Loading...
HomeMy WebLinkAboutRieth-Riley/Eng/CO #8/45,363.51/96th & Hazel Dell RAB– Project #16-ENG-35City of Carmel Project 16 -ENG -35 96th Street and Hazel Dell RAB CHANGE ORDER #8 According to the contract documents for the 96'h Street and Hazel Dell RAB project, the original project milestones were as follows: Project Start Date: 8/18/17 Substantial completion Date: 11/29/17 Completion Date: 12/13/17 Upon the expected start date of 8/18/17 all the necessary Right -of -Way had not yet been secured and most of the utilities had not yet been relocated. Great efforts were made in September between the City of Carmel and property owner Martin Marietta to try and obtain a right of entry in hopes of beginning construction yet in 2017. An onsite meeting was held on 9/20/17 to discuss the obstacles of being able to construct the RAB this late in the season without all necessary RW agreements, remaining utility relocations, and weather constraints. On 9/21/18 an email was sent to Reith -Riley from the City of Carmel stating that construction will be postponed on this project until 2018. Once it was confirmed that all utility relocation efforts were completed, construction was able to begin on May 15, 2018. Since the project was pushed into 2018 Rieth- Riley has submitted escalation costs for material, labor, equipment, trucking, etc. All associated costs have been included as part of this change order. This change order increases the contract price by $45,363.51 which is 2.86% of the original contract price of $1,588,508.70. Contract Price prior to this Change Order ------------------------------------------------------------------------------------------ $1,632,382.23 Contract Price will--be-increased/decreased-by this Change -order ---------------- $ 45,363.51 --------------------- --------------------------------- 1, (0-1-7,7.1 New Contract Price including this Change Order , ------------------------------------------------------------- - Amount Adjusted Contract Cumulative % Change Price from Original Contract Original Contract $1,588,508.79 $1,588,508.79 N/A C01- Const Chng 1 $(4,164.65) $1,584,344.14 (0.3%) Storm Water Bond CO2 -MM Add Insured $0.00 $1,584,344.14 (0.3%) General06lig. Bond CO 3 - Const Chng 2 $5,111.10 $1,589,455.24 0.06% General06lig. Bond CO 3 - Const Chag 2 $3,250.34 $1,592,705.58 0.3% Storm Water Bond CO 4 — Temp Const. Fence and New Fence $9,288.12 $1,601,993.70 0.85% General Oblig. Bond CO 5 — Added Turn $7,126.62 $1,609,120.32 1.30% Lane at Gray Rd General Oblig. Bond CO 6—Straw Blanket $522.10 $1,609,642.42 1.33% w/ U Seed General Oblig. Bond CO 7 — Fox Additional $22,739.81 $1,632,382.23 2.76% Costs for Utility Conflicts Storm Water Bond CO 8 — 2018 Escalation $45,363.51 $1,677,745.74 5.62% Costs General Oblig. Bond I. You are directed to make the following changes in this Contract: (Brief Description) According to the contract documents for the 966' Street and Hazel Dell RAB project, the original project milestones were as follows: Project Start Date: 8/18/17 Substantial completion Date: 11/29/17 Completion Date: 12/13/17 Upon the expected start date of 8/18/17 all the necessary Right -of -Way had not yet been secured and most of the utilities had not yet been relocated. Great efforts were made in September between the City of Carmel and property owner Martin Marietta to try and obtain a right of entry in hopes of beginning construction yet