HomeMy WebLinkAboutKheradiya Basement SpecsSpecifications to Project
07.10.2018
Prepared For:
Kheradiya Residence
10494 Hyde Park
Carmel, IN 46032
General Project Description:
Custom Living proposes services for a basement remodel as follows:
08/28/18
Mike Sheeks
2 Initials ______ ______
SITE PREPARATION
Owner is responsible to have all personal belongings removed from the areas of
construction prior to the start of work
Owner understands that during construction of home there will be more dust and
particulates ventilating through home and Custom Living can at an additional charge
have ductwork cleaned prior to completion of project
All materials provided by homeowner need to be on-site prior to the start of
construction to ensure there are no delays in construction
PERMIT FEES
Custom Living assumes the responsibility to submit and receive appropriate permits for
project. The Homeowner is responsible for any additional municipal fees
WASTE MANAGEMENT & CLEANUP
Scavenger service is included to remove Custom Living’s debris for its work under this
contract.
Any additional scavenger pick-up by client for non-related debris will be charged to
Homeowner. Custom Living is to remove all related debris from job site upon
completion
Homeowner will need to designate a driveway location for the dumpster to be located
during construction
The dumpsters are estimated as an allowance, if there is more debris from demolition
and construction than originally anticipated. Additional dumpsters delivered on site will
be charged to the Homeowner.
Custom Living can provide a dust fan rental of $15 per week up to eight weeks if
requested by homeowner.
ROUGH CARPENTRY L&M
Install all plastic and floor protection necessary prior to demolition
Remove all existing cabinets, countertops and appliances (TRASH)
Remove existing floor tile down to basement slab
Remove drywall necessary for mechanical rough ins
Remove drywall from soffits to be deleted as shown on prints
Remove existing direct vent fireplace box
Delete non load bearing interior walls and wall niches as shown on prints
Remove existing floor tile located in wine cellar down to concrete slab
o Prep surface for carpet installation
Prep existing basement slab for LVT flooring installation
o Existing basement slab will need to be grinded down
o Homeowners understand that there will be dust and particulates in the air
during time of concrete grinding that will be difficult to contain to the areas of
construction.
Install framing for new soffits in locations shown on prints
08/28/18
Mike Sheeks
3 Initials ______ ______
Install non load bearing interior walls as shown on prints
Frame 2x4 and 2x6 half wall in location of basement bar as shown on prints
Frame 2x8 drop ceiling in location of proposed bath and storage closet
o Ceiling to be dropped approx. 12” for venting of new bath and HVAC fixtures
Homeowners understand that it is impossible to know with absolute certainty, the
location of all mechanical runs located in existing walls of the home. If there are any
additional mechanical runs found in walls to be deleted or reframed, as noted on the
prints, there will be an additional charge for labor and material to relocate necessary
mechanicals for proposed plans. Updated will be determined with a field walk
following the demolition phase, with the Homeowners, Custom Living, and the
necessary trades.
Separate Pricing
Remove existing wine cellar door, wine cellar cooling unit and wine cellar racks
o Remove door casing and exterior door threshold
MASONRY
Patch (1) exterior fireplace penetration to be deleted from demolition
o Homeowners understand there will be a noticeable difference between new
brick and old brick due to age of the existing brick and sun exposure.
HVAC
Connect new microwave exhaust vent to existing exterior vent duct
o Add a booster fan to existing ductwork to vent to exterior of the home
Install supply vent for maintenance access to booster fan unit
Fan will need a power feed provided by electricians
Booster fan to be supplied by Custom Living
Check all zone dampeners for proper operations.
