HomeMy WebLinkAboutMorphey Construction/Eng/CO #4/9,764.03/96th Street and Shelborne Trail – Project #16-ENG-73City of Carmel Project 16 -ENG -73 Shelborne Trail/ 96th Street Trail '700 �o t. CHANGE ORDER #4 Change Order #4 includes the following, Time Extension Request due to INDOT Permit, Relocation of Citizen Water residential service line due to conflict with storm, Structure Modification on Structure 57 due to conflict with pipe size and Additional milling added on Line PR -C from station 28+75 to 34+00. Contract Price prior to this Change Order Contract Price will be increased/decreased by this Change Order New Contract Price including this Change Order $3,853,642.94 $9,764.03 $3,863,406.97 Amount Adjusted Contract Price Cumulative % Change from Original Contract Original Contract $3,652,000.00 $3,652,000.00 N/A CO1 $100,247.97 $3,752,247.97 2.7% CO2 $82,000.00 $3,834,247.97 5% CO3 $19,394.97 $3,853,642.94 5.5% C04 $9,764.03 $3,863,406.97 6.0% CITY OF CARMEL TO: WORK DIRECTIVE CHANGE NO.4 DATE: 9/4/18 PROJECT NAME: Shelborne Trail 961) St. Trail PROJECT NO.: 16 -ENG -73 Specification Reference Time Extension, Water Service, Structure 57 Modification and Additional Milling Drawing Reference: PG. 19-27 DESCRIPTION OF WORK COVERED BY THIS DIRECTIVE CHANGE: A. Morphey has submitted a Time Extension Request for an Additional 41 Calendar Days to be added to the contract. This Request is due to delays in receiving INDOT ROW permits for work on project. (See Attachment A) B. EWA 08 has been submitted for work on a Citizens Water service line that was in conflict with the storm sewer on Line PR -C Station 31+70. The Additional work is for boring and new line to the meter and attaching to the existing meter. The additional cost to the project is $4,500.00 and 3 additional calendar days added to the contract. (See Attachment B) C. EWA 07 has been submitted for Structure Modification completed in the field due the size of the pipe was a 30"00" box under 961 street instead of the 30" CMP at the outflow. The additional cost to the contract is $1,614.03 and 1 additional calendar day added to the contract. (See Attachment Q. D. EWA 10 has been submitted for Added Milling on Line PR -C from station 28+75 to station 34+00. The additional cost to the contract is $3,650.00 and 1 additional calendar day added to the contract. (See Attachment D). REASON FOR THIS ORDER: A. Time request due to INDOT ROW PERMIT delays. B. Relocate Citizens Water residential service line due to conflict. C. Structure Modified due to unforeseen pipe size change. D. Additional Milling added on Line PR -C. AUTHORIZATION: THIS WORK DIRECTIVE CHANGE AUTHORIZES THE WORK TO BE COMPLETED AS OUTLINED. A Contract Change Order in the Amount of $ 9,764.03 will be issued to you in the near future to cover this Work Directive Change. PROJECT COMPLETION DATE: ADD/DEDUCT/UNCHANGED 46 DAYS. AR -3 Version 2016-08-31 By: Approved By: Robert Surber (BFS) ATTES Kristine S. Pauley, Clerk -Treasurer AR -3 Version 2016-08-31 CITY OF CARMEL BOARD OF PUBLIC WORKS AND SA' By: / � d James Brainard, MA Mary By: Lori �Jatso , Member By: Jerem;�0�1 , y Engineer DATE: DATE: /0 —3 _ l Attachment "A" August 28, 2018 Jeremy L. Books, PE, CPESC Construction Department Manager Butler, Fairman & Seufert, Inc. 8450 Westfield Blvd., Suite 300 Indianapolis, IN 46240-8302 Re: Delay Claim, Time Extension Request, 08-28-18 Revisions Contract 16 -ENG -73 — Shelborne and 96th Street Trails MORPHEY CONSTRUCTION Reference to: Delay Claim, Time Extension Request, 07-23-18 Submittal No. 26 — Project Schedule, Updated 08-28-18 (Attached) Dear Mr. Books, During our 08-27-18 progress meeting, the City of Camel indicated that verbal approval will be provided for the 55 Days requested in our 07-23-18 request letter less the 14 calendar days Morphey Construction, Inc. (MCI) mobilized off the project from 05-16-18 through 05-29-18. In light of these discussions, MCI would request adding 41 calendar days to the following substantial and final completion dates: Shelborne Road Trail, from Inverness Boulevard to 106"' Street Substantial Completion: Work Completed — No Change Shelborne Road Trail, from 96t6 Street to Inverness Boulevard Substantial Completion: +41 Calendar Days 96th Street Trail from Michigan Road to Ditch Road Substantial Completion: +41 Calendar Days Final Completion, all Sections: +41 Calendar Days This 41 calendar day request accounts for the delays experienced while INDOT ROW permits were being issued for the Michigan Road intersection included in our Contract. In addition to this 41 calendar day request, 10 additional calendar days have been previously requested in pending extra work agreements (EWA 07 -10). Provided this information, our Contract's substantial and final completion dates would be summarized as follows: Shelborne Road Trail, from Inverness Boulevard to 1061h Street Substantial Completion: December 15, 2017 Shelborne Road Trail, from 961h Street to Inverness Boulevard Substantial Completion: 10/30/18 + 41 CD + 30 CD (EWA 7 —10)* = December 20, 2018 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 fx: 317.35.9253 www.morpheyconstruction.com 961h Street Trail from Michigan Road to Ditch Road Substantial Completion: 10/30/18 + 41 CD + 30 CD (EWA 7 —10)* = December 20, 2018 Final Completion, all Sections: 11/26/18 + 41 CD + 10 CD (EWA 7 — 30)* = January 16, 2019 *Includes the following pending time extensions: EWA 07 — 5 CD, EWA 08 — 3 CD, EWA 09 —1 CD, EWA 30 —1 CD. Total 10 CDs For your reference, we have attached an updated project schedule showing the anticipated December 20, 2018 substantial completion dates. Please see attached Submittal No. 26 — Project Schedule, Updated 08-28-18. Sincerely, Morphey Construction Inc. Jason Umlauf l!// Project Manager p. 1-317-356-9250 m. 1-317-766-3951 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 fx: 317.35.9253 www.morpheyconstruction.com 0 MORPHEY CONSTRUCTION Submittal September 5, 2018 To: Attention: Project Engineer/Project Supervisor City of Carmel 16 -ENG -73, Shelborne Rd. and 96th One Civic Square Re: St. Trails Carmel, Indiana 46032 Job Number: ® Attached 10 ❑ Shop Drawings ❑ Copy of Letter ❑ Total Quantity Submittal Quantity We are transmitting Under Separate Cover via: [Type text here] the following: Prints ❑ Plans ❑ Other: Change Order ❑ Samples Reproducible ❑ Specification Date DWG. # rtncrrin}inn These are transmitted as checked below ❑ For Approval ❑ ® For Your Use ❑ ❑ As Requested ❑ Approved as Submitted ❑ Approved