HomeMy WebLinkAboutGradex/Eng/CO #1/-484,726.89/North Range Line Road ReconstructionCity of Carmel Project 16 -ENG -49
North Range,line Road Reconstruction
CHANGE ORDER #1
RA8 Deletion / 2018 Escalation Adjustments
Contract Price prior to this Change Order $4,541,978.00
Contract Price will be increased by this Change Order -$484,726.89
New Contract Price including this Change Order $4,057,251.11
Amount Adjusted Contract
Price
Cumulative % Change
from Original Contract
Original Contract $4,541,978.00 $4,541,978.00
N/A
CO1 (-484,726.89) $4,057,251,11
-10.67%
Page I of 2
CITY OF CARMEL
TO: Tom DeKlyen CONTRACT CHANGE ORDER NO.: I
Gradex, Inc. DATE: 10/22/2018
12900 N. Meridian St., Suite 120 PROJECT NAME: N. Rangeline Road Reconstruction /
Carmel, IN 46032
Project # 16 -ENG -49
CITY REQ. NO.:
CITY PO NO.: COLT -100417 / SW -100425
CITY PO DATE: COLT- 5/4/2017 / SW — 5/6/2017
You are directed to make the following changes in this Contract:
*All additional work associated with the documents referenced below.
*This Change Order will create multiple new items to compensate for the ESCALATION
COSTS of constructing the above reference project in 2018 (Originally scheduled for 2017
construction.).
• All items created are based on the below referenced attachments.
*This Change order will create a new `Meter Pit Relocation' item (Item # 178 - I EACH
_ $1928.84)
• This item is based on the below referenced attachment.
*This Change Order adjusts all necessary items due to the deletion of the RAB on the
north end of the project.
• These items have been adjusted based on the below referenced
attachments.
11. The following referenced Documents further describe the changes outlined in Paragraph 1,
and are to be considered a part of this Change Order:
*N. Rangeline Road ESCALATION WORKBOOK
*N. Rangeline Road ESCALATED PAY ITEMS FOR 2018
*N. Rangeline Road ESCALATED CLEARING COSTS FOR 2018
*Meter Pit Relocation/Installation
* 16 -ENG -49 Plans Revised. RAB Removal
* 16 -ENG -49 RAB Removal QTY Changes
*Change Order I Report -N. Rangeline Road Reconstruction
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $_4,541,978.00
Contract Price will be increased/deereased by this Change Order $ -484,726.89
New Contract Price including this Change Order $ 4,057,251.11
GORtMOt "FiM8 PROF Ee this Change OF&F Days Completion Date
AR-1
e
Page 2 of 2
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are
Recommended:
United Consulting
ENGINEER
1625 N. Post Road
Address
Indianapolis, IN 46219
City/State/Zip
By:
Phone 317.724.5582
Date: 10/27/2018
The Above Changes Are
Accepted:
Gradex. Inc.
CONTRACTOR
12900 N. Meridian St.,
Suite 120
Address
Carmel, In 46032
City/Stat
By:
Phone, 3t? �'-'" )3X-Vm
Date: 10%Z.S j1 t
Approved:
Treasurer
ley, Cierk-
Je my Kash , P.E.
ity Engineer
Date:
Memo
To: Doug Haney, Corporation Counsel
From: Lisa Scott
CC: Jeremy Kashman
Date: 11/08/18
Re: C.O. #1 North Range Line Road Reconstruction - Project #16 -ENG -49
Doug, please find attached 1 original of same change order for project #16 -ENG -49 North Range Line Road. Please
review & initial for the next BPW Meeting.
Change Order #1- Original Contract Amount: $4,541,978.00 Decrease: $484,726.89 New Contract Amount:
$4,057,251.11
Thank you,
Lisa Scott
0 Page 1