Loading...
HomeMy WebLinkAboutMorphey Construction/Eng/CO #3/19,394.97/Shelborne Trail/96th Street Trail – Project #16-ENG-73City of Carmel Project 16 -ENG -73 Shelborne Trail/ 96th Street Trail CHANGE ORDER #3 Change Order #3 includes the following T&M work completed, Relocation of water main from 23+00 to 26+00 on Line PR -B (RFI 4) and Additional Clearing from 59+00 to 62+00 on Line PR -C. Also included in Change Order #3 was additional Construction Engineering Cost due to Revision #2 on Line PR -S -1-A (Enoch ROE Agreement) and Revisions to Pedestrian Crossings on Michigan Road at 96'' and 106` Streets and 12" Vertical Stand Pipe (RFP 2) added at Station 16+20 on Line PR -B. Contract Price prior to this Change Order $3,834,247.97 Contract Price will be increased/decreased by this Change Order $19,394.97 New Contract Price including this Change Order $3,853,642.94 Amount Adjusted Contract Price Cumulative % Change from Original Contract Original Contract $3,652,000.00 $3,652,000.00 N/A C01 $100,247.97 $3,752,247.97 2.7% CO2 $82,000.00 $3,834,247.97 5% CO3 $19,394.97 $3,853,642.94 5.5% �•; tui CITY OF CARMEL o``��ii Fo �� TO: WORK DIRECTIVE CHANGE NO.3 DATE: June 21, 2018 PROJECT NAME: Shelbome Trail 90 St. Trail PROJECT NO.: 16 -ENG -73 Specification Reference T&M Work, Additional Construction Engineering eering Drawing Reference: PG. 10, 14, 15 and 27 DESCRIPTION OF WORK COVERED BY THIS DIRECTIVE CHANGE: A. Water main relocation from station 23+00 to 26+00 was addressed in RFI 4. This work was to be done on a T&M basis. Work was completed 4-12-18. The total additional cost to project for this Item is $10,333.86. Also 3 Calendar Days Added to Contract Completion Date. (See Attachment A) B. 12" Vertical Stand Pipe Drain: This item was addressed in RFP 2 as work to be completed on a T&M basis. The work was completed on 3-27-18. The total additional cost to the project for this Item is $3,274.14. Also 1 Calendar Day Added to Contract Completion Date. (See Attachment B) C. Additional Clearing on Line PR -C from station 59+00 to 62+00: This item was addressed in RFI 12. The work was to be completed on a T&M basis. The work was completed on 5-11-18. The total additional cost to the project was $4,568.14. Also 2 Calendar Days Added to Contract Completion Date. (See Attachment C) D. Additional Construction Engineering: Construction Revision #2 on Line PR -S-1 -A (Enoch ROE Agreement) resulted in re -alignment of the trail and also includes Revisions made to Pedestrian Crossings on Michigan Road at 96th and 106'b Streets. The total additional cost to project was $1,218.83. (See Attachment D) REASON FOR THIS ORDER: A.) T&M work completed for Water Main Relocation. B.) Additional Work Added to Contract. C.) Additional work Added to Contract. D.) Revision of Trail Alignment due to ROE Agreement. AR -3 Vasion 2016.08-31 AUTHORIZATION: THIS WORK DIRECTIVE CHANGE AUTHORIZES THE WORK TO BE COMPLETED AS OUTLINED. A Contract Change Order in the Amount of $_1_9,394.97 will be issued to you in the near future to cover this Work Directive Change. PROJECT COMPLETION DATE: ADD/— — — GT 6 DAYS. By: Robert Surber (BFS) A E Stine S. Pau , Clerk-Treas er AR -3 Version 2016-08-31 Approved By: CITY OF CARMEL BOARD OF PUBLIC WORKS AND SAFET B/esBjainar0j J Mayor Mary C.110SEMILIAr� ber By: Jeremy ashman, PE, City Engineer DATE: DATE: /zl),h,r Attachment "A" June 20, 2018 Jeremy L. Books, PE, CPESC Construction Department Manager Butler, Fairman & Seufert, Inc. 8450 Westfield Blvd., Suite 300 Indianapolis, IN 46240-8302 Re: EWA 02a — Watermain Relocation, T&M In Reference to: RFI No. 04 — Watermain, Utility Conflict, Response (Attached) T&M was tracked on 04-09-18, 04-10-18, and 04-12-18 for the watermain relocations as discussed in the response to RFI 04. Morphey Construction Inc. is requesting to add the following work item to our Contract for this work: EWA 02a-1—T&M 04-09-18............................................................................... 1 LS @ $2,450.91 Totaling $2,450.91 EWA 02a-2 — T&M 04-10-18............................................................................... 1 LS @ $3,376.68 Totaling $3,376.68 EWA 05a-3 — T&M 04-12-18................................................................................ 1 LS @ $4,506.27 Totaling $4,506.27 EWA 02a — Clearing Right of Way, Added Clearing Ln "PR -C" ..................... 