CITY OF CARMEL
CONTRACT CHANGE ORDER NO.: 2
DATE: 10/24/18
PROJECT NAME: 17 -ENG -01 Duke Energy Relocation Plans Phase 1 & 3
CITY REQ. NO.:
CITY PO NO.: 100743
CITY PO DATE: 9/21/18
1. You are directed to make the following changes in this Contract:
9
Add additional items due to modifications in the field and requests from Carmel Utility Departments.
SCHEDULED ADJUSTMENT
ITEM AMOUNT [+) OR (-) DAYS
` See detail of items and summary of changed costs in attached Table
92
Thermal Flowable Fill
$60,715.31
0 Days
TOTAL OF CHANGE ORDER ITEMS
560.715.31
0 Days
If. The following referenced Documents further describe the changes outlined in Paragraph 1,
and are to be considered a part of this Change Order: R.F.P.: n/a W.D.C. NO.:n/a_
Other: _ By Request from the City of Carmel per proposals included herein
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order
Contract Price will be increased by this Change Order
New Contract Price including this Change Order
Contract Time prior to this Change Order 131 Days
Net increased resulting from this Change Order
Current Contract Time including this Change Order
$2.647.010.93
$60,715.31
52.707.726.24
June 16 2018 Completion Date
0 Days
June 16 2018 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are Recommended The Above Changes Are Accepted Approved
CROSSROAD ENGINEERS
ENGINEER
3417 Sherman Drive
Address
Beech Grove. IN 46107
City/State/Zip
Ry:
P one: 317-780-1555
7wMt.% H*46 cfte
Date: IOI Z 6 ((S
Mornitev Construction
CONTRACTOR
1499 N Sherman Dr
Address
Indianapolis, IN 46201
City/Blatt/ ip
Ily:
Phone: 317-716-6719
Date: /0-2$—►a
ames Brainard, Mayor
�1 Christine S. Paule , Clerk -Treasurer
Date:—A
g
17 -ENG -01 Duke Energy Relocation Plans Phase 1&3
CHANGE ORDER #3 TABLE
Item Odow Original Final
No. Description Unit Unit Price an Amount uantity FinalAmount Over/Under
92 Thermal Flowable Fill LS IS 60,715.31 0 S I S 60,715.31 S 60,715.31
TOTAL OF CHANGE ORDER ITEMS S 60,715 31
CONTRACT PRICE PRIOR TO CHANGE ORDER
S 2.647.010.93
CHANGE ORDER #2 S 60,715.31
NEW CONTRACT AMOUNT INCLUDING APPROVED CHANGE ORDERS S 2,707.726.24
17 -ENG -01 Duke Energy Relocation Plans Phase 1&3
EXHIBIT A
You have been directed to make the following changes in this Contract:
Item
No Description Reason For Change
q 1 Thermal Flowable Fill added due
City of Carmel Project 17 -ENG -01
Duke Energy Relocation Plans Phase 1&3
CHANGE ORDER #2
Added due to omission from pre-bid Duke Specifications.
Contract Price -prior-to-this Change Order
Contract Price will be increased/decreased by this Change Order
New Contract Price including this Change Order
-----------------------------------------------------------------------------------------
$2,647,010.93
$60,715.31
$2,707,726.24
Amount
Adjusted Contract
Price
Cumulative % Change
from Original Contract
Original Contract $2,627,746.00
$2,627,746.00
N/A
C01 $19,264.93
$2,647,010.93
0.7%
CO2 $60,715.31
$2,707,726.24
3.0%
Memo
To: Doug Haney, Corporation Counsel
From: Lisa Scott
CC: Jeremy Kashman
Date: 10/30/18
Re: C.O. #2 Duke Energy Relocation Plans Phase 1 &3
Doug, please find attached 1 original of a change order for project #17 -ENG -01 Duke Energy Relocation Plans
Phase 1 U. Please review & initial for the next BPW Meeting.
Change Order #2 Original Contract Amount: $2,627,746.00 Increase: $60,715.31 New Contract Amount
$2,707,726.24