CHANGE ORDER #7
During the installation of the storm structures and pipe throughout the project, minor conflicts were
discovered with several of the utility facilities located within the project limits. The unknown location and
elevation of the Carmel Sanitary Force main required adjustments at 3 locations on the north side. As well
as an unmarked pipe found on the north side required determining if the facility was abandoned and could
be removed. An IPL duct bank on the south side, that was to be clear, required adjustments at 4 locations.
Also, due to the location of an existing fire hydrant, the BMP structure required adjustment for the safety
of the workers to use a trench box and the public to not shut the hydrant down. These necessary adjustments
posed additional costs to Fox Contracting and were made in order avoid any delay conflicts and to meet the
time constraints of the project. The costs and general remarks regarding each individual incident have been
included as part of this change order.
Contract Price prior to this Change Order $1,609,642.42
-----------------------------------------------------------------------------------------
Contract Price will be increased/decreased by this Change Order $ 22,739.81
New Contract Price including. this Change Order $1,632,382.23
Amount
Adjusted Contract
Cumulative % Change
Price
from Original Contract
Original Contract
$1,588,508.79
$1,588,508.79
N/A
C01— Const Chng 1
$(4,164.65)
$1,584,344.14
(0.3%)
Storm Water Bond
CO2 — MM Add Insured
$0.00
$1,584,344.14
(0.3%)
General Oblig. Bond
CO 3 — Const Chng 2
$5,111.10
$1,589,455.24
0.06%
General Oblig. Bond
CO 3 — Const Chag 2
$3,250.34
$1,592,705.58
0.3%
Storm Water Bond
CO 4 — Temp Const.
Fence and New Fence
$9,288.12
$1,601,993.70
0.85%
General Oblig. Bond
CO 5 — Added Turn
$7,126.62
$1,609,120.32
1.30%
Lane at Gray Rd
General Oblig. Bond
CO 6 — Straw Blanket
$522.10
$1,609,642.42
1.33%
w/ U Seed
General Oblig. Bond
CO 7 — Fox Additional
$22,739.81
$1,632,382.23
2.76%
Costs for Utility
Conflicts
Storm Water Bond
CITY OF CARMEL
TO: CONTRACT CHANGE ORDER NO.: 7
Chris Ogg DATE: 8/30/18
One Civic Square PROJECT NAME: 16 -ENG -35
Carmel, IN 46032 CITY REQ. NO.: N/A
CITY PO NO.: 100637 - Storm Water Bond
CITY PO DATE: 8/9/2017
I. You are directed to make the following changes in this Contract:
(Brief Description)
During the installation of the stone structures and pipe throughout the project, minor conflicts were
discovered with several of the utility facilities located within the project limits. The unknown location and
elevation of the Cannel Sanitary Force main required adjustments at 3 locations on the north side. As well
as an unmarked pipe found on the north side required determining if the facility was abandoned and could
be removed. An IPL duct bank on the south side, that was to be clear, required adjustments at 4 locations.
Also, due to the location of an existing fire hydrant, the BMP structure required adjustment for the safety
of the workers to use a trench box and the public to not shut the hydrant down. These necessary adjustments
posed additional costs to Fox Contracting and were made in order avoid any delay conflicts and to meet the
time constraints of the project. The costs and general remarks regarding each individual incident have been
included as part of this change order.