as Noted ❑ Returned for Corrections ❑ Resubmit copies for approval Submit [#] copies for distribution Return [#] corrected prints ❑ For Review and Comment ❑ Revise and Resubmit/Work ❑ FOR BIDS DUE: ❑ May Not Proceed PRINTS RETURNED AFTER LOAN Comments: Copy to: Morphey Construction Inc Signature 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 Fx: 317.356.9253 www.morpheyconstrucction.com 16 -ENG -73 Shelbome Rd. & 96th St. Trails Created: 08-28-17 Updated: 08-28-18 Morphey Construction, Inc. Substantial Completion: 12-20-18 Final Completion: 01-16-19 ID Task Name IDuration Istart lFinish lResource Names 1 Administrative Bid Date Award Date Notice to Proceed Precon Meeting Shop Drawings - Box Shop Drawings - Strs Shop Drawing Review- Box Shop Drawing Review - Strs Fabricate - Box Fabricate - Strs Field Office Setup Utilities - Shelborne Rd Utilities - Une "PR -A" Utilities - Line "PR -B" Utilities - Line "PR -C' Utilities AT&T Distribution Carmel Water Charter Communications Citizens Energy Group - Gas Citizens Energy Group - Water CTRWD Comcast Duke Energy Transmission Hamilton County Surveyors IPL Level 3 Communications Lightower MCI-Verison Metronet Vectren Gas Zayo Bandwidth Construction - Shelbome Rd., Inverness Blvd. to 106th St, Construction Signs Staking Clearing - Shelborne and 96th Erosion Control Removals Storm Sewers Common Ex. C&G Prep C&G Install Conc Prep - Dives and Ramps Drive and Ramps Install Subgrade Treatment Subbase Milling HMA Paving Final Restoration Seeding Construction - Line "PR -A" and 96th/Michigan Rd. Intersection Construction Signs - 96th/Michigan MOT Staking Removals Hydrant Relocation Storm Sewers Concrete Prep - Curbramps and Drives Concrete Drive, Curb, and Sidewalk Compacted Aggregate/HMA Prep HMA Paving Seed/Sod Prep Final Seeding Pavement Markings Final Restoration Signal Work 49 days 1 day 1 day 1 day 1 day 5 days 5 days 5 days 5 days 28 days 5 days 15 days 0 days 0days 0days 0 days 0 days 0days 0 days 0 days 0 days 0 days 0days 0 days 0 days 0 days 0 days 0 days 56 days 1 day 2 days 6 days 1 day 1 day 5 days 7 days 2 days 2 days 2 days 3 days 7 days 7 days 1 day S days 7 days 2 days 189 days 1 day 1 day 10 days 2 days 5 days 8 days 10 days S days 5 days 5 days 5 days 5 days 19 days 104 days Wed 8/16/17 Wed 8/16/17 Wed 8/23/17 Wed 8/30/17 Wed 8/30/17 Thu 8/31/17 Thu 8/31/17 Thu 9/7/17 Thu 9/7/17 Thu 9/14/17 Thu 9/14/17 Thu 8/31/17 Tue 9/5/17 Tue 9/5/17 Wed 9/6/17 Fri 9/8/17 Mon 9/18/17 Tue 9/19/17 Wed 9/20/17 Wed 9/27/17 Fri 10/6/17 Tue 10/10/17 Tue 10/10/17 Thu 10/12/17 Thu 10/12/17 Mon 10/23/17 Wed 11/1/17 Thu 11/2/17 Thu 11/9/17 Mon 11/20/17 Mon 4/2/18 Mon 4/2/18 Mon 4/2/18 Mon 9/10/18 Mon 9/24/18 Wed 9/26/18 Wed 10/3/18 Mon 10/8/18 Mon 10/15/18 Mon 10/22/18 Mon 11/19/18 Mon 11/26/18 Mon 11/19/18 Mon 11/26/18 Mon 7/30/18 Mon 10/23/17 Wed 8/16/17 Wed 8/23/17 Wed 8/30/17 Wed 8/30/17 Wed 9/6/17 Wed 9/6/17 Wed 9/13/17 Wed 9/13/17 Mon 10/23/17 Wed 9/20/17 Wed 9/20/17 Tue 11/21/17 Tue 9/5/17 Thu 9/7/17 Fri 9/15/17 Mon 9/18/17 Tue 9/19/17 Tue 9/26/17 Thu 10/5/17 Mon 10/9/17 Wed 10/11/17 Wed 10/11/17 Mon 10/16/17 Fri 10/20/17 Tue 10/31/17 Wed 11/1/17 Wed 11/8/17 Fri 11/17/17 Tue 11/21/17 Thu 12/20/18 Mon 4/2/18 Mon 4/2/18 Fri 9/21/18 Tue 9/25/18 Tue 10/2/18 Fri 10/12/18 Fri 