SECTION 01 78 39 - PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for project record documents,
including the following:
1. Record Drawings.
2. Record Specifications.
3. Record Product Data.
4. Miscellaneous record submittals.
B. Related Requirements:
1. Section 01 73 00 "Execution" for final property survey.
2. Section 01 77 00 "Closeout Procedures" for general closeout procedures.
3. Section 01 78 23 "Operation and Maintenance Data" for operation and maintenance
manual requirements.
1.3 CLOSEOUT SUBMITTALS
A. Record Drawings: Comply with the following:
1. Number of Copies: Submit one set(s) of marked-up record prints.
2. Number of Copies: Submit copies of record Drawings as follows:
a. Initial Submittal:
1) Submit one paper-copy set(s) of marked-up record prints.
2) Submit PDF electronic files of scanned record prints and one of file prints.
3) Submit record digital data files and one set of plots.
4) Architect will indicate whether general scope of changes, additional
information recorded, and quality of drafting are acceptable.
b. Final Submittal:
1) Submit three paper-copy set(s) of marked-up record prints.
2) Submit PDF electronic files of scanned record prints and three set(s) of
prints.
3) Print each drawing, whether or not changes and additional information were
recorded.
c. Final Submittal:
1) Submit one paper-copy set(s) of marked-up record prints.
2) Submit record digital data files and three set(s) of record digital data file
plots.
THE KENT
01 78 39 -
PROJECT RECORD
THE KENT Issue
Date 05.09.18 DOCUMENTS
THE KENT
3) Plot each drawing file, whether changes and additional information were
recorded.
B. Record Specifications: Submit one paper copy of Project's Specifications, including addenda
and contract modifications.
C. Record Product Data: Submit one paper copy of each submittal.
1. Where record Product Data are required as part of operation and maintenance manuals,
submit duplicate marked-up Product Data as a component of manual.
D. Reports: Submit written report weekly indicating items incorporated into project record
documents concurrent with progress of the Work, including revisions, concealed conditions,
field changes, product selections, and other notations incorporated.
PART 2 - PRODUCTS
2.1 RECORD DRAWINGS
A. Record Prints: Maintain one set of marked-up paper copies of the Contract Drawings and Shop
Drawings, incorporating new and revised drawings as modifications are issued.
1. Preparation: Mark record prints to show the actual installation where installation varies
from that shown originally. Require individual or entity who obtained record data, whether
individual or entity is Installer, subcontractor, or similar entity, to provide information for
preparation of corresponding marked-up record prints.
a. Give attention to information on concealed elements that would be difficult to
identify or measure and record later.
b. Accurately record information in an acceptable drawing technique.
c. Record data as soon as possible after obtaining it.
d. Record and check the markup before enclosing concealed installations.
e. Cross-reference record prints to corresponding archive photographic
documentation.
2. Content: Types of items requiring marking include, but are not limited to, the following:
a. Dimensional changes to Drawings.
b. Revisions to details shown on Drawings.
c. Depths of foundations below first floor.
d. Locations and depths of underground utilities.
e. Revisions to routing of piping and conduits.
f. Revisions to electrical circuitry.
g. Actual equipment locations.
h. Duct size and routing.
i. Locations of concealed internal utilities.
j. Changes made by Change Order or Construction Change Directive.
k. Changes made following Architect's written orders.
l. Details not on the original Contract Drawings.
m. Field records for variable and concealed conditions.
n. Record information on the Work that is shown only schematically.
3. Mark the Contract Drawings and Shop Drawings completely and accurately. Use
personnel proficient at recording graphic information in production of marked-up record
prints.
THE KENT
01 78 39 -
PROJECT RECORD
THE KENT Issue
Date 05.09.18 DOCUMENTS
THE KENT
4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish
between changes for different categories of the Work at same location.
5. Mark important additional information that was either shown schematically or omitted
from original Drawings.
6. Note Construction Change Directive numbers, alternate numbers, Change Order
numbers, and similar identification, where applicable.
B. Record Digital Data Files: Immediately before inspection for Certificate of Substantial
Completion, review marked-up record prints with Architect and Construction Manager. When
authorized, prepare a full set of corrected digital data files of the Contract Drawings, as follows:
1. Format: Annotated PDF electronic file with comment function enabled.
2. Incorporate changes and additional information previously marked on record prints.
Delete, redraw, and add details and notations where applicable.