in 2017. An onsite meeting was held on 9/20/17 to discuss the obstacles of being able to construct the RAB this late in the season without all necessary RW agreements, remaining utility relocations, and weather constraints. On 9/21/18 an email was sent to Reith -Riley from the City of Carmel stating that construction will be postponed on this project until 2018. Once it was confirmed that all utility relocation efforts were completed, construction was able to begin on May 15, 2018. Since the project was pushed into 2018 Rieth- Riley has submitted escalation costs for material, labor, equipment, trucking, etc. All associated costs have been included as part of this change order. This change order increases the contract price by $45,363.51 which is 2.86% of the original contract price of $1,588,508.70. SCHEDULED ADJUSTMENT ITEM AMOUNT (+) OR (-) DAYS New 115 — 2018 Escalation Costs $45,363.51 11. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: R.F.P.: N/A W.D.C. No.: N/A Other: The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $1,632,382.23 Contract Price will be increased/decreased by this Change Order $� 45,363.51 New Contract Price including this Change Order $1,677,745.74 AR— 6 Version 2016-0&31 cz, CITY OF CARMEL TO: CONTRACT CHANGE ORDER NO.: 8 Chris Ogg DATE: 11/19/18 One Civic Square PROJECT NAME: 16 -ENG -35 Carmel, IN 46032 CITY REQ. NO.: N/A CITY PO NO.: 100624 — General Obligation Bond CITY PO DATE: 8/2/2017 I. You are directed to make the following changes in this Contract: (Brief Description) According to the contract documents for the 966' Street and Hazel Dell RAB project, the original project milestones were as follows: Project Start Date: 8/18/17 Substantial completion Date: 11/29/17 Completion Date: 12/13/17 Upon the expected start date of 8/18/17 all the necessary Right -of -Way had not yet been secured and most of the utilities had not yet been relocated. Great efforts were made in September between the City of Carmel and property owner Martin Marietta to try and obtain a right of entry in hopes of beginning construction yet in 2017. An onsite meeting was held on 9/20/17 to discuss the obstacles of being able to construct the RAB this late in the season without all necessary RW agreements, remaining utility relocations, and weather constraints. On 9/21/18 an email was sent to Reith -Riley from the City of Carmel stating that construction will be postponed on this project until 2018. Once it was confirmed that all utility relocation efforts were completed, construction was able to begin on May 15, 2018. Since the project was pushed into 2018 Rieth- Riley has submitted escalation costs for material, labor, equipment, trucking, etc. All associated costs have been included as part of this change order. This change order increases the contract price by $45,363.51 which is 2.86% of the original contract price of $1,588,508.70. SCHEDULED ADJUSTMENT ITEM AMOUNT (+) OR (-) DAYS New 115 — 2018 Escalation Costs $45,363.51 11. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: R.F.P.: N/A W.D.C. No.: N/A Other: The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $1,632,382.23 Contract Price will be increased/decreased by this Change Order $� 45,363.51 New Contract Price including this Change Order $1,677,745.74 AR— 6 Version 2016-0&31 Contract Time Prior to this Change Order 74 Days 12/13/17 Completion Date Net increased/decreased resulting from this Change Order 0 Days Current Contract Time including this Change Order 74 Days 12/13/17 Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are The Above Changes Are Approved: Recommended yccepted: 63) CHA Rieth-Rile Construction ENGINEER CONTRACTOR es Bra' rd, M 300 S. Meridian Street 1751 W. Minnesota Street Kj Address Address Ma1 n B , Member Indianapolis, IN 46225 Indianapolis, IN 46221 Li n, Member City/State/Zip City/State/Zip remy ashm , PE, City Engineer By:.icr�rr, T Phone: 317-407-3760 Phone: hristine S. auley, Clerk - Treasurer Date: 11/19/18 Date: I t- Z 1 • l $ Date: AR -6 Version 201648-31 AR-6 Version 20l "8-31 'MULE ` CoNsmucvw Co, INc. New 100% Quality • 100% Employee Owned - Over 100 Years LETTER OF TRANSMITTAL TO: CHA Companies DATE: 11/9/18 300 S. Meridian St Indianapolis, IN 46225 PROJECT: 16 -ENG -35 96t" & Hazel Dell JOB #: RR Job# 3200723 ATTN: Brian Andres RE: 2018 Escalation Notes/Remarks: The following pricing is based upon the revised projects costs due to delays in commencement of the project. Item I Description Quantity I Unit I Unit Price I Extension EWA 12018 ESCALATION 1.00 1 LS 1 $45,363.51 $45,363.51 CC: 3200723 - Job File Eric Holmes, RR Superintendent Chris Ogg PE, Carmel Asst. City Engineer Signed: Jeff M , . Project Manager P.O. Box 276 •1751 W. Minnesota St, • Indianapolis, IN 46206 Phone: (317) 634.5561 • www,rieth-dley.com LABOR 2017 Rate Classification Delta Combo Laborer Regular $44.58 Overtime Finisher Regular 62 Overtime Foreman Regular $94.55 Overtime Laborer Regular $1.20 Overtime Mechanic Regular $54.49 Overtime Operator Regular $39.18 Overtime C1A Tech Regular 124 Overtime Superintendent Regular $179.80 Overtime Teamster Regular $1.20 Overtime Hours 2017 Rate 2018 Rate Delta Total 124 $44.58 $45.73 $1.15 $142.60 62 $59.46 $60.99 $1.53 $94.55 496 $40.18 $41.38 $1.20 $595.20 248 $53.04 $54.49 $1.45 $359.60 248 $39.18 $40.38 $1.20 $297.60 124 $51.54 $52.99 $1.45 $179.80 677 $37.68 $38.88 $1.20 $812.40 338 $49.29 $50.74 $1.45 $490.10 12 $39.18 $40.38 $1.20 $14.40 6 $51.54 $52.99 $1.45 $8.70 342 $51.71 $53.26 $1.55 $530.10 171 $68.74 $70.66 $1.93 $329.17 18 $37.68 $38.88 $1.20 $21.60 9 $49.29 $50.74 $1.45. $13.05 193 $40.68 $41.88 $1.20 $231.60 96 $53.79 $55.24 $1.45 $139.20 240 $43.28 $44.43 $1.15 $276.00 120 $57.51 $60.99 $3.48 $417.00 $4,952.68 WORKERS COMPENSATION $283.29 BODILY INJURY/ PROPERTY DAMAGE INSURANCE $287.26 STATE UNEMPLOYMENT $190.68 FEDERAL UNEMPLOYMENT $19.81 $5,733.71 EQUIPMENT Classification Hours 2017 Rate 2018 Rate Delta Total Paver Curb & Gutter 40 $91.68 $94.43 $2.75 $110.01 D4 Dozer 30 $36.17 $37.25 $1.09 $32.55 320 / 325 Excavator 16 $76.94 $79.25 $2.31 $36.93 580 Backhoe 124 $32.34 $33.31 $0.97 $120.30 Skid Steer 23 $39.65 $40.84 $1.19 $27.36 10' Asphalot Paver 85 $154.08 $158.70 $4.62 $392.91 66" Roller 30 $45.13 $46.48 $1.35 $40.61 Distributor Truck 85 $41.31 $42.55 $1.24 $105.33 Mechanics Truck 17 $24.29 $25.02 $0.73 $12.39 Superintendent Truck 289 $14.99 $15.44 $0.45 $129.93 1 Ton Truck 25 $14.20 $14.63 $0.43 $10.65 1.5 Ton Truck 186 $15.94 $16.41 $0.48 $88.92 Foreman Track 433 $12.08 $12.44 $0.36 $156.87 Tractor/Trailer 90 $71.06 $73.19 $2.13 $191.85 Water/ Fuel Truck 159 $27.48 $28.31 $0.82 $131.10 $1,587.71 TRUCKING Classification Hours 2017 Rate 2018 Rate Delta Total Triaxle Regular 175 $93.00 $96.00 $3.00 $525.00 Overtime 87 $112.00 $115.00 $3.00 $261.00 $786.00 ASPHALT MATERIAL 