HomeMy WebLinkAboutMorphey Construction/Eng/CO #1 Final/296,137.14/Duke Energy Relocation PlansCity of Carmel Proj ect 17 -ENG -01
Duke Energy Relocation Plans
Phase 2 South &4
CHANGE ORDER #1, FINAL
Balancing/Reconciliation for Pay Items 1 through 30
Contract Price prior to this Change Order
................................................. ..... -----
Contract Price will be increased/decreased by this Change Order
-- ................ ............. -
New Contract Price including this Change Order
......... ... . ....
Amount Adjusted Contract
Price
Ori final Contract $1,496,947.00 $1,496,947.00
CO1, Final -$296,137.14 $1,200,809.86
$1,496,947.00
-$296,137.14
$1,200,809.86
Cumulative %
Change from Original
Contract
N/A
-19.8% —�
CITY OF CARMEL
TO: Morphey Construction, Inc. CONTRACT CHANGE ORDER NO.. 1, FINAL
1499 N Shennan Dr DATE: 11/12/18
Indianapolis, IN 46201 PROJECT NAME: 17 -ENG -01 Duke Energy Relocation Plans Phase 2 South & 4
CITY REQ. NO.: N/A
CITY PO NO.: 101592
CITY PO DATE: 4/19/18 0�1
I. You are directed to make the following changes in this Contract:
Add additional items due to modifications in the field and requests from Carmel Utility Departments.
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+) OR ( -1 DAYS
* See detail of items and summary of changed costs in attached Table
TOTAL OF CHANGE ORDER ITEMS 1 -5296,137.14 0 Days
It. The following referenced Documents further describe the changes outlined in Paragraph 1,
and are to be considered a part of this Change Order: R.F.P.: _n/a _W.D.C. NO.: n/a
Other: _ By Rgguest from the City of Carmcl per proposals included here
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order
Contract Price will be increased by this Change Order
New Contract Price including this Change Order
Contract Time prior to this Change Order 60 Days
Net increased resulting from this Change Order
Current Contract Time including this Change Order
$1,496.947. W
S (296.137.141
$1.200.809.86
June 30 2018 Completion Date
27 Days
July 27 2018 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and tithe
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are Recommended The Above Changes Are Accepted Approved
CROSSROAD ENGINEERS
ENGINEER
3417 Sherman Drive
Address
Beech Grove. IN 46107
Ciry/State/Zip
Bv� —
T,le.-� %�xb�ltNer
Phone: 317-730-1555
Date: ((.If 2// a
Momhcv Construction
CONTRACTOR
1499 N Sherman Dr
Address
Indianapolis. 1N 46201
City/State/Zip
By:
Phone: 317-716-6719
Date: //^ r Z-/ 8
1
James inard, Mayor
Kash( Citv gineer
Ltary Aur ur lcmbcr
Lori ' Member
A
Christine S. Paul y, Cl k -Treasurer "
Date: // (Zr (r
17 -ENG -01 Duke Energy Relocation Plans Phase 2 South & 4
CHANGE ORDER#1 TABLE
Item
No.
Description
Unit
Unit Price
Original
uanti
Original
Amount
Final
Quantity
Final Amount
Over/Under
I
Construction Lngineering
LS
S 7,500.1;0
1
7,50000
1
S 7.500.00
S
2
Mobilization and Demobilization
IS
S 75.750.00
1
b
75,750.00
1
S 75,750.00
$
3
Field Office
DOL
S 1.00
1000
S
1,00000
0
5
5 (I,000.n0)
4
Office Equipment
MO
S 800,00
2
$
1,60000
0
S
S 1.600.00)
5
I Maintenance of Traffic
LS
S 25.000.00
1
S
25.000 00
1
S 25,000.00
S
6
1171carina of Right of Way
LS
S 25.000.00
1
S
25,000.00
1
S 25.000.00
S
SW CP Pre aration and Implementation Level I
LS
S 5.000.40
1
S
5,000.40
1
S 5,000.40
S
R
Storm Water uality Management Budget
DUI.
5 1.00
7190
S
7,190.00
200
S 200.00
S (6,990.00)
9
Dukc Ener v Transmission Duct Bank
LFT
S 523.68
1520
S
795,993.60
1460
S 764,572.80
S (31,420.80)
10
Transmission Duct Bank Backfill, Native
LFT
S 105.00
1520
S
159,600.00
150
S 15,750.00
S (143,850.00)
11
Transmission Duct Bank Backfill. Structural
1_1T
S 160.00
1520
S
243,200.00
1370
S 219,200.00
S (24,000.001
12
Compacted Aggregate Base. No. 53 Stone (Undistributed) CYS
S 100.00
2
S
20000
9.44
S 944.00
S 744.00
13
ISidcwalk. COnerele, 4 in.