SCHEDULED ADJUSTMENT
ITEM AMOUNT H OR O DAYS
New 114 — Fox Additional Costs For $22,739.81 0
Utility Conflict Adjustments
Il. The following referenced Documents further describe the changes outlined in Paragraph I, and
are to be considered a part of this Change Order: R.F.P.: N/A W.D.C. No.: N/A
Other:
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $_1,609,642.42
Contract Price will be increased/decreased by this Change Order $_ 22,739.81
New Contract Price including this Change Order $_1,632,382.23
Contract Time Prior to this Change Order 74 Days 12/13/17 Completion Date
Net increased/decreased resulting from this Change Order 0 Days
Current Contract Time including this Change Order 74 Days 12/13/17 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
Version 2016-08-31
The Above Changes Are
Recommended
CHA
The Above Changes Are
Accepted:
Rieth-Riley Construction
ENGINEER CONTRACTOR gsB
300 S. Meridian Street 1751 W. Minnesota Street
Address Address Nlary 1
Indianapolis, IN 46225 Indianapolis, IN 46221
City/State/Zip
By: rz
Phone: 3f7-407-S760—
Date:
f7-407-37 0
Date: 91271f8
Version 20164)8-31
Approved:
Member
Member
City/State/Zip Jere dslAan,—P-f.—City
weer
A
�v,
Phone:_ - • �S4
�C—
'--Christine S. P uley, Clerk
Treasurer
Date: ��J�6 Date: A)//7/�f-
j
IETHIMILEY CoNsmucnoN Co., INc.
100% Quality • 100% Employee Owned • Over 100 Years
LETTER OF TRANSMITTAL
TO: CHA Companies DATE: 8/30/18 (REV 9.4.18)
300 S. Meridian St
Indianapolis, IN 46225 PROJECT: 16 -ENG -35 961" & Hazel Dell
JOB #: RR Job# 3200723
ATTN: Brian Andres RE: Structure Modifications (REVISED)
We Are Sending:
Shop Drawings
Letter
Prints/Plans
X Change Order
Samples
Specifications
Other:
Notes/Remarks:
Submitted For:
X Approval
Your Use
As Requested
Review and Comment
Sent Via: Email
X Attached
Separate Cover Via:
Action Taken:
Approved as Submitted
Approved as Noted
Returned After Loan
Resubmit Copies
Submit Copies
Returned
Returned for Corrections
Due Date:
The following pricing is based upon the revised projects costs due to structure modifications required by
existing utility conflicts.
Item Description
I Quantity I
Unit I
Unit Price
Extension
EWA ISTRUCTURE MODIFICATIONS
1 1.00 1
LS 1
$22,739.81
$22,739.81
CC: 3200723 - Job File
Eric Holmes, RR Superintendent
Chris Ogg PE, Carmel Asst. City Engineer
Signed:
Jeff M � , . Project Manager
P.O. Box 276 •1751 W. Minnesota St. • Indianapolis, IN 46206 Phone: (317) 634-5561 • www.rieth-riley.com
RIETH-RILEY CONSTRUCTION
EXTRA WORK AGREEMENT
DATE: 8/30/18 Work Performed: Structure Modifications for Utility Conflicts (REVISED)
CONTRACT: 3200723 PROJECT: 16 -ENG -35 96th & Hazel Dell Parkway Improvements
FORCE ACCOUNT/EXTRA WORK FOR
LABOR 109.05 (b)(1)
Hn( IRS
EMPLOYEE
Regular Overtime Doubletime TOTAL
RATE
EXTENSION
CARPENTER
