HomeMy WebLinkAboutProject Scope Outline 9-17-18Wedding Project Outline
Demolition:
Demo requirements for the following removal for existing materials:
NOTE: All material will be carefully disposed into on-site receptacle
Demo and remove drywall and framing for tray ceiling in 1st floor Dining Room
Demo and remove drywall/framing to expose bearing wall to install new beam header in Dining Room
Demo and remove interior wall framing, drywall where required, tub deck, doors and trim per plan
Demo and remove existing shower, tub, plumbing, and electrical fixtures per plan
Demo and remove all existing Bath flooring and carpet from stairs, Hall, Master Suite
Demo and remove vanity top, faucets, and cap off water lines in Hall Bath
Framing:
Labor and materials to frame new 2x4 walls for door openings, vanity, toilet room, and shower bath walls per
plan
Proposed beam work includes structural analysis, labor and materials required to install temporary support
walls, LVL beam from wall removal for Dining / Family Room with visible header per plan
Provide labor and materials to build out Dining Room / Kitchen wall to install larger ductwork to Master Bedroom
/ Bathroom
Exterior Finishes:
Labor and materials required to replace and lace in new T-111 siding, exterior trim, and flashing required
around Bathroom windows
Exterior Door:
Not included in scope of work
Insulation:
Install fire-stop in exterior walls per code requirements, install R-15 batt insulation and foam all joints on exterior
vanity wall for plumbing
Window Schedule:
Window cost based on walk thru and schedule below:
Labor and miscellaneous material cost for all windows installed per plan
Window Schedule:
(1) Architect Series 34"x41" double casement unit above vanity in Master Bath
*NOTE: Window to be installed just above 6" High Dolomite Vanity Backsplash
(1) Architect Series 29"x41" single casement unit in toilet room in Master Bath
(1) Architect Series 20.25" x 45.5" single casement replacement unit in Hall Bath
(Note: Kitchen window is not included)
09/21/18
Mike Sheeks
Plumbing:
MASTER BATH:
Plumbing cost for the following rough-in and finish labor and installation materials:
Cap off existing lines for construction and/or relocation
Labor to connect drain, vent, and water lines for the following:
Master Bath: Install Fixtures: (2) lavatory sink, (2) lavatory faucet, toilet, (2) shower valve/finish trim, shower
rough/finish drain, freestanding soaker tub, floor mounted tub filler valve and finish trim
Hall Bath: Labor and material to install (2) lavatory faucets in Hall Bath for replacement
Hall Bath: Labor and material to install (1) tub/shower finish trim and drain assembly
Site visit to determine if rough in valve can remain, additional labor and materials to remove drywall, install new
tub/shower valve and patch wall for valve replace is not included
Electrical:
Bathroom/Closet:
REVISION: Based on walk thru
2 - Exhaust fan wiring
2 - Vanity light wiring
3 - Closet light wiring
1 - Ceiling light outlet w/ fan support
1 - Install chandelier fixture
4 - 6" Recessed light wiring
1 - 3-way switches installed
7 - Switch outlets installed
2 - Bath GFI outlets and circuits
5 - GFI protected countertop outlets installed
1 - Exhaust fan fixture package
1 - Recessed lighting package
1 - Lutron package
3 - Slim LED ceiling fixture furnished
Bedroom Area:
REVISION: Based on walk thru
1 - Duplex outlet installed
1 - Replace ceiling fan fixture - same location
6 - Remodel 6" recessed lighting, fixtures, and wiring
1 - Fan control outlet installed
1 - 4-way switch installed
09/21/18
Mike Sheeks
1 - Lutron fixture package
Miscellaneous:
Estimated circuits ran into panel
Estimated costs to remove, terminate, and relocate existing wiring
Front Room / Dining Room / Tray Ceiling / Family Room:
REVISION: Based on walk thru
TOTAL Labor and materials
1 - Ceiling light outlet / suitable for fan support
1 - 3 way switching
1 - Install ceiling blank cover plate
HVAC:
HVAC Scope of work based on walk thru for the following work:
Minor relocation of up to (2) two heat runs expected from renovation
Install exhaust fan venting as required with roof termination
HVAC: To install and/or relocate (4) new supply registers dedicated to the Master Bedroom and
Bathroom/Closet due to Dining Room wall removal. Includes upsizing Master Bedroom runs to 8" to provide
more air flow and install dampers in the Basement to control heat in the winter.