SYS
S 300.00
9
S
2.700.00
0
5
S (2,700.00)
14
lir sod (undistributed)
CYS
S 40.00
704
S
28,160 00
0
S
S (28,160.00)
15
Erosion Control Blanket w/ Seed
SYS
S 7.00
2639
S
18,473 00
3259.28
S 22 814.96
S 4.341.96
16
Mulched Seedin •
SYS
S 5.00
1583
S
7.91500
0
S
$ (7,915 00)
17
Mobilisation and Demobilization for Seeding
EA
S 50.00
2
S
100.00
1
S 50.00
S (50.00)
18
Structure Backfill. 'f e I
CYS
S 170.00
5
$
85000
8.7
S 11479.00
S 629.00
19
Pipe. Type 2, Circular. 12"
LFT
$ 85.00
33
S
2,805.00
48
S 4,080.00
S 1,275.00
21)
PiDe. Tvm 2, Circular. 18"
LFT
S 9500
36
S
3,420.00
40
S 3,800.00
5 380.00
21
Pipe.'rype 2. Circular, 24"
I_FT
5 500.00
4
$
2,00000
0
$
S (2,000.00)
22
12" Pie End Section. Concrete
EA
S 1,500.00
2
S
3.00000
5
$ 7,500.00
S 4,500.00
23
18" Pipe End Section, Concrete
EA
S 1700.00
2
S
3,400.00
2
S 3,400.00
S
24
Inlet, Tv e'E-7'
LA
S 2,600.00
1
S
2,600.00
0
S (2,600.00)
'S
Manhole, Tv 'C-4'
EA
5 3,700.00
1
$
3.700.00
0
$ (3,700.00)
26
Tem orary Construction Lente
LFT
S 8 35
1400
S
11.690.00
1390
$ (83.50)
27
Pavement Patching. Tem orary (Undistributed)
SYS
S 20.00
2000
$
40,000,00
112.6
M2.252,00
S (37,748.00)
'-8
Surface Overlay, tem ora (Undistributed)
TON
S 1(10.00
166
$
16,600.00
0
S16.60!)00)29
Dum ster Enclosure
LS
5 2,500.00
1
$
2.500.00
1
5
30
Union Brewin Pedestrian A roach
LS
S 2,410.20
0
$
1
S 2,410 20
TOTAL OF CHANGE ORDER ITEMS
I S (2%,137.14)1
CONTRACT PRICE PRIOR TO CHANGE ORDER
S 1,496,947.01)
CHANCE. ORDER til S (296.137.14)
NEW C'ONTRACT' AM0UNT INCLUDING APPROVED CIIANG E ORDERS S 1,200,809.86
17 -ENG -01 Duke Energy Relocation Plans Phase 2 South & 4
EXHIBIT A
You have been directed to make the following changes in this Contract;
Item
No
Description
ResewFor Chraege
3
Ficid Otlice
not used
4
Of)ice E ui mem
not used
8
Stonn Water Quality Manaigentent Budget
adjusted to balance original quantities versus actual
quantities used for original items
b
JDukc I.ner v Transmission Duct Bank
adjusted to balance original quawitics versus actual
quantities used for original items
10
ITransmission Duct Bank Backf ll. Naii\c
adjusted to balance original quantities versus actual
quantities used for original items
1 I
Transmission Duct Bank Backfill, Structural
adjusted to balance original quantities versus actual
quantities used for original items
12
Compacted Aggregate Base, No. 53 Stone (Undislribut4 adjusted to balance original quantities versus actual
quantities used Ibr original items
3
Sidewalk, Concrete, 4 in.
not used: asphalt used instead
14
Topsoil (undistributed)
not used; existing soil was suitable forseed
15
Brosion Control Blanket w/ Seed
adjusted to balance original quantities versus actual
uanti(ies used for original items
16
Mulched Seeding
not used due to Monon Blvd project schedule
17
Mobilization and Demobilization for Seeding
adjusted to balance original quantities versus actual
quantities used for original items
IS
Structure Backfill, Type I
adjusted In balance original quantities versus actual
quantities used for original items
19
]Pipe, Type 2, Circular, 12"
quantity increased due to added Union Bre vin Pedestrian Approach
'17)
Pipe, l'ype 2, Circular, 18"
adjusted to balance original quantities versos actual
quantities used for original items
21
Pipc.Typc 2, Circular, 24"
not used; exisling pipe not removed
'2
12" Pipe End Section, Concrete
quantity increased due to added Union 13rewing Pedestrian Approach
24
Inlet, T 'G7'
not used; existing structure not removed
2-
Manhole, T e'C-l'
not used; existing structure not remmed
26
Temporary Construction Fence
adjusted to balance original quantities versus actual
quanLIOCS used for original items
_27
Pavement Patching, Temporary (Undistributed)
adjusted to balance original quantities versus actual
quantities used for original items
.S
Surface Overlay,"rem ora (Undistributed)
not used
30
JUnion Brewing Pedestrian Approach
added at the city's request
Memo
To: Doug Haney, Corporation Counsel
From: Lisa Scott
CC: Jeremy Kashman
Date: 11/13/18
Re: C.O. #1 FINAL — Duke Energy Relocation Plans Phase 2 South & 4 Project #17 -ENG -01
Doug, please find attached 1 original of same change order for project #17 -ENG -01 Duke Energy Relocation Plans
Phase 2 South & 4. Please review & initial for the next BPW Meeting.
Change Order #1 FINAL- Original Contract Amount: $1,496,947.00 Decrease: $296,137.14 New Contract
Amount: $1,200,809.86
Thank you,
Lisa Scott
0 Page 1