HomeMy WebLinkAbout31 62 50 - Aggregate PiersMidtown West 17070
Carmel, Indiana September 15, 2017
31 62 50 - 1
SECTION 31 62 50 – AGGREGATE PIERS
PART 1 - GENERAL
1.1 DESCRIPTION: Work shall consist of designing, furnishing and installing materials, and
constructing a ground improvement system at the locations noted on the drawings and as
specified herein. Ground improvement system shall be either vibro stone columns or rammed
piers. “Aggregate piers” referenced in these specifications refer to both vibro stone columns and
rammed piers.
1.2 WORK INCLUDED:
A. Provision of all equipment, material, labor, and supervision to design and install
aggregate pier elements. Design shall rely on subsurface information presented in the
project geotechnical report. Removal of spoils from the site (which result from aggregate
pier construction), removal of spoils off the working pad, footing excavation, and
subgrade preparation following aggregate pier installation is not included.
B. Drawings and General Provisions of the Contract, including General and Supplemental
Conditions, and Division 1 Specifications, apply to the work in this specification.
1.3 APPROVED INSTALLERS:
A. Installers of aggregate pier foundation systems shall have a minimum of 5 years of
experience with the installation of aggregate piers and shall have completed at least 100
projects.
1.4 RELATED WORK:
A. Section 03 30 00 – Cast-in-Place Concrete.
B. Section 31 20 00 – Earth Moving - Building.
C. Geotechnical Report and Recommendations.
1.5 REFERENCE STANDARDS:
A. Design: The ground improvement installer shall be responsible for design of a vibro stone
column or rammed pier ground improvement system that meets the global stability,
allowable bearing capacity, and settlement requirements stated on the contract plans.
Industry recognized standards or design methods specific to the installer‟s equipment
and construction methods shall be used.
B. Modulus and Uplift Testing:
1. ASTM D-1143 – Pile Load Test Procedures.
2. ASTM D-1194 – Spread Footing Load Test.
C. Materials and Inspection:
1. ASTM D-1241 – Aggregate Quality.
2. ASTM STP 399 – Dynamic Penetrometer Testing.
3. ASTM D-422 – Gradation Soils.
1.6 CONFLICTS IN SPECIFICATIONS/REFERENCES: Where specifications and reference
documents conflict, the Architect/Engineer shall make the final determination of the applicable
document.
Midtown West 17070
Carmel, Indiana September 15, 2017
31 62 50 - 2
1.7 CERTIFICATIONS AND SUBMITTALS:
A. The installer shall submit detailed design calculations and construction drawings to the
Architect and to the Engineer of Record for approval at least three (3) weeks prior to the
start of construction. All plans shall be sealed by a Professional Engineer in the State in
which the project is constructed (referred in this specification as “the Designer”).
B. The Stone Column or Aggregate Pier engineer shall have Errors and Omissions design
insurance for the work. The insurance policy should provide a minimum coverage of $2
million per occurrence.
C. Modulus and uplift test data - The Installer shall furnish the General Contractor a
description of the installation equipment, installation records, complete test data, analysis
of the test data and recommended design parameter values based on the modulus test
results. The report shall be prepared under supervision of a registered professional
engineer.
D. Daily Progress Reports – The Installer shall furnish a complete and accurate record of
aggregate pier installation to the General Contractor. The record shall indicate the pier
location, length, average lift thickness and final elevations of the base and top of piers.
The record shall also indicate the type and size of the densification equipment used. The
Installer shall immediately report any unusual conditions encountered during installation
to the General Contractor, to the Designer and to the Testing Agency.
1.9 BASIS OF PAYMENT:
A. This work will be paid for at the contract lump sum price for AGGREGATE PIERS.
PART 2 - PRODUCTS
2.1 MATERIALS:
A. Aggregate used for piers constructed above the water table shall be Type I Grade B in
accordance with ASTM D-1241, or shall be other graded aggregate selected by the
Installer and successfully used in the modulus test. It shall be compacted to a
densification and strength, which provides resistance to the dynamic penetration test
(ASTM STP 399) of a minimum average of 15 blows per 1.75-inch vertical movement.
B. For aggregate used for piers constructed below the water table, the gradation shall be the
same as Type I Gradation B, except that particles passing the No. 40 sieve shall be
eliminated. Alternatively, No.57 stone or other stone selected by the Stone Columns or
Aggregate Pier Installer may be used. Dynamic penetration resistance testing is
inappropriate for this material.
C. Potable water or other suitable source shall be used to increase aggregate moisture
content where required. Access to water on site shall be provided to the Installer.
