
SEEDBED PREPARATION FOR PERMANENT SEEDING:
MAINTENANCE:
INSPECT THE SILT FENCE PERIODICALLY AND AFTER EACH STORM EVENT. IF FENCE
FABRIC TEARS. STARTS TO DECOMPOSE, OR IN ANY WAY BECOMES INEFFECTIVE,
REPLACE THE AFFECTED PORTION IMMEDIATELY. REMOVE DEPOSITED SEDIMENT WHEN
IT REACHES HALF THE HEIGHT OF THE FENCE AT ITS LOWEST POINT OR IS CAUSING THE
FABRIC TO BULGE. TAKE CARE TO AVOID UNDERMINING THE FENCE DURING CLEANOUT.
AFTER THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZED REMOVE THE FENCE
AND SEDIMENT DEPOSITS, BRING THE DISTURBED AREA TO GRADE, AND STABILIZE.
LOT 6 CARMELWOOD
CARMEL, INDIANA
135 AUDUBON DRIVE