1 LS @ $10,333.86 Totaling $10,333.86 Total Increase to our Contract: $10,333.86 Please see attached cost summaries and supporting documentation for your records. This work delayed our controlling operation by 2 work day. Morphey Construction would request 3 calendar days added to our Contract's completion dates. If you need any additional information, please let us know. Sincerely, Morphey Construction Inc. �/�9a-d-� �/�yGE��cc� Jason Umlauf (� Project Manager p. 1-317-356-9250 m. 1-317-766-3951 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 fx: 317.35.9253 www.morpheyconstruction.com BUTLER, FAIRMAN & SEUFERT, INC. Civil Engineers 8450 Westfield Boulevard, Suite 300 • Indianapolis, Indiana 46240-8302 317 713-4615 9 FAX 317 713-4616 email: BFS@BFSEngr.com TO: Jason Umlauf — Morphey Construction FROM: Jeremy Books CC: File �✓ DATE: January 31, 2018 Job No.: 592500 SUBJECT: 16 -ENG -073 Carmel Shelborne & 96'h Street Trails RFI No. 4 Resr)onse: The option of shifting of the watermain alignment to miss the utilities in moving of the watermain to the south from approximate station 23+00 to station 25+00 PR -B is the direction. The work related to modifications to the storm sewer has already been directed and the submitted price is acceptable for this work. As previously discussed, the work that is in addition to the original bid work for the watermain shall be tracked and paid for through time and materials. We expect the additional work to include the time, materials and labor to install any additional fittings required for the change in alignment. INDOT specification section 109.05(b) shall be utilized for pricing and tracking. Only time, materials and labor directly related to the additional work shall be compensated. A tracking sheet of labor, materials and equipment are to be agreed to on a daily basis. Let us know if you have any further questions. MORPHEY CONSTRUCTION Request For Znf'ormat%on December 5, 2017 Project: 16 -ENG -073 RFI No. 04 To: From: Jeremy Books - BF&S Morphey Construction Date Submitted: December 5, 2017 Date Info Req'd: 12-08-17 Category ❑ Info Not in Contract Documents Reference: Carmel Water Relocations ❑ Interpretation of Contract Documents Drawing: 96th Street Pg 15 O Discrepancy in Contract Documents Shop Drawing: ® Coordination Problem Specification: ❑ Clarification Attachments: ❑ Other Subject: Carmel Water's Water Main Relocation, Utility Conflict from Sta. 23+00 to 26+00 Ln "PR -B" Description: Two locations have been discovered were utility poles and nearby concrete pads/pedestals are prohibiting the installation of the proposed watermain. These conflicts are also extreemtly close to the proposed storm sewers. One location has a private shed adjacent to the proposed waterline that may need relocation. Please see attached pictures. The watermain as drawn in our plans cannot be installed with the present utility conflicts. Please provide information on how you would like us to proceed with the proposed watermain through this area. We offer the following for your consideration Z Solution ❑ Alternate ❑ Change Order Request Solution: Looking at the conflicts, two possible solutions can be Dresented by MCI. 1.) Relocation of Lh-e utilities.:j.)Shifting of the proposedwatermain n rm 5ewers to theh. This still may require some guy wire relocations, but it appears that the utilitv poles can remain in place. Structures 32 and 33 may be able to be shifted to the south and changed to manholes. Inlets may need to be added from the shifted trunk line to hit drainage points. The Proposed waterline may need t4 be shifted/lowered around the proposed storm. We will need further guidance on how to proceed. 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 Fx: 317.356.9253 www.morpheyconstrucction.com M� P ,... � . ,.��ay � ���� a � � _ � � �z�_ ,. .,� �'� : . �� ���," �i .} � , . ,�. MORPHEY CONSTRUCTION INC. - COST SUMMARY Pool Na_C� `��nW OSS oM I`7r-Z�>,'�i,,%Lf \-1°Z5-_poE d r -n j PM SWIM Add ..j o W �- -s'�' p or "p'S y> -- -1 0,g o 151ja o -YID \fLtS s 1 ,s E1 rYw'Wq}k 41U:f , bl.s a n IIogsoo'I nog uosaa •om mull SWIM Add IKKI:tizUAliee :dam L enol lad U04mM 'W y :dma,L q2!H �; pJ d��, i o loloe�IIo� CSS ! Jb :Xg uodoW ON[ `NouonmisNoo A3Hdaon JO l aged sxoagt u0113naoxa (MV aM.L Awa 1 ..j o W �- -s'�' �� 15 � 2W4MAo ag goan l OAU aaacy gsnn3 awry iS amBH as of IKKI:tizUAliee :dam L enol lad U04mM 'W y :dma,L q2!H �; pJ d��, i o loloe�IIo� CSS ! Jb :Xg uodoW ON[ `NouonmisNoo A3Hdaon JO l aged sxoagt u0113naoxa (MV aM.L Awa 1 0-1 1� it I} � /,6 C- K &n l DALLY TIME AND PRODUCTION REPORT Page ! of / NORPHEY CONSTRUCTION, INC. 1 Contract: �6 --f—r) %t" '- 7 Job # ,6 0 Date Report By: 09--VI'X j1 Contractor: Modke yp High Temp: A.M. Weather. P - C/0 uZ— Low Temp: aZ S° P.M. Weather: P c /0 U WWI RR RT Employee Name Start Time Finish Time Drive Lunch Regular Overtime a r Kl r e.--- do/(- 6 -cd 3Os J W " I C �OJ er Mo r ,�-- s.0, Tin �o,,.�•- ..� ST.`hl e�t-of�s�� PSV rr .MC Item No. Desai tion - - --- -- Location Quantity Unit a 3 t 7 0 s.0, Tin �o,,.�•- ..� ST.`hl e�t-of�s�� • S hd�— JC %So�,dC C01ChC (yOG� fi•�c�'¢.!''�df �s'",(30��0( �G Not":rK_c)N 30?0 Reviewed le I k Igned - Title r � / DAILY TIME AND PRODUCTION REPORT Page of j // MORPHEY CONSTRUCTION, INC. �trContract•. %l/ " ,yn 5 " % 3 Job # , O Date Report By: 1"e-)c'Lr'TX I',)" r_ �/ � Contractor: High Temp: A.M. Weather Low Temp: P.M. Weather: WKE SHEET y- Employee Name PAY Start Time Finish Time Drive Lunch Regular Overtime Quantity Unit vlrx CT 3� Dew; cl or 3,1 iry we rc 1, 3.3- wJ3-5- 3-5- PAY ITEMS Item No. t.on Lotion ca Quantity Unit 5�q C11 C� 1t [ 1 \ o r 57ruc urs I .r Frrr 6"Svm/ isnc�-u arfe, KjCkTo 3,s— Notes: MORPHEY CONSTRUCTION INC. -COST SUMMARY HNS WORKED/DAY --_---■------- TOTAL ECKAPMENT_ { • --����;CSMi�■li•Pll]71 i:•�!I\:PIH--iil� �- /�� ir�•�`Y4��`''ii� �-�i���'.