D. Installer to coordinate adequate and suitable marshalling areas on the project site for the
use of the Installer for the storage of aggregate and equipment.
PART 3 - DESIGN REQUIREMENTS
3.1 STONE COLUMN AND AGGREGATE PIER DESIGN:
Midtown West 17070
Carmel, Indiana September 15, 2017
31 62 50 - 3
A. The Aggregate Pier design stiffness modulus value shall be verified by the results of the
modulus test, described in this specification.
B. Stone Columns or Aggregate piers shall be designed in accordance with generally-
accepted engineering practice and the methods described in Section 1 of these
Specifications. The design shall meet the following criteria.
1. Minimum Allowable Bearing Pressure for Aggregate Pier Reinforced Soils: 4,500
psf.
2. Estimated Total Long-Term Settlement for Footings: ≤1-inch.
3. Estimated Long-Term Differential Settlement of Adjacent Footings: ≤ ½-inch.
4. The bearing pressure settlement criteria is to explicitly include stress interactions
between all adjacent foundations. Aggregate pier scopes of work used for
bidding must include the effect of stress overlap on building footing settlement
calculations. No changes to the contract cost for ground improvement will be
allowed for additional aggregate pier lengths or quantities required during the
final Aggregate Pier design or after structural review of the aggregate pier
submittal.
5. Aggregate piers must be designed and constructed to a depth sufficient to satisy
the above settlement criteria over the life of the structure. An aggregate pier
modulus test must be performed to verify the parameter values selected for the
aggregate pier design.
C. The design submitted by the Installer shall consider the bearing capacity and settlement
of all footings supported by aggregate piers, and shall be in accordance with acceptable
engineering practice and these specifications. Total and differential settlement shall be
considered. The design life of the structure shall be 50 years.
D. The Stone Column or Aggregate Pier system shall be designed to preclude plastic
bulging deformations at the top-of–pier design stress and to preclude significant tip
stresses as determined from the shape of the telltale test curve from telltales installed in
modulus test piers. The results of the modulus test shall be used to verify the design
assumptions.
3.2 DESIGN SUBMITTAL: The Installer shall submit four (4) sets of detailed design calculations,
construction drawings, and shop drawings, (the Design Submittal), for approval at least three (3)
weeks prior to the beginning of construction. A detailed explanation of the design parameters for
settlement calculations shall be included in the Design Submittal. Additionally, the quality control
test program for stone columns or aggregate piers, meeting these design requirements, shall be
submitted. All computer-generated calculations and drawings shall be prepared and sealed by a
Professional Engineer, licensed in the State or Province where the piers are to be built.
PART 4 - CONSTRUCTION
4.1 STONE COLUMNS:
A. Install stone columns with a down-hole vibrator capable of densifying the aggregate by
forcing it radially into the surrounding soil. The vibrator shall be of sufficient size and
capacity to construct stone columns to the diameters and lengths shown on the installer‟s
approved construction drawings.
B. The probe and follower tubes shall be of sufficient length to reach the elevations shown
on the installer‟s approved construction drawings. The probe, used in combination with
the available pressure to the tip jet, shall be capable of penetration to the required tip
elevation. Preboring shall be permitted if it is specified in the installer‟s approved
Midtown West 17070
Carmel, Indiana September 15, 2017
31 62 50 - 4
construction procedure submittal.
C. The probe and follower shall have visible markings at regular increments to enable
measurement of penetration and repenetration depths.
D. Provide methods for supplying to the tip of the probe a sufficient quality of air or water to
widen the probe hole to allow adequate space for stone backfill placement around the
probe.
E. The probe shall penetrate into the foundation soil layer to the minimum depths required in
the installer‟s construction plans.
F. Lift thickness shall not exceed 4 feet. After penetration to the treatment depth, slowly
retrieve the vibrator in 12-inch to 18-inch increments to allow backfill placement.
G. Compact the backfill in each lift by repenetrating it at least twice with the vibrating probe
to densify and force the stone into the surrounding soil.
H. Install stone columns so that each completed column is continuous throughout its length.
4.2 RAMMED PIERS:
A. All Aggregate Pier elements shall be pre-augered using mechanical drilling or excavation
equipment. Installation of piers without pre-augering shall not be allowed because this
technique results in significant disturbance and remolding of the matrix soils surrounding
the piers.
B. If cave-ins occur during excavation such that the sidewalls of the hole are deemed to be
unstable, steel casing or a drilling slurry shall be used to stabilize the excavation.
C. If cave-ins occur on top of a lift of aggregate such that the volume of the caved soils is
greater than 10 percent of the volume of the aggregate in the lift, then the aggregate shall
be considered contaminated and shall be removed and replaced with uncontaminated
aggregate.