0.00
$2749
$0.00
CARPENTER FOREMAN
0.00
$28.99
$0.00
COMBINATION
0.00
$29.76
$0.00
FINISHER
0.00
$25.72
$0.00
FOREMAN
1 0.00
$3505
$0.00
LABORER
0.00
$24.72
$0.00
MECHANIC
0.00
$35.05
$0.00
OPERATOR (103)
0.00
$34.05
$0.00
OPERATOR (841)
0.00
$32.55
$0.00
OPERATOR OILER (103)
0.00
$29.91
$0.00
CA TECH
0.00
$24.72
$0.00
SUPERINTENDENT/PROJECT MANAGER
0.00
$44 05
$0.00
TEAMSTER
0.00
$28.41
$0.00
FRINGES
TOTAL LABOR $0.00 (2)
FICA 7.50 x LINE (2) $0.00 (3)
EMPLOYEE
HOURS
% X LINE (2)
RATE
EXTENSION
CARPENTER
000
X
$21 25 =
$0.00
CARPENTER FOREMAN
0.00
x
$21.25 =
$0.00
COMBINATION
0.00
X
$1491 =
$0.00
FINISHER
0.00
X
$13.96 =
$0.00
FOREMAN
0.00
X
$17.66 =
$0.00
LABORER
0.00
X
$1396 =
$0.00
MECHANIC
0.00
X
$17.66 =
$0.00
OPERATOR (103)
0.00
X
$17.66 =
$0.00
OPERATOR (841)
0.00
X
$2051 =
$0.00
OPERATOR OILER (103)
0.00
X
$17.66 =
$0.00
CA TECH
0.00
X
$13.96 =
$0.00
SUPERINTENDENT/PROJECT MAN
0.00
X 1
$1766 =
$0.00
TEAMSTER 1
0.00
1 X 1
$14.91 =
$0.00
TOTAL FRINGES $0.00 (4)
WORKERS COMPENSATION
5.72
% X LINE (2)
$0.00 (5)
BODILY INJURY / PROPERTY DAMAGE INSURANCE
5.80
% X LINE (2)
$0.00 (6)
STATE UNEMPLOYMENT
3.85
% X LINE (2)
$0.00 (7)
FEDERAL UNEMPLOYMENT
0.40
% X LINE (2)
$0.00 (8)
TRAVEL ALLOWANCE OR SUBSISTENCE (NOTE #3)
$0.00 (9)
TOTAL LINES 2, 3, 4, 5, 6, 7, 8 & 9
$0.00 (10)
10 % x LINE (10)
$0.00(11)
GRAND TOTAL LABOR LINES (10) + (11)
$0.00(12)
Page 1 of 2
MATERIAL 109.05 (b)(3)
Purchased or
Manufactured Description Quantity Unit Unit Price
Extenstion
EXTENSION
(25)
a
$
s
s
$
$
s
$
Is
I $
MATERIALS PURCHASED
MATERIALS MANUFACTURED
TOTAL. LINE (18) + (19)
10 %x LINE (20)
GRAND TOTAL FOR MATERIALS: LINE (20) + (21)
EQUIPMENT 109.05 (b)(4)
$0.00 (18)
$0.00 (19)
$0.00 (20)
$0.00 (21)
$0.00 (22)
Equipment # CONTRACTOR OWNED EQUIPMENT
FHWA HOURLY RATE Days
EXTENSION
(25)
$0.00
$0.00
$0.00
$0.00
$0.00
(28)
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Tricking - Stnaght Time
$0.00
$0.00
Trucking - Over Time
$0.00
$0.00
Trucking - Double Time
$0.00
$0.00
TOTAL EQUIPMENT
TOTAL TRUCKING
FUEL, LUBRICANTS AND TRANSPORTATION COSTS
TOTAL LINES (23) + (24) + (25)
10 % x LINE (26)
GRAND TOTAL FOR EQUIPMENT: LINES (26) + (27)
SUBCONTRACTORS 109.05 (b)(6)
$0.00 (23)
$0.00
(24)
$0.00
(25)
$0.00
(26)
$0.00
(27)
$0.00
(28)
DESCRIPTION AMOUNT
Fox Contractors see attached breakdown $20,447.63
TOTAL SUBCONTRACT WEEK ENDING $20,447.63 (29)
10 % x LINE (30) $3,000.00 OR LESS $2,044.76 (31)
GRAND TOTAL FOR SUBCONTRACTORS: LINES (30) + (31) + (32) $22,492.39 (33)
TOTAL OF WORK COMPLETED FOR THE WEEK
TOTAL LINES (12), (17), (22). (28) 8 (33) $22,492.39 (34)
i % OF BOND RATE BASED UPON LINE (34) $224.92 (35)
10 % x LINE (35) $22.49 (38)
TOTAL EXTRA WORK LINES. (34) + (35) + (36) $22,739.81 (37)
UNITS 1.00
UNIT PRICE $22,739.81
Page 2 of 2
° Fox Contractors Corp.