�k�■E+1J+IIi1♦--t ---�}F6YIirl■------ '��f�" ■------� UNIT SUPPLY COST �������:d.J■Eiaa+r.�i:ac cn:rm�aianrl.:i:l������y.;� TOTAL HAUL COST Certified Pavroll Report Contractor MORPHEY CONSTRUCTION. INC. Project City of Cam* Mike McBride3064Shebane 8 96th St. 1 ProjectlComraU E 1499 Y SHERMAN DRIVE 3400 W. 131st Street Payroll Number INDIANAPOLIS, IN 45201 Carmel, Indiana 48074 For Week Ending 411512018 Hours Worked by Day Work Pay Man Tve Wed Thu Fri Sat Sun. Timesheet Palo Pay Job Fringe. Check Total Social Medl• Federal State Total 6m61wee Name Cr91g Davd A ID Clessifl-U.0 Type 8358 Operators Reg Rate R7 - S. io 11 12 13 I!L 8.00 8.00 8 16 Hours Hours Rate Grass Pay Rata Number Gto! Pav SecurltV care Tax Tax Other Deduct Net Pay 00 900 8.00 40.00 40.00 35.80 1.49200 58.46 DD3167 2,563.80 135.40 37.66 258.00 69.92 57 90 582.66 1.600.92 CrAll, DBVIdA 8358 Operators Overtime Rate RT 2.00 2.50 3.00 3.00 3.50 14,00; 14.00 53.76 751.90 16,46 DDG157 2,183.80 135.40 31.66 256.00 68.82 87.90 592.85 1,000.92 Gassed, Edward C 5370. Reg. .... Operators R Rate RT .. .. 9.00 8.00 9.00 21.00 24.60 34,80 '. 835.20. 1448-DD3174 .. 1,861.90 . ' 115.4 29.9 132.06 56.41 74.48 405.31 1,458.49 G935K EOxad C 5370 C"rators Overtime Rate RT . 2.00' 2A0 2.60 460' 6.50 5220 379.30' ' 18.46 DD3174 1.961.BD 115.43 36.98 132.00 38.41 744! 405.31 1,458.49 Haler, David E 3047 Operators per9laa Reg. Rate RT ... - 4.00 - .. .. 4.00 4.00 33.08 - 13292 . ' . 19.49 DD3175 1,993.07- .. 123.57 28.90 . 227.09 64.38 79.79 577.38 1,475.49 Haler, D94 E 3047 OperelOra Overme Rak RT 7.00 1.G0' 1.00 4962 44.82. 118411.6631S- 1,993.07 123.57 28.90 U1.00 64 ill 70.73 517.58 1,476.49 IUrby, MargrL 8740 Laborer Reg. Aar' Ri '7.6D 7.90 7.00 7.50 7.00 -- 38.00; 38.60 3096 .. 1.179.09 15.78 1303184.. 1,755.29 108 53 25.48 314.0081 J0 91.44 925.42 7,129.87 Morgan, DaWd W 8156.Operators Reg. Rale RT '11,01) 8.06 8.00 8.00 8.& 40,00: 40.00 94.90 1,392.00 16.48 D153189 1,992.30 123.52 25.69 351-60'64-35'140.05' 70711 1,284.49 Morgan. QevidW r9 8150 O Aerators Overdma Rely RT .. - 200 2.00 2.50 2.00 3.00 11,60 11.506 52.20 800.30, . 78.48 D03189 1,992.30 723.52 28.89 351.00 84.35 140,05 707.87 1,294.49 Morgan, Tyler M 2223 l5borer- . Reg. Rafe R7 .. 400 8.00 9.00 8.00 9.00 .. .. 40.111V4111.66 Z.241 806.90 15.78 DD3190 1,168.74 71.e4 78.80 1ai:do 37.4] 14.01371.09 787.88 Morgan. Tyler 2223 Laborer OmMme Rate RT 2.06 3.00 2.60 240 9.00 11.50. 11.60 ]8.38 3414 13.1E DD3/90 1,15474 71.84 16.80 '161.00 37.4 ..84.01 371.06 767.66 Welch, Bary E' 1860 Laborer Reg. Rata - RT 8.06 9.00 8-1064 GO 8.06 0.00: -40.00 24.72 688.80' 19.18`D03M 1,376.14 ' 85.45 19.99 64A0 4206 98.92 311.36 11,068.75 Weidi, Barry E 1860 Laborer OveK me Rale RT 2.662-00 2.50 2.00 2.00 70.50 1090 37.05 389.34 15.18 003209 1,378.14 95.45 19.95 64,00 42.03 99.92 311.39 1,088.76 Date. Apf-20, 2'J1B L tine Mreaeratla, AOFaWeng Marag.r, de henbyetal.; 0)That l pry or aupem,aedte paymani oftha plesons wnp"d ey MORPHEY CONSTRUCTION, INC an Ta prypq Cb of Cann MIFe Mr�ntle7mgSh tamed a6n St eatl sial dVn he employed on the said pm;m Mrs bean pod the fuu weaWY wag. "Mod NM m rabmea nave then or wad bO meds ark"' oV! tt➢ yMa'I feint our 1 moldy pit Apr -0g, ed b and ending , o her-1ma 20ero all prisons 4y 4 esdracay b 48, 5 ulna 0 said MORPIIFY CONSTRl1CT10N, INC ROT ria fW weedy wages Wined by airypaean, phot Bart permhelNe deQCCom .s daLraad m Reg�AaLlons. Part (29 CFR $Wase A), ranted DY pa $aaemry M Ubar uw'a the Copeland Aq. as amended (� 5tH. W B, SJ $tet. 106, 72 Stat 667; 76 Slat ]67, W U 9 C 276e), and daauEed below' (2) Tnet any P"rgra clhenwes order this cdneaq npdred b b. naYNtlad for ere ax pen=d"correct and gfmplah, Oral Ime wipe rhes for lebowa aril medanre rnrtlMntd TereF an ml W s then ah applloble wage rotas cmal000 in levy wage cunermmatm Imorp mf Mao ale coreracL that the daeplcat-W aH 1011h thereto sole each I.orer or reprep, —I— v* the work he Parknned (317140 am apprert— e."din the above porodare dtly reysterad in. bona ifs epp.'tb Np orcgram mgdlaatnaSlate appr0foceship agency Wooled bythe Steam ofApprarMcesiI and Tmmng, Wista Stiles Deparenem J Labor, of ffm sLh fan.Wt rd panty serum a Salta, are regmtered wYn rile Oaeau dAppratacufl�Nd Trenirg. Umkd $lads Dapgmhnl of Labq. (4) The (.11Ae4ERE FRINGE BENEFITS ARE PAID TO APPROVED PUNS, FUNDS, OR PROGRAMS 13 m Wailion to In. basic hurly wage rates pad k each laborer or mechanic dada in the above Wernaso payroll, psymnlb; df fringe bertefis a a Rated M the conena have Dean orwll be maoa to apprcionete programa forte benetll of Suri, artploy.s. a pl as roved In Secton a(c) below. (0) YAIERE FRINGE BENEFITS ARE PAID IN CASH 13 Each 4hdsra yr c leo listed In Ion soar. rate rented payfol due bean P.O. —no -dad on In. payroll, an amouq rot