10/19/18 Fri 10/19/18 Fri 10/26/18 Fri 11/23/18 Fri 11/30/18 Fri 11/23/18 Thu 12/20/18 Thu 12/20/18 Utility Clear Date - 09-15-17 Utility Clear Date - 11-15-17 Utility Clear Date - 03-01-17 Utility Clear Date - 03-01-17 Delay on Line "S -PR -1-A" Substantial Completion: 12-15-17 Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Substantial Completion: 12-20-18 Complete SurveyTech MCI - Pipe/Prep MCI - Pipe/Prep MCI - Pipe /Prep MCI - Pipe/Prep Harmon MCI - Pipe/Prep Midwest Paving MCI - Pipe/Prep Earth Images ITS MCI - Pipe/Prep MCI - Elec. 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 Page 1 16 -ENG -73 Shelbome Rd. & 96th St. Trails Created: 08-28-17 Updated: 08-28-18 Morphey Construction, Inc. Substantial Completion: 12-20-18 Final Completion: 01-16-19 ID Task Name IDuration IStart lFinish iResource Names 73 Construction -106th/Michigan Rd. Intersection Construction Signs - 106th/Michigan MOT Ph 1 Staking Removals - Ph 1 Common Excavation Compacted Aggregate/HMA Prep HMA Paving Concrete Prep Concrete Ramps and Sidewalk MOT Change - 106th/Michigan MOT Ph 2 Removals - Ph 2 Concrete Prep Concrete Ramps and Sidewalk Seed/Sod Prep Final Seeding Pavement Markings - Multi -Component Final Restoration Signal Work Construction - Towne Rd. and Firestone lane Preclosure Signs Construction Signs - Towne/Firestone MOT & Closure Construction Engineering Erosion Conrol Clearing R/W Removals Storm Sewers Curp Prep Concrete Curb Sidewalk and Ramp Prep Concrete Walks and Ramps Milling and HMA Prep HMA Paving Final Restoration Pavement Markings Landscaping Construction - Shelborne Rd., 96th St. to Inverness Blvd. Construction Signs Staking Clearing Erosion Control Install Box Extension Removals Storm Sewers Hydrant Relocation Concrete Prep - C&G C&G Installation Concrete Prep - Curbramps and Drive Drive and Ramp Installation Common Ex. Subgrade Treatment Subbase Milling HMA Paving Seed/Sod Prep Final Seeding Pavement Markings Final Restoration Construction - With Street, Ln "PR -B" Construction Signs Staking Clearing Erosion Control Removals Storm Sewer and Water Main Storm Sewers - Laterals Concrete Prep - Curbramps and Drives Drive and Ramp Installation Common Ex. Sub rade Treatment 189 days? 1 day 1 day 5 days 5 days 5 days 15 days 5 days 5 days 1 day 5 days 5 days 5 days 5 days 5 days 5 days 9 days 104 days 27 days 10 days 1 day 1 day 1 day 1 day 1 day 1 day 1 day 2 days 2 days 2 days 2 days 2 days 1 day 1 day 2 days 189 days 1 day 1 day 1 day 1 day 2 days 4 days 10 days 1 day 5 days 5 days 5 days 10 days 40 days 40 days 40 days 2 days 5 days 15 days 5 days 5 days 19 days 264 days? 1 day 1 day 2 days 1 day 1 day 165 days 25 days 20 days 25 days 55 days 55 days Mon 4/2/18 Mon 4/2/18 Mon 4/2/18 Mon 10/22/18 Mon 10/29/18 Mon 11/5/18 Mon 10/29/18 Mon 11/12/18 Mon 11/12/18 Mon 11/19/18 Mon 11/19/18 Mon 11/26/18 Mon 11/26/18 Mon 12/3/18 Mon 12/10/18 Mon 12/10/18 Mon 12/10/18 Mon 7/30/18 Tue 5/1/18 Tue 5/1/18 Mon 5/14/18 Mon 5/14/18 Mon 5/14/18 Mon 5/14/18 Tue 5/15/18 Wed 5/16/18 Thu 5/17/18 Fri 5/18/18 Fri 5/18/18 Tue 5/22/18 Tue 5/22/18 Thu 5/24/18 Mon 5/28/18 Mon 6/4/18 Tue 6/5/18 Mon 4/2/18 Mon 4/2/18 Mon 4/2/18 Mon 5/14/18 Mon 5/14/18 Mon 7/16/18 Mon 8/6/18 Fri 8/10/18 Fri 8/24/18 Mon 8/27/18 Mon 9/3/18 Mon 9/3/18 