° Av www.foxcontractors.com
w.
5430 W. Ferguson Road • Fort Wayne, Indiana 46809-9612
e �p Ft. Wayne (260) 747-7461 • Fax (260) 747-7717
°,p Whitestown (317) 769-6291 Fax (317) 769-6294
l WAYNE
Mr. Jeff Mattix
Rieth Riley Construction Co.
1751 West Minnesota Street
Indianapolis, IN 46221
RE: 96" & Hazel Dell — Change Order Request Summary
Dear Mr. Mattix:
There were several utility conflicts for the new storm sewer pipe on the above referenced
project. Please find enclosed a summary of those conflicts and the associated cost, for the
engineers review.
The total of this summary is $20,447.63. Would you please request a change order for
this amount from the engineer?
If you have any questions, please feel free to contact me.
Thank you,
ry Paul
Fox Contractors
Enc.
Certified MBE • Equal Opportunity Employer
96TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
CLAIM •
DESCRIPTION
LABOR
EQUIPMENT
MATERIAL
SUBCONTRACTOR
TOTAL
1
Sir 102. Cut Lager Holes Forcemain Conflict
$
349.00
$ 286.00
$ -
S 345.00
$ 980.00
2
Str 106 Elkninated Forcemain Conlict
$
349.00
$ 286.00
$ 535.00
$ 1,170.00
3
Sir 113 IPL Dud Bank Conflict
$
349.00
$ 286.00
$ -
$ 850.00
$ 1,485.00
4
Sir 314 - 315 IPL Dud Bank Conflict
$
698.00
$ 572.00
$ -
$ 1,270.00
5
Sir 127 Old Gas Line Conflict
$
667.00
$ 218.00
$ -
$ 885.00
6
BMP Move 5' South & Rework Sir's 204 & 203
$
2,094.00
$ 1,716.00
$ 624.00
$ 4,434.00
7
Sir 203 - 209 Force Main Conflict
$
1,308.75
$ 715.00
$ 468.00
$ 500.00
$ 2,991.75
8
Readjust Castings Northside Walk Path
$
1,244.00
$ 864.00
$ 725.00
$ 2,833.00
9
Sir 310 - 311, 306 - 307, 302 - 303 IPL Dud Bank
$
1,396.00
$ 1,144.00
$ -
$ 2,540.00
$
$
TOTALS BEFORE MARK-UP
$
8,454.75
$ 6,087.00
$ 2,352.00
$ 1,695.00
$ 18,58&75
10%MARK-UP
$ 1,858.88
TOTAL
$ 20,447.63
96TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
Oescrlptbn units
Str. 102 Cut larger holes Forcommin Conflict
Foreman
Operator
Laborer
Pickup
320 Trackhoe
930 Loader
ABC Saw Cutting ARC - DID NOT CORE SYR IT WAS SAW CUT
Total
CHA COMMENTS:
DATE OF OCCURANCE: 5/23 & 5/24
UP Noun Nota
Amount Totaht
1 79.00
79.00
2 76.00
152.00
2 59.00
118.00
1 26.00
26.00
1 140.00
140.00
1 120.00
120.00
345.00 THIS MAY BE FOR DO CORE ON 5/23
345.00
980.00
REMARKS: On 5/23 Crew notified Brian A. Of Structure 102 conflict with Sanitary Sewer Force Main at 3:10 PM. I contacted Hanl with Carmel and
he said he would look at it In the morning. We determined that Str 106 was also in direct conflict and proposed to be eliminated to
Samantha. Crew moved to Str 116 and continued to install str & pipe.
On 5/24 approval was given by Carmel Sewer to raise pipe to go over force main at Str 102 and to eliminate Str 106 by CMA. Fox saw
cut str 102 and 101 in order to raise the pipe approx. 4" to clear Camel Force Main.
APPROVE / I would agree to pay $980 for this claim - considering the ABC charge is for coring the underdrain on 5/23 and no additional charges
DENY / for UD installation which was paid for under existing bid items.
