HomeMy WebLinkAboutP-103-PLUMBING-THIRD-FLOOR-PLAN-Rev.2UP
UP
story wall
MAHC 1 MAHC 3
MAHC 2 MAHC 4
IT 8 IT 10
IT 9 IT 11
HR 1 HR 2 HR4 3 HR
ACCT 1 ACCT 3
ACCT 2 ACCT 4
ACCT 5 ACCT 7
ACCT 6 ACCT 8
IT 1
IT 2
IT 3
IT 4
IT 5
IT 6
IT 7
IT 8
IT 12
IT 13
IT 14
IT 15
V V V V
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
C.5
8.6
GA.3
GA
OFFICE
331
OFFICE
330
OFFICE
329
INTERVIEW
328
MEETING
327
CONFERENCE
325
OFFICE
322
OFFICE
321
AUDIT
320
MEETING
319
PATIO
318
OFFICE
332
IT OFFICE
333
OFFICE
334
OPEN OFFICE
335
COFFEE HUB
341
WAR ROOM
340
MARKETING
339
IT
338
STAIR 1
S1
OPEN OFFICE
342
OFFICE
343
OFFICE
344
OFFICE
345
OFFICE
346
OFFICE
347
OFFICE
348
CONFERENCE
352
TRAINING
353a
TRAINING
353b
TABLES
354
SOCIAL HUB
356
LOUNGE
315
STAIR 2
S2
LOUNGE
314
OPEN OFFICE
324
WAR ROOM
323
GATHER
326
MEN
304
WOMEN
303
JAN
308
HALLWAY
309
LOBBY
302
CORRIDOR
355
GATHER
317
LOCKER 4
313
LOCKER 3
312
LOCKER 2
311
LOCKER 1
310
RECEPTION
301
OPEN OFFICE
336
IT
306
ELEC
307
SERVICE
305
BREAKOUT
351
STAGING
337
OPEN OFFICE
349
WC-1 WC-1 WC-1
WC-2
FD-1
L-1
L-1
FD-1
FD-1
UR-1 UR-2
WC-2
L-1
L-1
EWC-1
MB-1 FD-1 FD-1 FD-1
FD-1
FD-1
SK-2 IB-1
L-1
L-1
EWH-2
WC-1
WC-2
L-1
L-1
WC-1 WC-1
FD-1
FD-1
P-1
ET-1
AD-1
FD-2
SK-1
IB-1
FD-1
FD-1
1-1/2"V.
3/4" HWR
3/4"CW
3/4"HW
2"CW
1"HW
2"CW
1"HW
1-1/2"V.
1/2"CW
1/2"HW
2"CW
3/4"HW
2"V. 2"V. 1-1/2"V.
2"V.
2-1/2"V.
ST
B.V.
3"
4"W
SK-1 EWH-1
SH-1 SH-1 SH-1
SH-2
IB-1 IB-1
FD-2
IM-1
IB-1
1/2"HW
3/4"CW
3/4"CW
1-1/2"V.
1/2"CW
1/2"HW
3/4"CW
1/2"CW
1/2"CW
3/4"CW
WD-1
2"V. 2-1/2"V. 3"V.
3"V. 2-1/2"V.
2"V.
F
FS-1
FLOOR CONTROL VALVE
TS-1
FIRE COMBINATION
STANDPIPE / RISER
4
3
2
5
3
8
6
9
x
12
1 11 10 11
SHEET PROJECT INFO SEAL REVISIONS DRAWING TITLE PROJECT CLIENT ARCHITECT
17105
NOVEMBER 15, 2017
CONSTRUCTION SET
MERCHANTS
CORPORATE
CENTER
CARMEL, IN
P-103
PLUMBING THIRD
FLOOR PLAN
N
SCALE:
PLUMBING THIRD FLOOR PLAN
1/8"=1'
GENERAL NOTES
A. REFER TO DRAWING P000 FOR PLUMBING AND FIRE PROTECTION
SYMBOLS AND ABBREVIATIONS.