D. Special high-energy impact densification apparatus shall be employed to densify the
Aggregate Pier elements during installation. The apparatus shall apply direct downward
impact energy to each lift of aggregate.
E. A minimum tamper energy level of 250,000 foot-pounds of force per minute shall be
applied by the energy source.
F. The bottom of the excavation shall be densified prior to the placement of the aggregate.
If wet, soft or sensitive soils are present, open-graded aggregate, such as ASTM No.57
stone or other, shall be placed at the bottom of the excavation and compacted to stabilize
the element bottom and may serve as the initial lift.
G. Densification shall be performed using a beveled tamper. The beveled tamper foot is
required to adequately increase the lateral earth pressure in the matrix soil during
installation.
H. Downward pressure shall be applied to the tamper shaft during tamping.
I. Each lift of aggregate shall be tamped for a minimum of 15 seconds.
4.3 PLAN LOCATION AND ELEVATION OF AGGREGATE PIER ELEMENTS: The center of each
pier shall be within six inches of the plan locations indicated. The final measurement of the top of
Midtown West 17070
Carmel, Indiana September 15, 2017
31 62 50 - 5
piers shall be the lowest point on the aggregate in the last compacted lift. Piers installed outside
of the above tolerances and deemed not acceptable shall be rebuilt at no additional expense to
the Owner.
4.4 REJECTED AGGREGATE PIER ELEMENTS: Aggregate pier elements improperly located or
installed beyond the maximum allowable tolerances shall be abandoned and replaced with new
piers, unless the Designer approves other remedial measures. All material and labor required to
replace rejected piers shall be provided at no additional cost to the Owner.
PART 5 - QUALITY CONTROL
5.1 QUALITY CONTROL REPRESENTATIVE:
A. The Installer shall have a full-time Quality Control (QC) representative to verify and report
all QC installation procedures. The Installer shall immediately report any unusual
conditions encountered during installation to the Design Engineer, the General
Contractor, and to the Testing Agency. The QC procedures shall include the preparation
of Aggregate Pier Progress Reports completed during each day of installation and
containing the following information:
1. Footing and Aggregate Pier location.
2. Aggregate Pier length and drilled diameter.
3. Planned and actual Aggregate Pier elevations at the top and bottom of the
element.
4. Average lift thickness for each Aggregate Pier.
5. Soil types encountered at the bottom of the Aggregate Pier and along the length
of the element.
6. Depth to groundwater, if encountered.
7. Documentation of any unusual conditions encountered.
8. Type and size of densification equipment used.
5.2 QUALITY CONTROL VERIFICATION PROGRAM:
A. The installer shall be responsible for design of a verification program to assure the quality
of the construction. The program shall verify that the installed ground improvement
system satisfies the performance requirements noted on the contract plans and the
design requirements determined by the ground improvement system designer. As a
minimum, the verification program shall include the following:
1. Program to monitor performance of the ground improvement system during and
after construction of the proposed structure or embankment to be supported.
This program may include installation of settlement plates, monitoring points,
inclinometers, piezometers, or other instrumentation.
2. Stone column installation shall be monitored by an on board computer monitoring
system. Monitoring system shall log stone column number, time of installation,
depth, hydraulic pressure applied during the boring process and during the
compacting process. Recorded data for each stone column shall be plotted
depth/pressure versus time. Installation records for each shall be made available
upon request in electronic format within 24 hours of installation.
3. Proposed means and methods for verification that the installed aggregate piers
meet the strength and/or stiffness criteria required by the design. This may
include, but shall not be limited to, modulus or load tests on individual elements
and/or groups, soil borings, and other methods as approved by the Engineer.
Midtown West 17070
Carmel, Indiana September 15, 2017
31 62 50 - 6
4. Quality control program to verify that the ground improvement system is installed
in accordance with the designer‟s specifications and the requirements in this
special provision. The quality control program shall include testing and
observations by qualified personnel employed by the ground improvement
installer or an independent testing laboratory.
PART 6 - QUALITY ASSURANCE
6.1 INDEPENDENT ENGINEERING TESTING AGENCY: The Owner or General Contractor is
responsible for retaining an independent engineering testing firm to provide Quality Assurance
services. The Testing Agency should be the Geotechnical Engineer of Record.
6.2 RESPONSIBILITIES OF ENGINEER of RECORD & INDEPENDENT ENGINEERING TESTING
AGENCY:
A. The Engineer of Record shall review and approve the Installer‟s Design Submittal.
B. The Testing Agency shall monitor the installation of aggregate pier elements to verify that
all work is performed in accordance with the approved Design Submittal.