19 HMA, 4, 76, SURFACE, 9.5 mm 20 HMA, 4, 76, INTERMEDIATE, 19.0 mm 21 HMA, 4, 64, BASE, 25.0 mm 22 HMA, 5, 76, INTERMEDIATE, OG 19.0 mm 23 HMA FORTEMPORARY PAVEMENT, D (Surface) 23 HMA FORTEMPORARY PAVEMENT, D (Inter) 23 HMA FOR TEMPORARY PAVEMENT, D (Base) 28 HMA FOR SIDEWALK (Inter) 28 HMA FOR SIDEWALK (Surface) SUBCONTRACTORS Fox Contractors (see attached) Quantity 580 966 2,619 1,058 57 95 228 47 27 2017 Rate 2018 Rate $53.66 $61.76 $40.40 $45.60 $35.50 $40.24 $36.35 $40.02 $48.26 $56.37 $36.26 $41.46 $35.50 $40.24 $37.68 $43.04 $38.65 $46.00 Delta Total $8.10 $4,698.00 $5.20 $5,023.20 $4.74 $12,414.06 $3.67 $3,882.86 $8.11 $462.27 $5.20 $494.00 $4.74 $1,080.72 $5.36 $251.92 $7.35 $198.45 $2Q�.4B $23,330.89 FROM PG ADJUSTMENT CALCULATION $13,925.19 TOTAL $45,363.51 The monthly PG asphalt binder index (BI) is determined by averaging the weekly selling prices in Indiana as listed in the Poten & Partners Asphalt Weekly Monitor publication. -CONTRACT AWARD MO ACTUAL CONST. PERIOD 4VG = $478 INDIANA DEPARTMENT OF TRANSPORTATION PG 64-22 AVERAGE MONTHLY PRICE Year / Month * Binder Index (BI) (per ton or Mg) Year / Month Binder Index (BI) (per ton or Mg) 2013 2016 January $540.00 January_ $355.00 February $526.00 February $335.00 March $531.00 March $313.00 April $534.00 Aril $309.00 May $537.00 May $305.00 June $535.00 June $298.00 Jul $535.00 Jul $303.00 August $539.00 August $293.00 September $537.00 September $285.00 October $532.00 October $284.00 November $523.00 November $284.00 December $521.00 December 1 $284.00 2014 2017 January $521.00 January $288.00 February $521.00 February $303.00 March $526.00 March $322.00 April $525.00 Aril $330.00 May $537.00 May $332.00 June $551.00 June $330.00 Jul $565.00 Jul $329.00 August $575.00 August $327.00 Se tember $579.00 September $327.00 October $576.00 October $327.00 November $559.00 November $327.00 December $547.00 December $330.00 2015 2018 January $517.00 January $340.00 February $481.00 February $347.00 March $456.00 March $364.00 April $446.00 Aril $379.00 May $443.00 Ma $405.00 June $442.00 June $444.00 <- July $442.00 Jul $480.00 Au ust $440.00 August $510.00 September $430.00 September $512.00 October $401.00 October $512.00 November $373.00 November December $365.00 December The monthly PG asphalt binder index (BI) is determined by averaging the weekly selling prices in Indiana as listed in the Poten & Partners Asphalt Weekly Monitor publication. -CONTRACT AWARD MO ACTUAL CONST. PERIOD 4VG = $478 Indiana Department of Transportation Rev. 08-07-08 PG Asphalt Binder Material Cost Adjustment Calculation Contract No: 96th Street & l Letting Date: August 2, 2017 Month 8 Year of Hazel DelCalculation: JUNE - AUG 2018 LI = 327 BI = 478 (Bl - LI)/LI = 0.462 Absolute Value of (BI - LI)/LI > 0.101? YES MPA Calculated Below For Price Increase: MPA = (Q x Pb)/100 x LIx[(BI - LI)/LI - 0.1001 For Price Decrease: MPA = (Q x Pb)/100 x LI x [(BI - LI)/LI t 0.100) MPA = Mixture Payment Adjustment; Q = Quantity of HMA pay Item placed during the month; Pb = Percent of virgin asphalt binder from DMF or IMF; LI = Asphalt binder index for the contract (= BI for month prior to letting); BI = Asphalt binder index for the month MPA Data HMA Pay Q Pb MPA Pay Item Description DMF or JMF Item No. (Ton or Mg) 19 HMA, 4, 76, SURFACE, 9.5 MM 580.00 173450 D 4.8 3,293.47 20 HMA, 4, 76, INTERMEDIATE, 19.0 MM 966.00 183453 D 1.0 4,571.11 21 