race nen the awn or na agA.blo bask houny wage rale pne ne .....I tho req. ad fnnge bene!to as linea m itis c jr. ; et,,gA as now n Sacdon ((c) bel - (b) EXCEPTIONS Name and r e Sipyyra rf Dine M�aeald, AOpdeying Manager THE WILLFUL FALSIFICATION OF ANY OF THE ABOVE STATEMEM7S MAY SUBJECT THE OONTRA OR SU CML OR CRIMINAL PROSECUTION SEE SECTION 1001 OF TRUE 16 AND SECTION 13- OF TITLE a1 OF THE UIfTED STATES CODE AL UTILITY PIPE SALES OF IN, INC. QUOTE 2nd N. Ave Indianapolis, IN 46219 polis,CathIN 6 I 11UTILITY 00Fax PIP. (317)224-2301 Number 00028965 "Providing The Flow, Above 6 Below Website: 1NWW.utilitypipesales.com Page 1 Date 0712912017 Bill QUOTE6 Ship QUOTE6 To ALL BIDDING CONTRACTORS i To QUOTE6 j QUOTE6 116-ENG-73 96TH STREET TRAIL Ij !CARMEL Customer PO# Ship Date ISalesperson ` Terms _ .----___....._...W_..�.....__. _ _. Tax Code 16-ENG-73 i QUOTE BID 0-10 DAYS IN Document # Warehouse Freight Ship via 00028965 UTILITY PIPE SALES OF IN, INC. Prepaid BEST WAY Item ! Description Quantity um Price Per Extension --_......... _... ...i_...___. LINE 33 TX311 P75 3oz Fabric Underdrain Fabric 1 EA EA 7.5'x360' roll size 300 sq LINE 35 i ++ TX801P 8OZ NW RIPRAP FABRIC VEA ! EA INDOT, 500 SQ YD, 15'X300' HDPE PIPE LINE 36-40 DP12NH 12" DUAL WALL SOLID X 20' 560.00 EA I EA DP15NH 15" DUAL WALL SOLID X 20' 220.00 I EA EA DP18NH 18" DUAL WALL SOLID X 20' 160 EA EA DP24NH 24" DUAL WALL SOLID X 20' 500 EA EA DP30NH 30" DUAL WALL SOLID X 20' 600 EA EA LINE 42 DP4CP1 4" SINGLE WALL PERF HDPE 1 EA EA 100' COIL DP6CPIDOT 6" X 100' PERF DOT 2 EA EA IIIIIIIIIIIIIIIIIIII 1 IN 1111111111111111111111111111111111111 IN QU Q0028965 Note: Current legislation states of January 4th, 2014 it will be illegal to sell or install any items that are leaded brass in sizes 2" and below for use with potable water. Manufacturers have been making this conversion since this legislation was passed. UPSCO will be implementing the following changes effective as of January 2, 2013. Any leaded brass order will be special ordered for our customers, but will be non-cancellable and non-returnable. UPSO cannot accept leaded brass returns for credit or exchange. This matches the policies of our brass suppliers- As of June 1, 2013 brass product manufacturers will stop manufacturing leaded brass products & no leaded brass items will be purchased by UPSO. Utility Pipe Sales Co. Customer Copy Continued on next page ... UTILITY PIPE SALES CO. QUOTE: 00028965 DATE: 07/29/20 PAGE: 2 Reprint Item ; Description Quantity uta Price Per i DP6CPIDOT (continued AASHTO INDOT DF4CAP 4" HDPE EXT END CAP 2 EA EA DF6CAP 6" HDPE EXT END CAP 2 EA EA LINE 43 DP06NHP 16" DUAL WALL PERF X 20' 140 EA EA DF6CAP 6" HDPE EXT END CAP 1 EA EA DFN6T 6" X 6" DUAL WALL TEE 1 EA EA IS151-66 6" AC/DI X 6" CI/PVC 1 EA EA FLEXIBLE COUPLING P356G 6" SDR 35 PVC SEWER PIPE 14 FT FT GASKET JT 14' LENGTH FS6COASWH 6" SDR35 CLEANOUT ADAPTER 1 EA EA FIPT X SEWER HUB FS6TP 6" SDR35 RAISED MIPT PLUG 1 EA EA FOR CLEANOUT LINE 44 IS102-66 6" CLAY X 6" CI/PVC 10 EA EA FLEXIBLE COUPLING P356G 6" SDR 35 PVC SEWER PIPE 185 FT FT GASKET JT 14' LENGTH I FS6TYG 6" X 6" SDR35 T -WYE GXGXG 1 EA EA FS6COASWH 6" SDR35 CLEANOUT ADAPTER 1 EA EA FIPT X SEWER HUB FS6TP 6" SDR35 RAISED MIPT PLUG 1 EA EA FOR CLEANOUT LINE 47 i N-DP12SLOT 12" CMP SLOTTED DRAIN 220 EA EA 6" GRATE HEIGHT N -CA 12 SOLTTED BANDS 15 EA EA N -CA 12 CMP 45 BEND 2 i EA EA N -CA 12 CAP j 2 EA EA ii��VHQ0028�i�l1�i��n- i65 iiiuiiiiiiuiuuiuii Extension Accepted By Continued on next oaae ... UTILITY PIPE SALES CO. QUOTE: Q0028965 DATE: 07/29/20 PAGE: 3 Reprint Item Description Ouantity u&r Price 3 Per j Extension CASTINGS I CAR4215C R -4215-C CONVEX GRATE 18 EA EA INDOT TYPE 7 CAR328710V R -3287-10V FRAME GRATE BACK 19 EA EA COMPLETE INDOT TYPE 10 N -CAR R -1878-A91- 30X30 SOLID 2 EA EA N -CAR R -3588-A INLET 1 EA EA N-CAR1714 R-1714 FRAME & VENTED LID 11 EA EA INDOT TYPE 4 LINE 66 N-SV12TF1 12" CHECKMATE VALVE 1 EA EA LINE 68 PDIC3506 6" CL350 DI PIPE, MON JT 120.00 FT FT RGMLK6 6" D.I. MEGALUG KIT 12 EA i EA INCLUDES GASKET, BOLTS & NUT LINE 69 P26356HW 6" SDR 26-35 SEWER PIPE 140 FT FT HEAVY WALL, GJ, 14' FSH6RCG 6" SDR26 HW REPAIR CPLG 12 EA EA GXG FSH645BG 6" SDR26 HW 45 BEND GXG 12 EAJ EA WTCWIOGRCCS30 10GA WIRE X 500'30 MIL PE 1 EA EA GREEN JACKET WTD2S 2" DET. WARNING TAPE 1 EA EA 1000' ROLL "SEWER LINE" i LINE 112 PDII6 16" CL350 DUCTILE IRON PIPE 2560.00 FT 37.32 FT 95,539.20 TYTON JOINT BNGFLK16 16" FIELD LOK GASKET 20 EAJ 285.00 EA 5,700.00 FOR DUCTILE IRON PIPE I I MJD1611 B 16" MJ 11.25 BEND 4 EAS i EA f Accepted By Continued on next Daae UTILITY PIPE SALES CO. QUOTE: Q0028965 DATE: 07/29/20 PAGE: 4 Reprint Item Description Quantity ; um Price Peri Extension MJD1611 B (continued) DOMESTIC MJD1622B 16" MJ 22.5 BEND 3 EA EA DOMESTIC RGMLK16 16" D.I. MEGALUG KIT 14 EA 168.00 EA 2,352.00 INCLUDES GASKET, BOLTS & NUT WTCW10BLCCS30 10 -GA WIRE X 500' 30MIL PE 6 EA� EA PRO HF-CCS-10AWG-BL WT132W ! 