CONSIDER:
96TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
Str. 106 Eliminated Forcemaln Conflict
Foremen
1
79.00
79,0D
Operator
2
76.00
152.00
Laborer
2
59.00
11&00
Pickup
1
26.00
26.00
320 Tracthoe
1
140.00
140,00
930 loader
1
120.00
12000
Inlet 1 535.00
53500
Total
1,170.00
CNA COMMENTS:
DATE OF OCCURANCE: 5/23 & 5/24
REMARKS: See above remarks regarding the determination of conflicts with str's 102 & 106.
APPROVE / I would agree to pay $1,170, because crew did excavate in the location of str 106 to confirm that there was a conflict and that the
DENY / structure did need to be eliminated. Agree to pay for the material cost of $535 for str 106.
CONSIDER:
96TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
Str. 119 Power Duct Bank Conrlkt
ABC Saw CUttin & Core Drilling
1 8.50.00
850.00
Foremen
1
79.00
7900
Operator
2
761X)
152.00
Laborer
2
59,00
118.00
Pickup
1
2600
26.00
320 Trackhoe
1
140.00
140.00
930 Loader
1
120.00
120.00
Total
1485.00
CNA COMMENTS:
DATE OF OCCURANCE: 6/26 & 6/28
REMARKS:
On 6/26 the conflict with the IPL Duct bank was discovered late Tuesday afternoon. it was determined that there was no room to fit
the existing structure 113 between str 114 and the duct bank. It was decided that str 113 had to be modified by cutting off the sump
and coring new holes in structure. After this Jerrad began cutting subgrade and remaining crew poured collars and flowiines.
On 6/28 ABC was onsite to modify str 113. Jerrad assisted ABC with laying out structure and the remaining crew was busy with other
operations.
APPROVE / Would consider paying $ 1485 for the time required to determine a resolution to the situation. Though I have always been told you
DENY/ are to be given some time to determine a solution before you can begin claiming time. This was decided very quickly and crew was set
CONSIDER: up to pour collars and flowlines at the end of day. No time was really lost with this incident. When ABC was onsite Jerrad was really
the only one involved with ABC modifying the Str.
96TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
Sit. 314 to 315 Duct Rank Conflict
roremen
2 _-4-.
79.00
_316.89 158.00
Operator
4 -j-
76.00
"/.Go 304.00
Laborer
4 --6-
59.00
lwi.ea 236.00
Pickup
2 -4--
26.00
20460 52.00
320 Trackhoe
2 -*-
140.00
5ftee- 280.00
930 Loader
2 --4-
120.00
-4/D.E— 240.00
Total
-k5l111.915 1270.00
CHA COMMENTS:
DATE Of OCCURANCE: 6/23/2018
REMARKS:
Crew was aware of the potential conflict and was provided general information about being able to raise pipe 3" to clear duct bank
before even starting on this pipe run. It was determined that the pipe needed to be raised 4" to clear duct. Crew had to cut str 315
and 121- 4" to make this adjustment. I would consider allowing 1hr for each structure to be cut - no other portion of the operation
changed. Besides the 102' of 15 inch pipe and C30 MH - Crew also installed 2 - C4 Manholes and 86' of 12 Inch pipe and poured collars.
APPROVE / Consider paying for only 1 hr for each str to be modified (Sir 121 & Str 131) - Total of 2 hrs per the crew. _ $1270.00
DENY/
CONSIDER:
96TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
Str.127 Old Gas line Conflict
Foreman
3
-4
79.W
-M6.86 237.00
Operator
1
--4-
76.00
301.08 76.00
Laborer
6
-4-
59.00
-01.00 354.00
Pickup
3
-4-
26.00
04.00 78.00
320Trackhoe
1
-4-
140.00
5666B- 140.00
Total
34"A9 885.00
CNA COMMENTS:
DATE OF OCCURANCE: 5/18 & 5/19
REMARKS: On 5/18 Jerrads crew discovered a unknown 10" -12" steel pipe while excavating for str 127. Crew continued to install str's while
calls were made to detrmine who the line belonged to. No one claimed the pipe and later In the afternoon the pipe was drilled and
dtermined to be abandoned. On
5/19 Dan had two guys begin cutting on the pipe, the two laborers were new with little experience and were extremely slow in trying
to get it cut out. At times the two laborers were literally sitting doing nothing. No other equipment was used execpt a quickie saw and
possibly the excavator for a 1 hour to rip the pipe out completely.
