Loading...
HomeMy WebLinkAboutRieth-Riley Construction Co, Inc/Eng/CO #2/-5,134.32/106th & Towne Road RAB – Project #16-ENG-39City of Carmel Project 16 -ENG -39 106th Street and Towne Road RAB CHANGE ORDER #2 Extra work and revisions to existing contract items for the proposed roundabout. Contract Price prig to this Change Order $1,21 +,176.85 Contract Price wil I be decreased by this Change Order $5,134.32 New Contract Price including this Cliange Order $1,249.042.53 Amount I Adjusted Contract i Price Cumulative % Change from Original Contract Original Contract $1,196,604.12 N/A N/A C01 $17,572.73 $1,214,176.85 1.5% CO2 ($5,134.32) ` $1,209,042.53 1.0% E, i 1 TO: CITY OF CARMEL CONTRACT CHANGE ORDER NO.:) DATE: 3-9-18 PROJECT NANIE: 16 -ENG -39 106"'. St 8 ToN\ ne Rd RAB CITY REQ. NO.: CITY PO NO.: 100 179 CITY PO DATE: 2/16/17 fig/ RO�Fo �W 1, You are directed to make the following changes in this Contract: See Page 3-4 for all. or all charges in contract SCHEDULED ADJUSTMENT ITEM AMOUNT (+) OR (-)-DAYS [I. The following referenced Documents further describe the changes outlined in Paragraph 1. and are to be considered a part of this Change Order: R.F.P.: W.D.C. No.: Other: Chancre Order'-) The changes result in the following adjustment of' Contract Price and Contract Time: Contract Price prior to this Change Order $1.214,176.85 Contract Price will be increaseddecreased by this Change Order $ (5.134.32) New Contract Price including this Change Order $1.209,042.53 Contract Time Prior to this Change Order N/A Days N/A Completion Date Net increased/decreased resulting from this Change Order N/A Days Current Contract Time including this Change Order N/A Days N/A_ Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are The Above Changes Are Approved: Recommended Accepted: C-4 A+1 DreTf7, ENGINEER [? 2 00 �l�Y Sre CR:1tsi y{, Address CONTR.ACTUR 0.0 glAnesoA-4i Address CityiState'Zip City/State!zip By: Phone: siN-710 -t- 1 Date-- /f /% Date' 61(11"0 Christine S uley, Clerk - Treasurer Date: Clark Project No.' i6 -ENG -39 Description: 106th Street and Towne Road Roundabout Type. Overrun, /Underrun & T&N1 Work Summary: Balance to conract items and Additional T&M Work Change Order Descdptton: This change order represents the overruns and under runs for the contract items- R also includes additional work that was completed to adjus' curb ramp and gutter lines. The Time and Material work: report'or the ADA ramp and gutter line adjustments attached. The ADA -amp and curb and gutter adjustment work was completed due to grades shown In pians. They showed some fall around Che curb ramps but they were very slight along the gutter line. it was very difficuit to meet these grades it.. the field.An agreement wos made that the adju5zrneots would be compieted on T&M basis, Total for the T&M work totaled .$1.6,209„97„ The quanetity change; to the contract result in an underrun of 521,344,29 to the current authorized contract amount. The original contract amount was 51,196,04,12, Changer Order 1 added $17,572..73 to the contract giving it a Project Amount of $1,214,1 76>95. With this change order the reed project amount totals $1,209,042.53, That is wit^in 1% of the original contract amount: Awarded Project Amount: $1,196,60:,.12 Authorized Project Amount $1,214,1776.$$ Change Order Amount: Revised Project Amount: $1,209,042.53 Quantity Changes: 3'c; No, - On? J .i•1a PrcGI Guar .v i... BORR`L CYS S 1,0C 1 -..38,00f S SEDIMENT. REMOVE TEMPORARY CONS 7:Or, Fi `:» , LS 3 1,4'S r)0 L�G 8 TEMPORARY RIPRf I rclbS IF _-::. TON 1 V b.- j i TEMPORARY SILT FENCE LFT S 1.80 -r•'..: 7 FMPORARY SEED MIXTURE LBS S 0.26 - � a SUBGRADE TREA:JAIENT. TYPE:: ill SYS $ 3.34 ��,C:i 060RR04V - CYS S ' 2.9:1 r? Ni -3 i STRUCTURE BACKFI" TYPE 1 CYS 5 ` -28.:'5 . -33.7. FLOVlABLE BACKFILL, NO"EMOVABLE CYS S 50o 0: COMPACTED AGORSOATE NO. 53 B.