2" DETECTABLE TAPE 3 EA EA "WATER LINE" PE1618P 37" X 220' POLYWRAP 16-18" 15 EA EA FOR PIPE & FTGS - 8 MIL LINE 114 BFV16MJL 16" MJ BUTTERFLY VALVE 4 EA EA OPEN LEFT RGMLK16 16" D.I. MEGALUG KIT B EA EA INCLUDES GASKET, BOLTS & NUT CVBSPC POSICAP VALVE BOX ALIGNER 4 EA EA CVB664D 664-S ADJ VALVE BOX 39" - 60 i 4 EA EA SCREW-TYPE WITH LID, DOMESTI LINE 115 VARW8MJL MUE 8" MJ GATE VALVE OL 1 EA EA RES WEDGE, L/ACC CVBSPC POSICAP VALVE BOX ALIGNER 1 EA EA CVB664D 664-S ADJ VALVE BOX 39"- 60 1 EA EA SCREW-TYPE WITH LID, DOMESTI RGMLK8 8" D.I. MEGALUG KIT 2 EA EA INCLUDES GASKET, BOLTS & NUT LINE 116 VARW6MJL MUE 6" MJ GATE VALVE OL 1 EA EA RES WEDGE, LESS ACC CVBSPC I POSICAP VALVE BOX ALIGNER 1 EA EA CVB664D [664-S ADJ VALVE BOX 39" - 60 1 EAI EA �iumimii00028965 mmuuiuuiiiumuimiu� Accepted By Continued on next nage... UTILITY PIPE SALES CO. QUOTE: Q0028965 DATE: 07/29/20 PAGE: 5 Reprint Item DescriP tion Quantity ' unr Price Per CVB664D (continued) SCREW-TYPE WITH LID, DOMESTI RGMLK6 6" D.I. MEGALUG KIT 2 EA EA INCLUDES GASKET, BOLTS & NUT LINE 117 MJD166HYDT 16" X 6" MJ HYDRANT TEE 2 EA EA DOMESTIC VARW6MJL MUE 6" MJ GATE VALVE OL 2 EA EA RES WEDGE, LESS ACC CVBSPC POSICAP VALVE BOX ALIGNER 2 EA EA CVB664D 664-S ADJ VALVE BOX 39" - 60 2 EA EA SCREW-TYPE WITH LID, DOMESTI MJD624AC 6" X 24" MJ ANCHOR COUPLING 2 EA EA DOMESTIC FH42350SYS FIRE HYD 5 1/4 SAFETY YELLOW 2 EA EA 5" STORZ 3 WAY 5'0" BURY, O RGMLKI6 16" D.I. MEGALUG KIT 4 EA EA INCLUDES GASKET, BOLTS & NUT A6GB 6" GASKET & BOLT ACC KIT 6 EA EA LINE 118 MJD166T 16" X 6" MJ TEE 1 EA EA DOMESTIC MJD6SSLP 6" MJ SOLID SLEEVE LP 1 EA EA DOMESTIC PDIC3506 6" CL350 DI PIPE, TYTON JT 40.00 FT FT RGMLKI6 '16" D.I. MEGALUG KIT 2 EA EA INCLUDES GASKET, BOLTS & NUT RGMLK6 6" D.I. MEGALUG KIT 3 EAj EA INCLUDES GASKET, BOLTS & NUT EINE 1191 MJD168T 16" X 8" MJ TEE 1 EA EA DOMESTIC PDIC3508 8" CL350 D4 PIPE, TYTON JT 40.00; t i FT FT fli flimlit' Illlllllllllllllllllllllllllllllllllllnllllllllll Extension Accepted By Continued on next oaae ... UTILITY PIPE SALES CO. QUOTE: Q0028965 DATE: 07129120 PAGE: 6 Item ,t7escripdort MJD8SSLP 8" MJ SOLID SLEEVE LP .16 LINE STOP I DOMESTIC RGMLK16 16" D.I. MEGALUG KIT 8 LINE STOP IN INCLUDES GASKET, BOLTS & NUT j RGMLK8 8" D.I. MEGALUG KIT 6 LINE STOP INCLUDES GASKET, BOLTS & NUT LINE 125 LINE 120 MJD16SSLP 16" MJ SOLID SLEEVE LP LINE 128 DOMESTIC RGMLK16 16" D.I. MEGALUG KIT 6" MJ45 BEND INCLUDES GASKET, BOLTS & NUT LINE 121 1 2 3 2 4 BMD47018Q1 f1" BALL CORP CC X CTS 2 NO LEAD CK1100 11" "K" SOFT COPPER X 100' 100 BMD610001 1" CURB STOP CTS X CTS 2 NO LEAD BMD475801 1" CTS BRASS COMP CPLG 2 DOMESTIC 2 1 1 15 40.00 4 Pf q1011ma. NO LEAD LINE 122 I N -CA .16 LINE STOP LINE 123 N -CA 8 LINE STOP IN j LINE 124 N -CA 6 LINE STOP LINE 125 CVB60E 24" VALVE BOX EXTENSION LINE 128 PDIC3506 6" CL350 DI, PIPE, TYTON JT MJD645B 6" MJ45 BEND DOMESTIC 2 1 1 15 40.00 4 Pf q1011ma. 111111111 IN Q0028965 Al EA EA EA EA EA EA FT EA EA EA EA EA EA FT EA EA EA EA EA EA EA FT EA EA EA EA EA EA FT EA Accepted By Continued on next Daae... UTILITY PIPE SALES CO. QUOTE: Q0028965 DATE: 07/29/20 PAGI Item Description MJD6SSLP 0.001 6" MJ SOLID SLEEVE LP DOMESTIC RGMLK6 6" D.I. MEGALUG KIT INCLUDES GASKET, BOLTS & NUT ! LINE 129 POIC3508 8" CL350 DI PIPE, MON JT MJD845B 8" MJ 45 BEND DOMESTIC I MJD8SSLP 8" MJ SOLID SLEEVE LP DOMESTIC RGMLK8 ! 8" D.I. MEGALUG KIT INCLUDES GASKET, BOLTS & NUT LINE 130 MJD16SSLP 16" MJ SOLID SLEEVE LP DOMESTIC MJD1645B 16" MJ 45 BEND DOMESTIC RGMLK16 16" D.I. MEGALUG KIT INCLUDES GASKET, BOLTS & NUT PD116 116" CL350 DUCTILE IRON PIPE TYTON JOINT QUOTED BY: jays EXPIRES: 08/30/2017 7 Repri Quantity i 2 12 40.00 4 2 12. 21 4' 12 40.00 nt UM EA EA FT EA EA EA EA EA EA FT Price Per i EA EA 685.48 FT EA EA EA EA EA EA FT Extension, __ s 2,741.92 Merchandises Add On Charges' Tax Total Due ,,,-, ..eT_.__.�.__,.. 247,271.41 0.00T 0.001 We appreciate your business! 111111111@ 111113 1 fell INQ0028965 Al Accepted By ... Last oaae 3821106 INVOICE Lehigh Hansen nvoice Number: Invoice Date: 04/14/18 HEIDELBERGUMENTGroup Page: 1 Terms of Sale: NET 30 DAYS Billing cn behalf of: WWWWW Customer Number: 8879224 Aggregates Midwest LLC 1111111111150 Tax Code: IN-NONTA Hanson WW Customer Job: 18-17H/16 ENG -73 ShelbarnEwa I—TH ENSURE PROPER CREDIT PLEASE INCLUDE MORPHEY CONSTRUCTION INC THE INVOICE NUMBER WITH YOUR PAYMENT Now son REMIT TO: 15620 Collection Center Drive , Chicago, IL 60693-0156 1499 NORTH SHERMAN DRIVE INDIANAPOLIS, IN 46201 —So VTax ID: 61-0476452 -�o0 Sales Carder Mani Ivery Job 3060 PO 6384 74531,44 Harding ST. Fuel Extended Product Description Quantity UOM nit Prac Amount Freight tithe fh9e8 F price Ticket Ticket Truck Ship to Reference roduct Numtw Date Number Type 17.66 Ton 55.65) $99.78 $0.00 50.00 04/12J18 1855242947 ST 6384 Sheinorne & 094230 112 Structure Backlill 17.36 Ton $5.65 $98.08 $0.00 $0.00 $99. $98.0 04/1211$\1855243065 ST 6384 Shelnome & 094230 112 Structure Backlill 17.95 Ton $5.65 $101.42 $0-00 $0.00 $101.4 \ 6384 Sheinorne & 094230 04/12/18 1855243171 ST 1/2 Structure Backtill 18.24 Ton $5.65 $103.06 $0.00 $0.00 $103.0 1855243266 ST 6384 Shelnorne & 094230 1/2 Structure Backfill --PRODUCT SUMMARY -- 094230 TOTAL QUANTITY --> 7121 71.21 Subtotal: S402. Tax: thtBstiQanta? Plessrr call Customer Cate at- (SS6) 242-5960 Invoice TOM: ;r*!f2m This invoice is subject to the terms set forth in the Credit Application andor General Terms ar.d Cfferent terms pponditions of Sale, as well hereby any additiobe a mate nal terms and `condition acontai erin the Qe tot tion o itOrd rreturned aregsubject o Cartageland handonal or l ng cha ges. Accoounts are due arndrpayab4e ythe above stated terms' Past due accounts are subject to service charges as outlined in the Credit Application and/or General Terms and Conditions of Sale. Attachment "B" March 27, 2017 Jeremy L. Books, PE, CPESC Construction Department Manager Butler, Fairman & Seufert, Inc. 8450 Westfield Blvd., Suite 300 Indianapolis, IN 46240-8302 Re: EWA 04 — 12" Vertical Standpipe Drain In Reference to: RFP No. 2 (Attached) MOPAHEY r~r t,C-!z .'i r ' i 0 N Per RFI No. 2, Morphey Construction Inc. is requesting to add the following work items to our contract: EWA 04 —12" Vertical Standpipe Drain.................................................................................1 EACH @ $3,274.14 Totaling $3,274.14 Total Increase to our Contract: $3,274.14 This work includes exposing and coring the top of the previously installed 24" RCP, installing a 12" vertical Standpipe, and placing a concrete collar completely around the 12"/24" RCP junction and vertically around the 24" RCP. This work will add —1 day to our Contract's controlling operation. Please see attached cost summary for your records. If you need any additional information, please let us know. Sincerely, Morphey Construction Inc. aJason Umiauf Project Manager p. 1-317-356-9250 m. 1-317-766-3951 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 fx: 317.35.9253 www,morpheyconstruction.com CITY OF CARMEL To: Jason Umlaf REQUEST FOR PROPOSAL 2 Morphey Construction DATE: 3-15-18 PROJECT NAME: 90 Street Trail PROJECT NO.: 16 -ENG -73 Specification Reference: Added Storm Structure Drawing Reference: PG 14 Drawing Date: 7/13/17 Identification of Attachments: N/A Please submit within fifteen (15) calendar days of this request date a proposal showing increase, decrease or no change in Contract Price and/or Contract Time. Proposal shall be accompanied by four (4) copies of breakdown showing quantities, cost of material, equipment, labor, overhead, profit and basis for the additional time if any. DESCRIPTION OF PROPOSED CHANGE COVERED BY THIS REQUEST: Request a price for adding an additional Vertical Stand Pipe type structure for storm drainage at approximant station 16+20 on line PR -B. (As proposed in Progress Meeting on 3-14-18, (8" vertical pipe tapped into the 24" RCP). REASON FOR CHANGE: At station 16+20 there is a low area along the property line between Mr. Jones and Mr. Kolerten draining the properties toward the trail. This will create a ponding area along the trail and backing up to the north along the property lines. SPECIAL INSTRUCTIONS: THIS REQUEST DOES NOT AUTHORIZE YOU TO PROCEED WITH THE ABOVE WORK NOR STOP PREVIOUSLY SCHEDULED WORK. Upon approval a Contract change Order and a Notice To Proceed will be issued. Please state in your proposal the effect the acceptance of this Request will have on the Project's Substantial Completion and Final Completion, if accepted with _ days of proposal due date. YOUR PROPOSAL DUE DATE: 3-30-18 By: Engineer Approved by: Owners Repres tative AR -1 Version 2016-08-31 Date AMC-' 54X X um COST Attachment "C" June 20, 2018 Jeremy L. Books, PE, CPESC Construction Department Manager Butler, Fairman & Seufert, Inc. 8450 Westfield Blvd., Suite 300 Indianapolis, IN 46240-8302 Re: EWA 05 — Added Clearing, Ln "PR -C" In Reference to: RFI No. 12 — Additional Clearing, Ln PR -C Additional clearing was directed for areas outside of the construction limits shown on line "PR -C". T&M was tracked on 05-07-18, 05-08- 18, and 05-11-18 to completed this work. Morphey Construction Inc. is requesting to add the following work item to our Contract for this work: EWA 05a — T&M 05-07-18............................................................................... 1 LS @ $2,481.79 Totaling $2,481.79 EWA 05b — T&M 05-08-18............................................................................... 1 LS @ $1,003.68 Totaling $1,003.68 EWA 05c —T&M 05-11-18................................................................................ 1 LS @ $1,082.97 Totaling $1,082.67 EWA 05 — Clearing Right of Way, Added Clearing Ln "PR -C" ..................... 