Interior Finishes:
Drywall Walls & Ceilings: ALLOWANCE to provide, deliver, stock, and hang interior walls and ceilings in
drywall, taped, sanded, ready for paint
Specific drywall installation and repair Allowance areas include:
Entire master Bathroom, Bedroom, and Closet complete as required by renovation
Minor repair in Hall Bathroom near shower location
Repairs complete in Dining Room ceiling from tray removal
Interior Trim:
Apply new primed wood baseboards and shoe moulding to Bathroom and Bedroom areas per plan, matching
existing profile as close as possible
Apply new primed casing trim to (2) new windows and interior Bath doors per plan. Casing trim is to match the
existing profile as closely as possible
Provide labor and materials to install primed standard colonial crown moulding in Dining Room and Front Living
Room areas to match existing on 2nd level as close as possible
Interior Doors:
Interior Doors: to install door package below:
09/21/18
Mike Sheeks
INTERIOR DOOR PACKAGE:
SELECTED: (3) - Primed 6 panel interior solid core doors with matching door hinges & hardware
(1) Bathroom entry / French Door
(1) Closet entry / French Door
(1) Water closet entry / Swing Door
SELECTED: Door Hardware IN BUDGET
Delany Callan Silona Silona Satin Nickel Lever (similar to exising lever style)
Vanity Cabinetry:
Vanity cabinetry: Labor to install custom cabinetry:
MASTER BATH VANITY CABINETRY PACKAGE:
Vanity Size: 117" Custom Cabinetry, shaker door style, full overlay solid construction. Pricing includes all
accessories and drawer features per plan
SELECTED: A/Co Custom Green City Cabinetry
Door style: 5-panel door and drawer head
Painted White Color: TBD (Snowbound noted)
Maple wood species
Full Overlay door style
Includes: See all details on 5/31 design
Vanity Countertop:
MASTER BATH VANITY TOP & SHOWER PIECES:
DOLOMITE Labor and material to template, fabricate, and installation
SELECTED: 7/25/2018: Global Granite (1) Polished
3CM Color: Dolomite Super White Level G Polished 119"X71"
Edge Profile: Standard Straight/Eased Profile (included), Vanity Splash: 6" high back only in Dolomite
Vanity Faucet: Countertop mount Single Hole
(2) Sinks: Kohler Caxton, K2209-0 U/M White, Vitreous China, Bowl area 15.25" L x 12.25" W x 5.75" D
(1) Shower Threshold Top & (1) Seat Top
HALL BATH:
CEASERSTONE Labor and material to template, fabricate, and installation
SELECTED: 8/20/2018: Global Granite
Color: Ceaserstone Himalayan Moon, Level E Jumbo 1/2 Slab
Edge Profile: Standard Straight/Eased Profile (included), Vanity Splash: 6" High back, left and right
Faucet: Countertop mount Single Hole
(2) Sinks: Kohler Caxton, K2209-96 U/M Biscuit, Vitreous China, Bowl area 15.25" L x 12.25" W x 5.75" D
Total labor and materials: $2,814.00 + $40 sink color upgrade (2) = $2,854.00
09/21/18
Mike Sheeks
Tile Finishes:
BATHROOM: SHOWER FLOOR, WALLS, VANITY WALL:
Complete custom shower: Labor and materials required for custom tile installation scope below:
Shower Floor: install custom concrete mud pan for shower floor, pitch to drain location
Shower Curb: build and install tile to both sides of curb
Shower Walls: install cement tile underlayment and apply waterproofing membrane to shower walls
Shower Walls: labor to install stone or equivalent tile and apply grout for finish
Shower Walls: provide and install schluter trim or bullnose tile to exposed tile edges
Accessories: labor to install shower seat, and install (4) corner shower shelves
Apply cement underlayment and install tile finish to (3) tub walls to approximately 42" height and cap with
matching tile trim
Shower Glass/Panel:
ALLOWANCE to template, provide and install shower panel package below:
Frameless Custom Shower Glass door and two panels with clear glass per plan.
NOTE: top rail is required as currently designed to support the weight of the door at the hinge locations.
Pricing includes standard hardware and integrated towel bar.
Flooring:
Tile: (Stone or equivalent) Master Bathroom
Tile: Install underlayment material to subfloor and install tile flooring per plan (standard pattern)
Additional labor for 12" X 24" Herringbone pattern installation
Tile Flooring Package:
Floor material to be provided by CCG, Inc. @ $4.86/SF, includes setting materials for Master Bathroom
Carpet Material ALLOWANCE: Master Bedroom, Main Hallway, stair step wrap to main level
09/21/18
Mike Sheeks
Other Flooring Requirements:
Labor and material to provide flooring transitions
Labor and material to provide new floor register covers ALLOWANCE
Bath Accessories:
Labor to install owner supplied tp holder, towel bar, cabinet hardware
Labor to install vanity mirrors (2)
Provide (2) Vanity Mirrors, Carmel Glass & Mirror Oval 1" Bevel 2' x 3'
Painting:
Exteriors & Interior Walls & Ceilings: Labor and material to prepare, prime, and paint renovation areas only as
specified below.
Ceilings: Finish: Standard Flat, Color: Standard ceiling white
Walls: Standard eggshell, Color: To be selected by owner prior to drywall finish
Quality and Quantity: Current paint quality level pricing is a level 3 finish (standard quality finish) with SW
Emerald or equivalent product. Level 5 paint finishes are available at additional cost and upon Owner request
ONLY. Additional paint colors selected for multiple walls will result in additional charges and those will be
presented after final walk-through by paint crew foreman once paint color selections are finalized.
Proposed areas to be painted from renovation:
Master Bathroom & Closet - Walls, ceilings, trim, and doors
NOTE: *Master Bath Door color TBD, may decide on stain (slightly darker than existing golden oak)
Master Bedroom - Walls, ceilings, trim, and existing window trim
Existing Dining Room - Walls and ceiling
Existing Family Room - Walls and ceilings from beam installation
Hallway Bathroom - Minor touch up to wall near shower (Owner to provide matching paint)
Exterior - New T-111 siding and trim only - existing unaffected to remain and is not proposed to be painted
(Owner to provide matching exterior paint)
NOTE: Due to the unpredictability of adjacent damages and additional painting that may be required from a
renovation, final painting costs will be reviewed by CCG and Owner will be notified of any differences from
planned costs after paint crew foreman performs a final walkthrough prior to painting.
Clean-up:
Completion of all punch-list items per scope of work and final clean upon project completion
09/21/18
Mike Sheeks
Estimated cost of construction: $95,285
Estimated start date: 10-1-2018
Finished area: 200 SF
Steve & Mary Jo Wedding Residence
5033 St. Charles Place
Carmel, IN 46033
(317) 697-5449
Central Construction Group, Inc.
09/21/18
Mike Sheeks