=.SE TON S 3' o-, 2' MILLING. ASPHALT; 1 1,? IN -- --- SY5S - 5 v`- -87 95 22 MMA PATCHING: TYPE C TDN 5 120.00 14 nrl 23 HMA SURFACE. TYPE B; 41,5 MM TON $ 12iYwn 15-0F 24 HMA SURFACE. TYPE C, 9.5 MM TON S _ 'r nL 2194g•,T5p. °: :. 25 HMA INTE:RMEDtATE. TYPE S. 19.0 rv1M... TON a 1a,OC 413.35 34.395: ' 26 HMA INTERMEDIATE, TYPE C. 110 MM TON S 50.00 -107:61 - s 27 Hktk BASE TYPE C. 25 C MM TON S 57,00 -122-30 23 HNIA INTERMEDIA I E. IYP E C. OG, 19.0 MM TON S 5x.00 417 $2.563,&: n1 CURB RAMP. CONCR_ "T SYS S 194, 00 -65,u} 32 DETECTABLE WARNING SURFACES SYS $ 40.00 -1.72 33 BARRIER CURB AT RAO TURN APRON LFT S 24,00. -2.041 i4 34 CURB AND GUTTER, CONCRETE, TYPE II LFT S 2200 -25,W - 35 CURB AND GUTTER, CONCRETE. TYPE III LFT $ 23.,50 314,00 sa ; e8 fP: 36 CENTER r%1JR6. A. CONCRETE SYS $ 11L-00 43,22 - S5 CUPS AND GUTTER. COMBINE,- LFT $ 14,00 -437.4C1 42 M:ONUtr1ENT-. SECTION CO:i":EP EACH S .^0C.00 ]..00 44 GEOTEXTILES f SYS 1 10,27. -13.4 4s... RIPRAP, CLASS 2 y TON $ 53175 -4.03 47 MOBILIZATION AND DEMOW. IZATION FOR SEEDING ° r A H. S 50.00 -100 48 FERTILIZER TON S 5CC400 -1-00? --j 53 PIPE, TYPE 2, CIRCULAR, 36 IN i..FT S 386.00 a.0C - 54 PIPE. TYPE 4. CIRCULAR, 61N i ..FT $ 8.75 -361,01; 1 55 PIPE, UNOERDRAIN, OUTLET 61N _FT 12,: j -13200 56 PIPE, TYPE 2. CIRCULAR, 12 IN LFT S 62.60 -3^..6C 57 PIPE. TYPE 2, CIRCULAR, 15 IN UT $ 141"'1"', 9.it6 $423. 56 PIPE TYPE 2, CIRCULAR. 21 IN LFT -S " 52.90 150 80 VIDEO INSPECTION FOR PIPE LF r $ 1.26 -2 593 fA 42 ADJUST TO GRADE, VALVE BOX EACH $ 473,33 -s OJ 54 GGREGATE FOR UNDERDRAINS CYS $ 56.00 -25.55 64,GEOTEXT'iLES FORUNDERDRAIN SYS $ 1,6_ 313.50 68 CASTING, ADJUST TO GRADE, TYPE 4 TACH S C-361 K; -S.;r- New Items: kem No 00 1 unprice I W.n, ly P -XV MA WO CWS NIODWWATIONIS I LS I 5'B sMW I ill VOM40 1 New Items j SIS,209.97 I Change Zrd Fir Toral I IS n» 77, vl� 41e#1 Phov TnE, WWW� RnWWKC%-, LFT $ 2W.0c &3 HMRAW WnST E-;-,1, S 2.,&21.10G BS CIO' STRQC-90N S!CN, 7AGH B 1 aza-- 66 nom EACH S 200 NO SNOW all DETOuR PrIVYZ 1ARKEP EMH S f!,:Zc ill, F U&SAUCTION SIGk A EACH S CORINOWN &GN lux I coo 500 =M 10 EMOCnE M -A yl b c, -23,OC 93 57 07 S vo j Wo us lot WNDOT PVC 2 in 70 $ T"T �05-wl 133 CONOWT PVC 4 IN 5 izm 4M00 SAW ow 104 70NDUITIjr AIN WITH 3A 25 MTERDVTS -Fr $ 15,�:) 111 5 z 0 105 cMIWTpw4Ilj',%,llH,4-I U 02 X 57 MINE X"W NO MGT 4 in LOT S .it llao 509,; 0� lie TRANSVERSE .MARKING, THERWPLASNC CRASIo< ME W L.Fr 5 4zo N�, ou'l SRU Ol IN LLKE -�-QEPKN&jOQPLXA_l�TC BIWOKEN WME, 41N LFT 3 a5o 1100 121 Ll`tE, T�4ERIVIOPL-A371& DMED.,AHITE 8 IN 2 N3 11,0113 us cc) 10 FL to' -. ET 77 �VVwf) TPLAA S T 0 0 0 U ED, WHITE, S 1, J YT 1 SD 14 $21 oc 125 LINE T-ERMRAS7!Q SOLID AEUOW 4 1% &T Is 050 FOG S5 CC., 1-9. RAISE-? PAvENIENT WRK<ER .:4.'.y.;,:? 130 LINE. T-iERVOP_ASTr,. SOi:-D. YELi..07-5 Fj -=7 3 i -.30 2&'J, 21 QTWY E)QaWQ&N HUE DYCH $ 1,444,00 152 SIDEPtALK. CONCRETE 4 i -N SYS 6 4.72d sssj SLA� I 0 �? iZ3 CDUJT, PV:,. I IN CC.: D:;11 -FT I., G E,,) V. TYPE I I Zle Ll,ml 5[" S7REET SiGNNS - CARW,,'� i s rAW'.-ARD�-! "I $ 2,6C7.E5 I SS I 3000 ILOMW 0=71 Chwwwl ;521.3-13,29) New Items: kem No 00 1 unprice I W.n, ly P -XV MA WO CWS NIODWWATIONIS I LS I 5'B sMW I ill VOM40 1 New Items j SIS,209.97 I Change Zrd Fir Toral I IS n» 77, vl� 41e#1 Phov Memo To: Doug Haney, Corporation Counsel From: Lisa Scott CC: Jeremy Kashman Date: 06/27/18 Re: C.O. #2 Project #16 -ENG -39106' St. & Towne Road RAB Doug, please find attached 1 original of same change order for project #16 -ENG -39 106th & Towne Rd RAB. Please review & initial for the next BPW Meeting. Change Order #2- Original Contract Amount: $1,196,604.12 Decrease: $5,134.32 New Contract Amount $1,209,042.53 Thank you, Lisa Scott 0 Page 1