1 LS @ $4,568.14 Totaling $4,568.14 Total Increase to our Contract: $4,568.14 Please see attached cost summaries and supporting documentation for your records. This work delayed our controlling operation by 1 work day. Morphey Construction would request 2 calendar days added to our Contract's completion dates. If you need any additional information, please let us know. Sincerely, Morphey Construction Inc. Jason Umlauf Project Manager p.1-317-356-9250 m.1-317-766-3951 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 fx: 317.35.9253 www.morpheyconstruction.com 0 MORPHEY CWYSTr iiON Request ,dor Information iri i � nwr� inn venni nnn iwwrr�rr ur r nmwuuwrrr� February 2, 2418 Project: To: From: 16 -ENG -073 Robert Surber - BF&S Morphey Construction RFI No. Date Submitted: Date Info Req'd: ategory ® Info Not in Contract Documents Reference: ❑ Interpretation of Contract Documents Drawing: ❑ Discrepancy in Contract Documents Shop Drawing: ❑ Coordination Problem Specification: ® Clarification Attachments: ❑ Other Subject: Additional Clearing Right of Way on Line "PR -C" 12 February 2, 2018 02-06-18 Item No. 0003 Sheet 27 of 97 96th Street Plans Description: On Sheet 27 of 97 in the 96th Street Trail plans, there is a tree/brush row along the north side of 96th street from Sta. 59+00 to Sta. 62+00. These area is located between 96th Street and the or000sed trail. However, it is outside of our construction limits and the clearing, arubbina and removals within this area were not included in our original Clearing Right of Way. Please provide clarification on whether or not it is desire to clear this tree/brush row area. Me offer the following for your consideration ® Solution ❑ Alternate ® Change Order Request Solution: If it is decided to have this area cleared, we would suggest tracking our work with T&M. 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 Fx: 317.356.9253 www.morpheyconstrucction.com iill����i�s ��� �� ����� 1 C� . . . .. ......... V WILY TIME AND PRODUC 1'1 REPORT 7 t.5-r� - of page 11 - TIME SHEET MORPHEY WqSTRW--I-�aN, RC - Date Contract: Emp"-nc Name Job #— -30 6 c -------- Finish Tinx Report By: Phey > conm(btmr- Pte' (t�� I ligb Temp: A.M. Wcad)a-V Low Temp: —P.M, weadwr- TIME SHEET Una Emp"-nc Name Sta;-t Tune. Finish Tinx Drive 5 4 i, -(r I k, AV" le' I- I R I - ,"A - i 11 rrVIL4k, No - Una 4 i, -(r I k, AV" le' I- I R I - ,"A - No - MORVNEY CONSTRUCTION INC - COST SUMMARY r h Y page t of ULY TM AND pRpDUCTTQtY REPORT Repast Bw: e t _ _Loab-acto !_ �r P ' _ . ,•-- High Temp - Low Temp: � �` � ��.�rk. Wcu F-YXW&Y*A7M Item No. v Uig Y" �XXYrIE)LS%fP r --Wu Sr Si r4� 6oa CA; 4-r- -9 -t SrJe ! #'' ,^s e } ! .! '�:.gr .�`�' r! ^x' J ?:..LY" 1=�`t'Y i � .�,�t�► ,+� ' +�"�'i ��:'� J r' M'l mm go MORPHEY CONSTRUMON INC. - COST SUMMARY K14it"I'm INA AMI t 11 i Certified Pavrol[ Report Contractor MORPHEY CONSTRUCrON, INC. Pro)"i City of Carmel Uke lAc8r1det3080Shelbome & 961h St. I ProtecItCordraet 0 1499 N SHERMAN DRIVE 3400W 131st_Street Payroll Number INDIANAPOLIS, IN 46201 Carmel, indlana 48074 Far Week Ending 5/1312016 Hours Worked by Day Wank Pay Mon Tue Wed Thu Fri Sat Sun Timesheet: Paid Pay Job Fringe Check Total Social Medi- Federal State Total Employee Name ID Classelcatien Type 7 8 9 10 11 12 13 Hourew Hours Rate Gross Pay Rate Number Gross PaXSecurity care Tax Tax Other Deduct Net Pay Crelg, Davkd A 8358 Operators Reg. Rate RT 800 8.00 18.001 15.00 35.80 572.80 18.4fi D0338C 2,210.85 137.08 32.05 264.00 70,78 88.98 592.87 1,617.76 Craig, David A 8358 Operators Overtime Rate RT 1.50 2.00 8.50 3.50 59,76 187.95' 18.46 DD3380 2,210.65 137.88 3206 264.G0 70.78 88.98 892.87 1,617.78 GasseR, tatlwartl L $376 Op of Rep. Rale R7 8.08 8.08 6.06' 24.00' 24.00 31.60 836.20 18.46 01013367 3,400.70 86.85 20.31 77.00'41.52 56.03 281.71 1,118.99 Gassed, Edward C 5370 Operators Overtime Rete RF - 1.60 � � . 200 3.5V' 8.60 52.20 18270 18.16.0013387 1,408.70 - 06.85-2631 77.00 41.52 58.03 281.71 11118.88 Hater. Davld E 9047 Operators Reg. Rate W 8.00 8.00 8.00 33.08 254,84 18.46 OD99B9 2,067.50 120.19 29.98 237.00 68.78 62.70 544.66 1,622.86 Haler, David E 3047 Operators Overtire Rate RT 2.60 2.50 2.50 49.82 124.05 18.46-DD3389 2.067.50 126.19 29.98 237.801 66.78 62.70 544.85 1,522.85 Kirby, Coie L 6890 Laborer Reg. Rale - RT - 8.00 8.00 11.60 8.00 8.00 40.00. 40.06 23,72 946.801 '19.7ti 003396 1,233,44 78.47 17.88 141.00 79.22 89,42 986.89 B67 43 [City, Cole L 6890 Labcrer ov"we Rate RT - 1.60 1.50 3.00 2.011 8.00 8.90'96.58 284.84 16.16 DD3390 1,239.44 78.47 17.88 14300 39.22 89.42 355.99 867.45 k1ts7, hhutYL 6720 Laborer Reg. Rale AT 7.60 6.50 4.56 8.00 3.00 29.90: 29.30'30.65 904.47 15.18 603397 1,732.30 10700 25.12 369,06 80.85 92.25 614.72 1,11758 KAY• Marty l. 6720 *Laharer Overtime Rab RT 1I70 1.00 1.011 15.90 45.98 15.18 01013397 1,732,30 107X9 25.12 909.00 80.95 92.25 814.72 1,117.38 Morgan, Tyler M 2223 Laborer Reg Rate RT 8,00 6.08 6.06, 21.00 21.00 20.24 425.04 15.18 OD3404 1,219.46 - 75.67 17.68 175.00 36.36 711.95 Ms.,63 832.89 Morgan, Tyler 2223 Laborer Overtime Rate RT 1.50 1.50 3.00. 3.00 90,36 91.D5 16,1W000M 1.219.46 75.81 17.88 17500 30.39 78.95 385.63 932.03 Uphaus, Ethan K 8407 Operators Reg. Rale RT - 8.00 8.00' 8.00 34.80 278.49 18,46 0013415 2,931.60 1+41.55 33.90 290.00 74.69 93.84 636.69 1,59.71 U086Ethan K- 8407 Operators Ovedlme Rafe RT 1.50 -1.60 1.50 6220 '78 ii) 18-411.003415 2,331.08 144.56 33.60 290.00 74.69 93.64 635.89 1,894.71 Barry We0ch,8anyE -1960LabOrefReg. Rale RT ......... 