C. The Testing Agency shall observe footing excavations and densification of aggregate
piers and provide written reports per section 7.3.D.
D. The Testing Agency shall report any discrepancies to the Installer and General
Contractor immediately.
PART 7 - RESPONSIBILITIES OF GENERAL CONTRACTOR
7.1 PREPARATION:
A. The Installer shall locate and protect underground and aboveground utilities and other
structures from damage during installation of the Aggregate Pier elements.
B. The General Contractor will provide the site to the Installer, after earthwork in the area
has been completed.
C. Site subgrade shall be established by the General Contractor within 6 inches of final
design subgrade, as approved by the Design Engineer.
7.2 UTILITY EXCAVATIONS:
A. The General Contractor shall coordinate all excavations made subsequent to Aggregate
Pier installations so that at least five feet of horizontal distance remains between the
edge of any installed Aggregate Pier and the excavation. In the event that utility
excavations are required at horizontal distances of less than five feet from installed
Aggregate Piers, the General Contractor shall notify the Aggregate Pier Designer to
develop construction solutions to minimize impacts on the installed Aggregate Piers.
B. Recommended procedures may include:
1. Using cement-treated base to construct portions of the Aggregate Piers subject
to future excavations.
2. Replacing excavated soil with compacted crushed stone in the portions of
excavations where the Aggregate Piers have been disturbed. The placement
and compaction of the crushed stone shall meet the following requirements.
Midtown West 17070
Carmel, Indiana September 15, 2017
31 62 50 - 7
a. The crushed stone shall meet the gradation specified by the Designer.
b. The crushed stone shall be placed in a controlled manner using
motorized impact compaction equipment.
c. The aggregate should be compacted to 95% of the maximum dry density
as determined by the Modified Proctor method (ASTM D-1557).
d. The Testing Agency shall be on site to observe placement, compaction,
and provide density testing. The test results shall be submitted to the
Designer and the General Contractor. The subcontractor shall provide
notification to the Testing Agency and the Designer when excavation,
placement, and compaction will occur and arrange for construction
observation and testing.
7.3 FOOTING BOTTOMS:
A. Excavation and surface compaction of all footings shall be the responsibility of the
General Contractor.
B. Foundation excavations to expose the tops of Aggregate Pier elements shall be made in
a workmanlike manner, and shall be protected until concrete placement, with procedures
and equipment best suited to (1) prevent softening of the matrix soil between and around
the Aggregate Pier elements before pouring structural concrete, and (2) achieving direct
and firm contact between the dense, undisturbed Aggregate Pier elements and the
concrete footing.
C. Recommended procedures for achieving these goals are to:
1. Limit over-excavation below the bottom of the footing to 3-inches (including
disturbance from the teeth of the excavation equipment,
2. Compaction of surface soil and top of Aggregate Pier elements shall be prepared
using a motorized impact compactor (“Wacker Packer,” “Jumping Jack,” or
similar). Sled-type tamping devices shall not be used. Compaction shall be
performed over the entire footing bottom to compact any loose surface soil and
loose surface pier aggregate.
3. Place footing concrete immediately after footing excavation is made and
approved, preferably the same day as the excavation. Footing concrete must be
placed on the same day if the footing is bearing on expansive or sensitive soils.
4. If same day placement of footing concrete is not possible, place a minimum 3-
inch thick lean concrete seal („mud mat”) immediately after the footing is
excavated and approved.
D. The following criteria shall apply, and a written inspection report sealed by the project
Geotechnical Engineer shall be furnished to the Installer to confirm:
1. That water (which may soften the unconfined matrix soil between and around the
Aggregate Pier elements, and may have detrimental effects on the supporting
capability of the Aggregate Pier reinforced subgrade) has not been allowed to
pond in the footing excavation at any time.
2. That all Aggregate Pier elements designed for each footing have been exposed
in the footing excavation.
3. That immediately before footing construction, the tops of all the Aggregate Pier
elements exposed in each footing excavation have been inspected and
recompacted as necessary with mechanical compaction equipment, and that the
tops of any Aggregate Pier elements which may have been disturbed by footing
excavation and related activity have been recompacted to a dry density
equivalent to at least 95% of the maximum dry density obtainable by the Modified
Proctor method (ASTM D-1557).
Midtown West 17070
Carmel, Indiana September 15, 2017
31 62 50 - 8
4. That no excavations or drilled shafts have been made after installation of
Aggregate Pier elements within horizontal distance of five feet from the edge of
any pier, without the written approval of the Installer or Designer.
END OF SECTION 31 62 50