Mon 9/24/18 Mon 8/27/18 Mon 8/27/18 Mon 8/27/18 Mon 10/22/18 Mon 10/22/18 Mon 10/22/18 Mon 11/12/18 Mon 11/19/18 Mon 11/26/18 Mon 12/18/17 Mon 4/2/18 Mon 4/2/18 Mon 4/2/18 Mon 4/2/18 Mon 4/2/18 Mon 12/18/17 Mon 9/17/18 Mon 8/20/18 Mon 8/20/18 Mon 8/6/18 Mon 8/6/18 Thu 12/20/18 Mon 4/2/18 Mon 4/2/18 Fri 10/26/18 Fri 11/2/18 Fri 11/9/18 Fri 11/16/18 Fri 11/16/18 Fri 11/16/18 Mon 11/19/18 Fri 11/23/18 Fri 11/30/18 Fri 11/30/18 Fri 12/7/18 Fri 12/14/18 Fri 12/14/18 Thu 12/20/18 Thu 12/20/18 Wed 6/6/18 Mon 5/14/18 Mon 5/14/18 Mon 5/14/18 Mon 5/14/18 Mon 5/14/18 Tue 5/15/18 Wed 5/16/18 Thu 5/17/18 Mon 5/21/18 Mon 5/21/18 Wed 5/23/18 Wed 5/23/18 Fri 5/25/18 Mon 5/28/18 Mon 6/4/18 Wed 6/6/18 Thu 12/20/18 Mon 4/2/18 Mon 4/2/18 Mon 5/14/18 Mon 5/14/18 Tue 7/17/18 Thu 8/9/18 Thu 8/23/18 Fri 8/24/18 Fri 8/31/18 Fri 9/7/18 Fri 9/7/18 Fri 10/5/18 Fri 10/19/18 Fri 10/19/18 Fri 10/19/18 Tue 10/23/18 Fri 10/26/18 Fri 11/9/18 Fri 11/16/18 Fri 11/23/18 Thu 12/20/18 Thu 12/20/18 Mon 4/2/18 Mon 4/2/18 Tue 4/3/18 Mon 4/2/18 Mon 4/2/18 Fri 8/3/18 Fri 10/19/18 Fri 9/14/18 Fri 9/21/18 Fri 10/19/18 Fri 10/19/18 Substantial Completion: 12-20-18 Complete SurveyTech MCI - Pipe/Prep MCI - Conc. Prep MCI - Pipe/Prep Midwest Paving MCI - Pipe /Prep Harmon ITS MCI - Pipe /Prep MCI - Pipe/Prep Harmon MCI - Pipe /Prep Earth Images ITS MCI - Conc. Prep MCI - Elec. Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Substantial Completion: 12-20-18 Complete Complete 50% Complete Earth Images Complete Complete Complete Complete MCI - Pipe/Prep Natural MCI - Pipe/Prep Harmon MCI - Dirt MCI - Dirt MCI - Dirt MCI - Milling Midwest MCI Dirt Earth Images ITS MCI - Conc. Prep Substantial Completion: 12-20-18 Complete Complete Complete Complete Complete MCI - Pipe MCI - Conc. Prep MCI - Conc. Prep Harmon MCI - Dirt MCI - Dirt 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 % 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 Page 2 16 -ENG -73 Morphey Construction, Inc. Substantial Completion: 12-20-18 Shelbome Rd. & 96th St. Trails Final Completion: 01-16-19 Created: 08-28-17 Updated: 08-28-18 ID Task Name IDuration IStart IFinish lResource Names 145 Subbase SS days Mon 8/6/18 Fri 10/19/18 MCI - Dirt 146 Milling 2 days Mon 10/22/18 Tue 10/23/18 MCI - Milling 147 HMA Paving 5 days Mon 10/22/18 Fri 10/26/18 Midwest Paving 148 Seed/Sod Prep 15 days Mon 10/22/18 Fri 11/9/18 MCI - Dirt 149 Final Seeding 5 days Mon 11/12/18 Fri 11/16/18 Earth Images 150 Pavement Markings 5 days Mon 11/19/18 Fri 11/23/18 ITS 151 Final Restoration 19 days Mon 11/26/18 Thu 12/20/18 MCI - Conc. Prep 152 153 Construction - 96th Street, Ln "PR -C" 189 days Mon 4/2/18 Thu 12/20/18 Substantial Completion: 12-20-18 154 Construction Signs 1 day Mon 4/2/18 Mon 4/2/18 Complete 155 Staking 1 day Mon 4/2/18 Mon 4/2/18 Complete 156 Clearing 3 days Mon 5/14/18 Wed 5/16/18 90% Complete 157 Relocate Masonry Wali 10 days Thu 5/17/18 Wed 5/30/18 Complete 158 Road Closure MOT 1 day Mon 6/18/18 Mon 6/18/18 Complete 159 Erosion Control 1 day Mon 6/18/I8 Mon 6/18/18 Complete 160 Storm Sewers during Road Closure MOT 10 days Tue 6/19/18 Mon 7/2/18 Complete 161 One-way MOT 1 day Fri 6/29/18 Fri 6/29/18 Complete 162 Storm Sewers One -Way Closure 34 days Tue 7/3/18 Fri 8/17/18 Complete 163 Storm