B. PROVIDE CEILING ACCESS PANELS TO SHUT-OFF VALVES, CONTROL VALVES,
DRAIN VALVES, ETC... LOCATED ABOVE NON ACCESSIBLE CEILINGS.
COORDINATE ALL ACCESS PANELS WITH THE ARCHITECTURAL DRAWINGS.
C. INSTALL ALL PIPING AS HIGH AS POSSIBLE.
D. ALL PIPING, INSULATION, JACKETS, COVERINGS, SEALERS, MASTICS AND
ADHESIVES ARE TO HAVE PLENUM RATING WITH A FLAME-SPREAD INDEX OF 25
OR LESS AND A SMOKE DEVELOPED INDEX OF 50 OR LESS AS REQUIRED BY
CODE.
E. COORDINATE ALL SANITARY PIPING SIZES, INVERT ELEVATIONS AND EXACT
LOCATIONS WHERE PIPING EXITS THE BUILDING WITH THE CIVIL DRAWINGS AND
SITE CONTRACTOR PRIOR TO THE START OF WORK. FAILURE TO COORDINATE
THIS WORK AHEAD OF TIME WILL RESULT IN THE CONTRACTORS ACCEPTANCE
OF ALL COSTS RELATED TO WORK THAT MUST BE REWORKED.
F. FIRE PROTECTION CONTRACTOR SHALL DESIGN A COMPLETE SPRINKLER
SYSTEM ACCORDING TO THE CRITERIA OUTLINED ON THE DRAWINGS AND
NFPA13 AND NFPA 13R.
G. FIRE PROTECTION CONTRACTOR SHALL PREPARE ALL DRAWINGS AND
APPLICATIONS REQUIRED TO OBTAIN APPROVAL OF THE STATE FIRE MARSHALL,
ALL AUTHORITIES HAVING JURISDICTION PRIOR TO THE START OF
CONSTRUCTION.
H. FIRE PROTECTION CONTRACTOR SHALL SUBMIT DRAWINGS WITH ALL
SPRINKLER HEAD LOCATIONS. ALL HEADS TO BE LAID OUT NEATLY WITHIN
CEILING SYSTEM AND BE COORDINATED WITH ALL BULKHEADS, CEILINGS,
CEILING CLOUD SYSTEMS AND STRUCTURE.
I. ALL PIPING, SIZES, ZONES, MAINS AND EQUIPMENT SHOWN ON THE DRAWINGS
ARE FOR DESIGN INTENT ONLY. FIRE PROTECTION CONTRACTOR IS
RESPONSIBLE FOR PROPER COVERAGE AND CAPACITY OF THE SPRINKLER
SYSTEM.
J. NO SPRINKLER PIPING IS TO ROUTED THROUGH ANY TECHNOLOGY OR
ELECTRICAL ROOM. PROVIDE SIDEWALL SPRINKLER HEADS WITH GUARD.
K. CONTRACTOR IS TO COORDINATE THE LOCATIONS OF ALL CORRIDOR SHUTOFF
VALVES WITH EXACT LOCATION OF ACCESS PANELS AS LOCATED AND DEFINED
ON THE ARCHITECTURAL DRAWINGS.
SHEET KEYNOTES
1. 6" ROOF CONDUCTOR, UP AND DOWN.
2. 3" STORM WATER LINE, UP AND DOWN.
3. 4" SANITARY WASTE STACK.
4. 4" VENT STACK.
5. 2-1/2" COLD WATER RISER.
6. 3/4" COLD WATER LINE DOWN.
7. 3/4" COLD WATER LINE UP, SEE DRAWING P102 FOR CONTINUATION OF
PIPING.
8. 2" WASTE LINE DOWN.
9. 3" WASTE STACK SERVING MOP BASINS.
10. 8" ST. ROOF CONDUCTOR.
11. INSULATED ROOF CONDUCTOR PIPING.
12. HOT WATER RETURN BALANCING VALVE: SET FOR 1.5 GPM FLOW.
05/01/18
Nick Mishler