3. Refer instances of uncertainty to Architect through Construction Manager for resolution.
4. Architect will furnish Contractor one set of digital data files of the Contract Drawings for
use in recording information.
a. See Section 01 33 00 "Submittal Procedures" for requirements related to use of
Architect's digital data files.
b. Architect will provide data file layer information. Record markups in separate
layers.
C. Newly Prepared Record Drawings: Prepare new Drawings instead of preparing record Drawings
where Architect determines that neither the original Contract Drawings nor Shop Drawings are
suitable to show actual installation.
1. New Drawings may be required when a Change Order is issued because of accepting an
alternate, substitution, or other modification.
2. Consult Architect and Construction Manager for proper scale and scope of detailing and
notations required to record the actual physical installation and its relation to other
construction. Integrate newly prepared record Drawings into record Drawing sets; comply
with procedures for formatting, organizing, copying, binding, and submitting.
D. Format: Identify and date each record Drawing; include the designation "PROJECT RECORD
DRAWING" in a prominent location.
1. Record Prints: Organize record prints and newly prepared record Drawings into
manageable sets. Bind each set with durable paper cover sheets. Include identification
on cover sheets.
2. Format: Annotated PDF electronic file with comment function enabled.
3. Record Digital Data Files: Organize digital data information into separate electronic files
that correspond to each sheet of the Contract Drawings. Name each file with the sheet
identification. Include identification in each digital data file.
4. Identification: As follows:
a. Project name.
b. Date.
c. Designation "PROJECT RECORD DRAWINGS."
d. Name of Architect and Construction Manager.
e. Name of Contractor.
THE KENT
01 78 39 -
PROJECT RECORD
THE KENT Issue
Date 05.09.18 DOCUMENTS
THE KENT
2.2 RECORD SPECIFICATIONS
A. Preparation: Mark Specifications to indicate the actual product installation where installation
varies from that indicated in Specifications, addenda, and contract modifications.
1. Give attention to information on concealed products and installations that cannot be
readily identified and recorded later.
2. Mark copy with the proprietary name and model number of products, materials, and
equipment furnished, including substitutions and product options selected.
3. Record the name of manufacturer, supplier, Installer, and other information necessary to
provide a record of selections made.
4. For each principal product, indicate whether record Product Data has been submitted in
operation and maintenance manuals instead of submitted as record Product Data.
5. Note related Change Orders, record Product Data, and record Drawings where
applicable.
B. Format: Submit record Specifications as annotated PDF electronic file with paper copy.
2.3 RECORD PRODUCT DATA
A. Preparation: Mark Product Data to indicate the actual product installation where installation
varies substantially from that indicated in Product Data submittal.
1. Give attention to information on concealed products and installations that cannot be
readily identified and recorded later.
2. Include significant changes in the product delivered to Project site and changes in
manufacturer's written instructions for installation.
3. Note related Change Orders, record Specifications, and record Drawings where
applicable.
B. Format: Submit record Product Data as annotated PDF electronic file with paper copy.
1. Include record Product Data directory organized by Specification Section number and
title, electronically linked to each item of record Product Data.
2.4 MISCELLANEOUS RECORD SUBMITTALS
A. Assemble miscellaneous records required by other Specification Sections for miscellaneous
record keeping and submittal about actual performance of the Work. Bind or file miscellaneous
records and identify each, ready for continued use and reference.
B. Format: Submit miscellaneous record submittals as PDF electronic file with paper copy.
1. Include miscellaneous record submittals directory organized by Specification Section
number and title, electronically linked to each item of miscellaneous record submittals.
THE KENT
01 78 39 -
PROJECT RECORD
THE KENT Issue
Date 05.09.18 DOCUMENTS
THE KENT
PART 3 - EXECUTION
3.1 RECORDING AND MAINTENANCE
A. Recording: Maintain one copy of each submittal during the construction period for project record
document purposes. Post changes and revisions to project record documents as they occur; do
not wait until end of Project.
B. Maintenance of Record Documents and Samples: Store record documents and Samples in the
field office apart from the Contract Documents used for construction. Do not use project record
documents for construction purposes. Maintain record documents in good order and in a clean,
dry, legible condition, protected from deterioration and loss. Provide access to project record
documents for Architect's and Construction Manager's reference during normal working hours.
END OF SECTION 01 78 39