Install wifi thermostat and wire to control basement unit
Tie both 8” located in great room to (1) zone damper
o Install new vent covers where necessary
Vent proposed bath vans to exterior of home
Add elbow and rework existing flex ducts to remove kinks in line
Run supply duct for workout room location through ceiling cavity
Extend return duct plenum in bulkhead located behind structural steel beam
ELECTRIC
Disconnect all outlets and switch legs in walls being removed or reframed prior to
demolition
Disconnect and remove existing surface mounted light fixtures
All new outlets to be white with white cover plates
All new switches to be white Decora toggle switches with white cover plates
o All Dimmer switches to be Decora slide dimmers
All recessed can fixtures to be LED with white trims
08/28/18
Mike Sheeks
4 Initials ______ ______
o Product Model No. - Cree SRDL6-065
All flush mount fixtures to be provided by the homeowners
o Homeowners understand that to avoid any delays or extra charges, all fixtures
need to be on site during rough in phase to provide appropriate wiring and
blocking necessary
Basement
o Install rough in and finish for (29) 6” recessed can fixtures in locations shown on
prints
o Install rough in and finish for (1) chandelier fixture in locations shown on prints
o Install rough in and finish for (8) 4” LED can lights in locations shown on prints
4” can fixtures to match 6” can fixture finish
o Install rough in for (1) pool table chandelier in location shown on prints
Provide and install blank plate on finish
Finish for chandelier to be installed by others
o Install rough in and finish for (12) toggle switches in location shown on drawings
o Install rough in and finish for (6) 3 way toggle switches in locations shown on
prints
o Install rough in and finish for new wall outlets in locations shown on prints
o Provide power supply for the following bar appliances
Refrigerator
Slide in electric range
Garbage disposal with air switch
Dishwasher
Microwave
o Provide low voltage supply for cabinet accent lighting in locations shown on
prints
Final low voltage light layout to be determined following final cabinetry
plan approval
Provide installation of low voltage fixtures
Allowance for (4) puck lights
o Install rough in and finish for (2) 6” recessed can fans in location of bathroom as
shown on prints
o Install all outlets to code
o Run (1) dedicated circuit with disconnect for proposed hot tub in location of
basement sunroom
o Provide power feed for (1) inline booster fan in location shown on prints
Homeowners understand that in order to meet the current code requirements, all
smoke detectors need to be linked through the house. If the existing smoke detectors
are not currently connected to each other and chase the signal throughout the home,
there will be an additional charge to bring detectors up to code requirements. This will
be determined upon a field walk prior to project start.
08/28/18
Mike Sheeks
5 Initials ______ ______
Homeowners understand that all lighting fixtures to be supplied by them, need to be
on site prior to project start in order to avoid any extra charges or delays in
construction
PLUMBING
Bathroom and bar sink drains and supplies are currently roughed in for proposed
locations
Cap existing fireplace gasoline prior to demolition
Cap existing bar sink lines prior to demolition
Run gas line rough in and cap the line to proposed location shown on prints for future
exterior log lighter fireplace valve
Full Bath
o Install rough in for tub shower combo for the following fixtures in locations
shown on prints
72” x 36” alcove tub
Single shower head
Single valve
Tub trim pack
o Install rough in for the following vanity fixtures
Single vanity under mount sink
Single vanity faucet
See cabinet prints for final sizing and dimensions
o Install finish for all bathtub and vanity fixtures following tile installation
o Install toilet following LVT installation
Basement Bar
o Install rough in for bar sink and bar sink faucet in location shown on prints
o Install rough in for dishwasher supply and drain line in location shown on prints
o Install rough in for refrigerator ice maker line in location shown on prints
o Install finish for bar sink and bar sink faucet
Install garbage disposal for bar sink
All plumbing fixtures provided by Custom Living to be from Ferguson.
Homeowners understand that all plumbing fixtures provided by them, need to be
ordered and on site prior to project start to avoid any delays or extra trip charges
Optional Items
Provide and install ejector pump and new ejector pit lid
Provide and install a Marlo 60k water softerner on existing by-pass lines
INSULATION
Foam and Firecaulk all framing and exterior penetrations to meet municipal code
requirements
08/28/18
Mike Sheeks
6 Initials ______ ______
Install 3” Roxul sound deadening insulation in all ceiling joist bays that are exposed from
demolition
DRYWALL, PAINT L&M
Install drywall, tape and mud seams in all necessary areas
o Approx. 8’ Ceilings
Ceiling finish will match the existing ceiling finish in the rest of the basement
o Finish to be Skip Trowel textured finish on all basement ceilings
Drywall patch all areas from demolition and wall framing
Include a drywall patch following countertop installation
All wall finishes will be a level 4 finish and ready for preparation, primer and painting
Optional Pricing
o Install RC channel perpendicular to existing ceiling joist prior to installation of
drywall and 3” Roxul sound deadening insulation
Prime (1) coat and paint (2) coats on all ceilings and walls
o Paint will be Sherwin Williams Duration on the walls, SW Trim Pro-Classic semi-
gloss on the trim and new doors, and SW Eminence flat white on ceiling
o Doors, casing and baseboard will be in semi-gloss white
o Prepare all trim with putty fill in holes, caulk on all joints and sand.