8.00600 8,008.008.00 - �- 40.80-�40,0024.72988.80' 16.16D1.7y120 1,24830 77.38 18.10' 49-00978q 90.54 272.84 876.62 Welch, Barry E IeW Laborer Overtime Rate RT 1.66 1.50 2.60 2.00 _ 7.80 7.60 37.08 259,58 75.16 DD3426 1,248.36 77.39 18.10 49.00 37.84 90,51 272.84 915.32 Dote MaY•21, 2018 I. Gdna Maztarella, Accounting Mamger, m hemby H41e; (1) Thal I ply or supervise the paymrtt of W peraorm emp"d by MORPHEY CONSTRUCTION, INC. m the pro)eat Coy of Carmel Mike mr�ido t08f1$rrWpme 5 BBtn SI. Nee Naltluing the peYcoll penotl carrmertartg an Aaym,x018 antl en6ng on MaY-13. 20la all persons smViayed an the Slid project have base paid pts, lull moldy wages, earned, that m+obalee have been or will be made ether dxaGly a Indirectly to or an behad of stud MORPHEY CONSTRUCTION. INC. horn the JIM weekly rapes earned by a„y pomm, OVUr Nan permissols dadu lima sur cWmd m RegulNw xs, PWt 3 (79 CFR SUbide A), leaved by Ne Secretary at Labor mdH gr Copeland W, es wae:ttletl 148 Sul 9d& 835Uh 108, 72 StM 987 78 Slat 367, 40 U.B C. 279x), ret d bed bear: 12) TAvI anY payrmts txhennse under ens mnkaG regrJrad lobe subm9led far the sbw�o periatl era curet antl mmFleU, slat Qts, wage ryes fpr Ubrners aM reerltenlu pOnlditatl tltareln ere viol teal Pen ow �parnlle wago rales conUlned in any weyo rlalemertalon ktmrpcmled Slip N0 CmtleG, drl Iti G®ti:aLroru eel lUlFl IhereYl lof�e�h laDOrer pr rrrGlerep cmfomt MMI Ne Wrk 1141 perlomled (3) That any appreduces Hnpad"d r the � bb" perp are Addy registered m a hurls me apperMiceeHp program regslered With a Slide aPPrvmaashp agemy remgrdted by the Bveeu Of APF—t hip end Training; INkled Stales Deporimen pl Leber. � t Fro :vch remgnbed egertey erste et a Sola. Seen ' ppMawsnp a>rb Trevlaq, UMkd SUNS DapennyN of Labor (4) That (e) MERE FRINGE BENEFITS ARE PAIC TO APPROVED PLANS, FUNDS, OR PROGRAMS In addi8m 1411141 baelch0llly wage retie Paid to each faborer m mecharsc listed to Bre above talemyad payrop, paymaN s of mope bendsSIR, lleled h Uwe comet have been m wo!be mad. to epprop note program, tar the benent a -m emptoyeee, e.cept as, rated rn Secdm 4(W below (b) MERE FRINGE BENEFITS ARE PAID IN CASH Q E..h lstarer ormechanc listed M the ab ,.WFW.ad payroll lNa been paid, as irtdreaed m Nepo"k m amourl rot Un Nen the sum of the applicable base: hcuty wage Fele Plus pip amount 09 the requited huge b..(s.listed 0 the corroact—pt as Sated rn Secbm d(c) below (d ExCEPT1OFS Name and Tips, Bgrowrs )l Gina M=aM)& A000unbr® Mannar IClfi_l THE tMLLFUL FALSIFICATION OF ANY OF THE ABOVE STATEMENTS MAY SUBJECTTHE CONTRACTOR OR SUBCONTRACTOR Tdt&L OR CRIMINAL PROSECUTION SEE SECTION 1WIOFTRLE 18 AND SECTION ' OF TITLE 111 OFT11E UNITED STATES CODE. Attachment "D" June 20, 2018 Jeremy L. Books, PE, CPESC Construction Department Manager Butler, Fairman & Seufert, Inc. 8450 Westfield Blvd., Suite 300 Indianapolis, IN 46240-8302 Re: EWA 06— Construction Engineering, Rev 2 Ln "PR -S -1-A" In Reference to: Construction Revision No. 2, Shelbourne Road Trail Construction Revisions No. 3 & 4, 961h Street Trail Construction Revision No. 2 on Line "PR -5-1-A" changed the alignment of the trail through the Enoch parcel. This revision required additional construction engineering to implement the required changed into our construction. Morphey Construction Inc. is requesting to add the following work item to our contract: EWA 06 — Construction Engineering, Rev 2 Ln"PR-S-1-A".......................................1 LS @ $1,218.83 Totaling $1,218.83 Total Increase to our Contract: $1,218.83 Please see attached cost summary and sub invoice detailing the extra work required. If you need any additional information, please let us know. Sincerely, 1 Morphey Construction Inc. ���/?ii �f94e� '''JJJ7 Jason Umlauf Project Manager p. 1-317-356-9250 m. 1-317-766-3951 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 fx: 317.35.9253 www.morpheyconstruction.com MORVTEY CONSTRUCTION INC. - COST SUMMARY ® ■ '® '®'®� '®'®®' ' WORKMANS COMP UNEMPLOYMENT SOCIAL SECURITY TAX f�11:17T1Z1: \:•[.iTlSiii /\'�--����'.'a'.� ■ �ir137R3�--�� �QSii�t�[•:TI:Y� MATERIALMARKUP TOTAL MATERIAL WITH MARKUP TOTAL COSTS WITH MARKUPS BOND AND INSURANCE MARKUP TOTAL HAUL WITH MARKUP SurveyTech P.C. 7172 North Keystone Unit J Indianapolis, IN 46240 Phone(317)255-9339 Fax (317)259-7560 Bill To Morphey Construction, Inc 1499 N. Sherman Drive Indianapolis, IN 46201 Date Invoice # 6/20/2018 2510 Job Description 16 -ENG -73 Serviced Qty Item Description Rate Amount 5/9/2018 2 Prof. Land Surveyor Update points and revise points etc on Revision on 130.00 260.00 Michigan Road 6/19/2018 1.5 2 man Crew Stake nails in pavement and locate elevation needed to 172.00 258.00 build surface. 6/20/2018 2.5 Prof. Land Surveyor Revise surface and set points on revised trail 130.00 325.00 6/21/2018 1.5 2 man Crew Extra Curb staking 172.00 258.00 Total $1,101.00