APPROVE / An expereinced couple of laborers would have had this pipe cut out In 2 hours. The excavator operator was only necessary to
DENY/ complete the removal of pipe once the cut was mostly complete. I will consider paying the 2 Laborers for 3 hours / 3 Hrs Foreman /
CONSIDER: 1 hour Operator
96TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
BMP Move S' South 6 Rework Stn. 204 i 203
Foreman 6 —8 79.00 .--632,00 474.00
Operator 12 —ii 76.00 —Km 912.00
Laborer 12 .16 59.00 708.00
Pickup 6 t 26.00 --296se 156.00
320 Trackhoe 6 --i 140.00—trr+E70.00 840.00
930 Loader 6 —Y 120.00 --960A0 720.DO
Tri -Axle 6 R 104.00 --4374)O 624.00
mecum
4434.00
CMA COMMENTS:
DATE OF OCCURANCE: 5/19, 5/20, & 5/25
REMARKS: 5/19 - Crew onsite today to begin installing BMP structure. Fox needed a trench box for safety due to depth of str and since it was
located close to fire hydrant It was agreed to shift the approx. 4'. (There possibly could have been other ways to shore the str but
under tight time constraints). Crew set the BMP str 204A, 204 and tied in remaining pipe towards 124, and installed str 203. It was
then determined the 30" pipe was not going to line up right so some modiflcaitons needed made to str 203. (2 Hr)
5/20 - Crew In the morning continued to modify str 203 to accept the 30" pipe alllgnment. (1 Hr) Crew laid the 86' of 12" pipe to str
208 and then laid the 98' of 30" pipe across Hazel Dell (Portion of this time is claimed on separate incident) and set str 209.
5/25 - Had to cut on Str 204 and 204A in order to install the 15" pipe which we used SDR 26 Instead of concrete (2 Hr). The remainder
of the day crew assisted with the grading operations and poured a lot of flow lines and collors on remaining structures.
APPROVE / Since having to move the BMP structure was for both Safety to get a box In the trench as well as being located near a fire hydrant I
DENY/ would be willing to pay for the times listed above in the remarks.
CONSIDER:
Stf. 203 to 209 Force Main Conflict
Foreman
Operator
Laborer
Pickup
320 Trackhoe
930 Loader
Tri -Axle
an Stone
Badger Vac Truck
Pylwood
Concrete
CHA COMMENTS:
DATE OF OCCURANCE: 5/20 & 5/21
96TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
2.5 - 8 7909 1.18.50
5.0 16 76:00 114.00
5.0 -46- 59:00 88.50
2.5 -8- 26.00
2.5 -8 140.00
2.5 -a 120.00
0.0 - a 4044)0
4 -89- 18.00
2 250.00
0 4 50.00
3 - 4 132.00
Total
63268 296.25
i;25698 570.00
944.80 442.50
18&08 65.00
1.42B60 350.00
sG0.00- 300.00
-832. 0.00
6440,90 72.00
500,0g 500.00
aw 99 0.00
62&.00- 396.00
2991.75 $5864);0
REMARKS: 5/20 - Mid afternoon crew began installation across Hazel bell with the 30" RCP with known conflict adjustments with Carmel Force
Main. Around 2:40 Crew encountered concrete in pipe trench and had to bust up to remove - Completed at 3:10 (0.5 Hr). At 3:30
Crew uncovered the Force Main and used mini excavator to dig a 2' wide by 2' deep trench under the pipe and placed a piece of scrap
plywood to hold fill back when vac out and filled with a8 stone. This operation was completed at 4:37 and the crew continued to lay
pipe as normal to str 209 and set str 209.