Sewers - Laterals 20 days Mon 8/20/18 Fri 9/14/18 Complete 164 Concrete Prep - Curbramp & Drives 5 days Mon 7/30/18 Fri 8/3/18 MCI - Conc. Prep 165 Drive and Ramp Installation 30 days Mon 8/6/18 Fri 8/17/18 Harmon 166 Concrete Prep - C&G 10 days Mon 8/6/18 Fri 8/17/18 MCI - Conc. Prep 167 C&G Installation 10 days Mon 8/20/18 Fri 8/31/18 Natural 168 Trim Milling 4 days Mon 9/3/18 Thu 9/6/18 MCI 169 HMA Structure Installation 5 days Fri 9/7/18 Thu 9/13/18 MCI/Midwest 170 End One-way MOT 1 day Fri 9/14/18 Fri 9/14/18 ITS 171 Common Ex. 50 days Mon 8/6/18 Fri 10/12/18 MCI - Dirt 172 Subbase 50 days Mon 8/6/18 Fri 10/12/18 MCI - Dirt 173 Subgrade Treatment 50 days Mon 8/6/18 Fri 10/12/18 MCI - Dirt 174 Milling 2 days Mon 10/15/18 Tue 10/16/18 MCI - Milling 175 HMA Paving 5 days Mon 10/15/18 Fri 10/19/18 Midwest Paving 176 Seed/Sod Prep 15 days Mon 10/22/18 Fri 11/9/18 MCI - Dirt 177 Final Seeding 5 days Mon 11/12/18 Fri 11/16/18 Earth Images 178 Pavement Markings 5 days Mon 11/19/18 Fri 11/23/18 ITS 179 Final Restoration 19 days Mon 11/26/18 Thu 12/20/18 MCI - Conc. Pre Page 3 Attachment "B" June 28, 2018 Jeremy L. Books, PE, CPESC Construction Department Manager Butler, Fairman & Seufert, Inc. 8450 Westfield Blvd., Suite 300 Indianapolis, IN 46240-8302 Re: EWA 08 — Water Service, Far Side, Citizens Water In Reference to: Verbal RFP for Relocating Citizens Water Services &I While installing the proposed storm sewer improvement on Line "PR -C" a Citizens Energy Group (CEG) water service was found to be in conflict at —Sta. 31+70 Ln "PR -C". The service line was temporary spliced around our Contract's storm sewer improvement. However, CEG does not allow permanent splices and requires a new service line from the water main to the meter pit. Per our verbal discussions, Morphey Construction Inc. proposes boring a new service line across 96th street to make the proper repairs. We would like to add the following work to our Contract at the stated unit price. EWA 08a — Water Service, Bored Far Side, Citizens Water ............................... This includes: Boring 1" Copper Tubing Connection to Watermain Connection to existing Meter Pit Backfill and Restoration Total Increase to our Contract: $4,500.00 1 EACH @ $4500.00/EACH Totaling: $4,500.00 This work will add —2 work days to our Contract's controlling operation. Morphey Construction Inc. would like to add 3 calendar days to our Contract's substantial and final completion dates for this added work. Please see attached cost summary for your records. If you need any additional information, please let us know. Sincerely, Morphey Construction Inc. Jason Umlauf Project Manager p. 1-317-356-9250 m.1-317-766-3951 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 fx: 317.35.9253 www.morpheyconstruction.com July 19, 2018 Jeremy L. Books, PE, CPESC Construction Department Manager Butler, Fairman & Seufert, Inc. 8450 Westfield Blvd., Suite 300 Indianapolis, IN 46240-8302 Re: EWA 09 — Structure Modification, Str. No. 57 (T&M) On 07-07-2018, while excavating for Str. No. 57, the existing downstream pipe run was found to be a 30" x 30" concrete box. The plans had shown an existing 30" CMP and the precast structure was built accordingly. Str. No. 57 was modified to connect to the existing 30" x 30" concrete box and T&M was tracked to complete this connection. I light of the above described, Morphey Construction Inc. would like to add the following work to our contract: EWA 09a — Structure Modifications, Str. No. 57 ................................................. 