o Sand, stain and finish proposed faux beam and faux beam packouts
Homeowners will need to approve a stain sample prior to staining of
beam goods
TRIM CARPENTRY L&M
Install basement bar cabinets as specified on cabinet prints provided by Cabinet
Company
Install 1x faux beam in location shown on prints
o Beam to be stained on finish
Install 1x boards for faux beam pack out
Build and install (3) floating shelves in location of bathroom as shown on prints using 1x
boards and ½” finish grade plywood
o Shelves to be painted on finish
Install 1x wainscot detail on back of basement bar as shown on prints
Install 1x wrap on basement beams in locations shown on prints
o Beam wrap and wainscot to be painted on finish
Install all interior doors and door hardware shown on prints
o Existing doors to be reused will be rehung prior to installation
Install new baseboard where necessary from framing and demolition.
o Baseboard to match existing profile of the basement
o Baseboard profile – 22168-CB
Install new door casing and window casing where necessary from framing and
demolition
o Match existing profile of the basement
o Casing Profile - TBD
Following LVT flooring installation, install shoe molding throughout the basement
08/28/18
Mike Sheeks
7 Initials ______ ______
FLOORING
Prep subfloor and install LVT flooring in all locations designated on prints
Install all flooring transition pieces as suggested by flooring manufacturer
recommendations
o Current allowance is for floating floor application
o Homeowners understand that the type of flooring selected and the pattern it
gets laid will have an effect on pricing
Install new carpet pad in location of workout room
Stretch and reinstall existing carpet in location of workout room
o Install new 10# carpet pad
Optional Pricing Available for steam cleaning following carpet installation
TILE LABOR AND MATERIAL
Basement Bar
o Prep and install backsplash
Backsplash will go to base of wall cabinets in location of back wall
Power Grout Color: TBD
Tile Material: TBD
Tile Pattern: TBD
Guest Bath
o Prep, waterproof and install shower wall tile
Shower wall tile will go up to the ceiling
Approx. 8’ Ceilings
Allowance for wall tile is for a subway pattern
Power Grout Color: TBD
Tile Material: TBD
Tile Pattern: TBD
Owners understand that the type of tile selected and the pattern the tile gets laid will
affect the final pricing
COUNTERTOPS
Basement Bar
o Template, and install kitchen perimeter countertops
Include (1) sink cutout
No countertop backsplash included in current allowance
Install (5) metal brackets for island countertop support
o Bar Selection; Mont Quartz, Palmetto
o Edge Profile; Double Round Over
Bath
o Template and install vanity countertop
Include (1) sink cutout
08/28/18
Mike Sheeks
8 Initials ______ ______
Current allowance includes a 4” backsplash
o Template for the following guest bathroom solid surface pieces
(1) niche shelf
o Guest Bath Selection; Vintage White Granite
o Edge Profile; Double Round Over
Owners understand that there will be a delay of up to two or three weeks from the date
of countertop template to the date of installation
o During that delay there may not be work being done in the home
o Final paint and drywall touchups will take place following countertop
installation to avoid extra costs in trip charges for drywall repairs
GLASS LABOR AND MATERIAL
No shower glass included in the current scope of work
Provide and install (1) bathroom vanity mirror
APPLIANCES
All appliances to be provided by the homeowners
Appliances need to be selected, ordered, and on site prior to cabinetry installation in
order to avoid any delays or extra trip charges
Appliance installation will be provided by the Homeowners
Kitchen Appliance Model Numbers:
o Slide in Range – Samsung; NE59M4320SG
o Refrigerator – Samsung French Door; RF263BEAESG
o Over the Range Microwave – Samsung; ME18H704
o Dishwasher – Samsung; DW80J3020UB
Remove existing Dishwasher appliance located at the home to install at homeowners
parent’s house
o Remove existing Dishwasher located at parents’ house
o Homeowners understand that the location of the home the dishwasher is to be
installed may have an effect on final pricing
GENERAL CONDITIONS
The Buyer represents and warrants that they are the owner of the premises to be
improved and have the right to improve the same
08/28/18
Mike Sheeks