5/21- Crew spent the day as usual installing pipe and structures and pouring a lot of flowllnes and collars( 3 loads) . At 4:30 PM
Badger arrived to vac out stone so concrete piers could be poured, Concrete was poured In and completed by 5:10 and Badger left at
5:20.(IHr)
96TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
7 -CONTINUED
/ I would agree pay a total of 2.5 hours for the additional work required to construct the piers based on the time 1 had recorded for this
DENY/ work. No Tri -Axle used. Also agreed to pay a time and half rate for labor since the work took place on the weekend.
CONSIDER:
%TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
Readjust Cestings Northskk Walk Path
Foreman
4
79.00
316.00
Operator
6 -8--
76.00
tiiN1W 456.00
Laborer
8
59.00
472.00
Pickup
4
26.00
104.00
320 Trackhoe
2 -4—
140.00
-56@.ft 280.00
930 Loader
4
120.00
480.00
Adjusting Rings 10
72.50
725.00
Total
2833.00
CHA COMMENTS:
DATE OF OCCURANCE: 7/11, 7/12, 7/13, 7/14
REMARKS: There were numerous days that crew made some kind of adjustment to castings. Short of shooting all the casting lids to determine
the plan differences, in almost every job there are generally some necessary adjustments based on stone or paving grade between
riser heights. I know that some of the adjustments were due to side slopes which required castings to be raised. I would agree that
many of the adjustments are justifiable but at the time of adjustments there was no need for an trackhoe to be claimed and only 1
operator would be necessary.
APPROVE / It was agreed that the trackhoe was used to remove the barrel section from the BMP Str and to shape up around the structure.
DENY/
CONSIDER:
96TH STREET & HAZEL DEL
FOX SUBMITTED EXTRA WORK COST SUMMARY
Slit. 310 to 311 * 306 to 307 + 302 to 303 Duct Bank Conflict
Cut Down Boaas
Foreman 4 ..f._ 79.00 W4 316.00
Operator 8 -il 76.00 —9}2:9 8.00
Laborer 8 -1:2- 59.00 --008,60472.00
Pickup 4 -6 26.00 -- 5668104.00
320 Trackhoe 4 -4— 140.00 --I4640560.00
930 Loader 4 -i- 120.00 —r:vw 480A0
-2540.00
CHA COMMENTS:
DATE OF OCCURANCE: 6/30/2018
REMARKS: Pipe was installed on 6/30 between the structures on Industrial Dr. The structures had to be slightly modified a few inches on each to
clear the IPL duct banks. Due to Fox not having this area ready for subgrade treatment for the pipe crew they choose to install the
structures on the east side before subgrade treatement was complete causing them to have to dig in pipe structures from the side.
Today crew also mixed up mortar and slicked up aruond pipes and Installed hoods and stacked out structures.
APPROVE / I will consider paying the crew for 2 Hrs to make the minor saw cut adjustments to the 6 structures in order to clear the IPL dud banks
DENY/ in this area. Also it was agreed to pay an additional 2 Hrs because the trenches were completely excavated and the IPL dud bank was
CONSIDER: exposed to get a elevation shot on in order to determine the amount of adjustments required at each structure.
Memo
To: Doug Haney, Corporation Counsel
From: Lisa Scott
CC: Jeremy Kashman
Date: 09/28/18
Re: C.O. #7 96"' Street and Hazel Dell RAB Project #16 -ENG -35
Doug, please find attached 1 original of same change order for project #16 -ENG -35 96h Street and Hazel Dell RAB
project. Please review & initial for the next BPW Meeting.
Change Order #7 - Original Contract Amount: $1,588,508.79 Increase: $22,739.81 New Contract Amount:
$1,632,382.23
Thank you,
Lisa Scott
0 Page 1