1 LS @ $1,614.03/LS Totaling: $1,614.03 Total Increase to our Contract: $1,614.03 This work delayed our controlling operation by "'1 work day. Morphey Construction Inc. would like to add 1 calendar days to our Contract's substantial and final completion dates for this added work. Please see attached cost summary for your records. If you need any additional information, please let us know. Sincerely, Morphey Construction Inc. 9J"asoonUmlaauf Project Manager p. 1-317-356-9250 m. 1-317-766-3951 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 fx: 317.356.9253 www.morpheyconstruction.com T&M FORM tFJNI,I ii1",I`1N MCI Job N 3060 Customer: Date: —7 / PROJECT: 16 —r✓1 G— 7 3 `J'6 f P/�OV�n�7r�;/' l lm 13 ) 4 9— 7 WORKTAS K:S-.161i(�L/-/'-T i-/7`'oCs X 3'xra�:�u/ &,7'3O`x30`laaacPR—(P -57k ,-5- EQUIPMENT LABOR +>TI T. 11L „+ 10-.I GESGInIn� —11, l� !/ _ _ Ort/l M z I a i I MATERIALS & SUPPLIES ouA„nn rl* , I I I SMALL EQUIPMENT XO P1'^ """s •un TRUCKING CO. „w■s .1 T■u AIRCOMPRESSOR ENERATDR [7� -UTE CUMPACTCR ap -EMO SAW IANHAMMER - DISPOSAL atilt ' * IOJoS -� Q XS/ 7 SUBCONTRACTORS EQUIPMENT FUEL •P1LO4 Mob/Demob "1T" MOORSOS°° ADMINISTRATION WT MOB (Ptl H—) >OMINISTRA'I(?N GEE OT UFMOB IPrr Nuu,l f Total: Morphey onstruction, Inc. CJI Printed: i�►l jl � t � i Title: iz'&Pec-r July 24, 2018 Jeremy L. Books, PE, CPESC Construction Department Manager Butler, Fairman & Seufert, Inc. 8450 Westfield Blvd., Suite 300 Indianapolis, IN 46240-8302 Re: EWA 10 — Added Trim Milling, Line "PR -C" Additional trim milling has been requested on Line "PR -C" from — Sta. 28+75 to Sta. 34+00 with an estimated area of 146 SYS. Our contract added a similar item with similar quantity through Change Order No. 2. Morphey Construction would like to add the following work to our Contract: Item No. 0143 — MILLING, ASPHALT, 11/2 IN.............................146 SYS @ $25.00/SYS Totaling: $3,650.00 Total Increase to our Contract: $3,650.00 This work will delay our controlling operation by —1 work day. Morphey Construction Inc. would like to add 1 calendar day to our Contract's substantial and final completion dates for this added work. Please see attached cost summary for your records. If you need any additional information, please let us know. Sincerely, Morphey Construction Inc. 9000 &IOV l�T;1� Jason Umlauf Project Manager p. 1-317-356-9250 m.1-317-766-3951 1499 N Sherman Drive Equal Opportunity Employer Indianapolis, IN 46201-1515 ph: 317.356.9250 fx: 317.356.9253 www.morpheyconstruction.com Memo To: Doug Haney, Corporation Counsel From: Lisa Scott CC: Jeremy Kashman Date: 09/21/18 Re: C.O. #4 91P Street and Shelborne Trail Project #16 -ENG -73 Doug, please find attached 1 original of same change order for project #16 -ENG -73 96"' Street and Shelborne Trail project. Please review & initial for the next BPW Meeting. Change Order #4- Original Contract Amount: $3,652,000.00 Increase: $9,764.03 New Contract Amount $3,863,046.97 Thank you, Lisa Scott 0 Page 1