HMA, 4, 64, BASE 25.0 MM 2619.00 183454 D 3.3 10,224 31 22 11 MA, 5, 76, INTERMEDIAT[, OG 19.0 MM 1058.00 163458 D 2.5 3.129.04 23 HMA, FOR TEMPORARY ASPHALT - SURF 57.00 02-610 D 5.6 377.61 23 HMA, FOR TEMPORARY ASPHALT - BASE 228.00 183454D 3,3 890.09 23 HMA, FOR TEMPORARY ASPHALT - INTERM 95.00 183453 D 4.0 449.54 28 HMA FOR SIDEWALK - INTERM 47.00 183451 D 3.9 216.84 28 HMA FOR SIDEWALK - SURF 27.00 02-610 D 5.6 178.87 0.00 0.00 0.00 0.00 0.00 0.00 For 1 i JUNE - AUG 2018 Item No. Payment Adjustment, PG Asphalt Binder = $23,330.89 (Sum of MPA) n z z 0 Fox Contractors Corp Total project summary breakdown for 2018 Increases LABOR Description Total Hrs 2017 2018 diff Total ECSPF Code Description $91.00 Total Hrs 2017 2018 diff Total LL1 Laborer Category I Reg 637.00 $37.98 $39.18 $1.20 $764.40 $90.00 $92.00 OT 159.00 $49.74 $51.19 $1.45 $230.55 LLC Laborer Combo Reg 288.00 $44.12 $45.57 $1.45 $417.60 $3.00 $360.00 OT 72.00 $58.95 $60.78 $1.83 $131.76 L01 Operator Group I Reg 978.00 $51.71 $53.26 $=.55 $1,515.90 ELSSLG Loader Skid Steer - Track OT 244.00 $68.74 $70.66 $1.92 $468.48 LOF Foreman - Operator Reg 468.00 $54.71 $56.26 $1.55 $725.40 20.00 $10.00 OT 117.00 $70.24 $72.16 $1.92 $224.64 LTl Teamster Wage Class 1 Reg 60.00 $43.28 $44.13 $0.85 $51.00 $335.00 $3.00 OT 15.00 $57.51 $58.59 $1.08 $16.20 $1.00 $360.00 ETLT Truck Lowboy Tractor 75.00 $97.00 subtotal $4,545.93 $150.00 ETLR Truck Lowboy Trailer 75.00 $34.00 GA Insurance $84.02 $75.00 ETM Truck Mechanic - Drain Crew 20.00 $71.00 $72.00 W/C $101.06 ETPF Truck Pickup Forman 585.00 $26.00 $26.50 $0.50 FICA $347.77 Truck Pickup Job 25.00 $20.00 $20.50 $0.50 $12.50 FUTA $36.37 SUTA $380.04 Total Labor $5,495.19 EQUIPMENT Code Description Total Hrs 2017 2018 diff Total ECSPF Compctr Stat Pad Foot 60.00 $91.00 $93.00 $2.00 $120.00 ECVSD Compctr Vib Smooth Drum 78.00 $91.00 $93.00 $2.00 $156.00 ED4 Dozer D4 Size 42.00 $90.00 $92.00 $2.00 $84.00 ED6 Dozer D6 Size 55.00 $138.00 $140.00 $2.00 $110.00 ED6GPS Dozer D6 w -GPS 120.00 $209.00 $212.00 $3.00 $360.00 EG140GPS Grader 140 w -GPS 75.00 $169.00 $171.00 $2.00 $150.00 EL3CY Loader 3CY Size 234.00 $128.00 $131.00 $3.00 $702.00 ELSSLG Loader Skid Steer - Track 60.00 $86.00 $87.00 $1.00 $60.00 EMCHIP Misc Chipper 10.00 $123.00 $125.00 $2.00 $20.00 EMSBOX Misc Stone Box 20.00 $10.00 $11.00 $1.00 $20.00 EMVACTOR Vactor 10.00 $55.00 $57.00 $2.00 $20.00 ENC900 Trencher Chain Tesmec 900 20.00 $332.00 $335.00 $3.00 $60.00 ETDS Truck Dump Single 360.00 $50.00 $51.00 $1.00 $360.00 ETLT Truck Lowboy Tractor 75.00 $97.00 $99.00 $2.00 $150.00 ETLR Truck Lowboy Trailer 75.00 $34.00 $35.00 $1.00 $75.00 ETM Truck Mechanic - Drain Crew 20.00 $71.00 $72.00 $1.00 $20.00 ETPF Truck Pickup Forman 585.00 $26.00 $26.50 $0.50 $292.50 ETPJ Truck Pickup Job 25.00 $20.00 $20.50 $0.50 $12.50 EX330 Excavator 336 Size 360.00 $185.00 S191.00 $6.00 $2,160.00 EXB Excavator Backhoe 72.00 $64.00 $66.00 $2.00 $144.00 Total Equipment $5,076.00 TRUCKING Code Description Total Hrs 2017 2018 diff Total UTRIAXLE Hourly Hauling 736.00 $92.00 $95.00 $3.00 $2,208.00 UTRIAXLEOT Hourly Hauling Overtime 184.00 $110.00 $113.00 $3.00 $552.00 Total Trucking $2,760.00 ITEM NOT USED MATERIAL Total t 2017 diff Total �^�App/^�Cppoppd�^e�l� pa,�..,,��,�.�������� �{Description MBORRGW 'dirt le" le" � '� ��2p0/1�/8� $18.W p /�/� $-,&-w 53,816.00. etti e i w-r,Q MGTGTRR Geotextile for Rip Rap roll 1 $338.00 $385.00 $47.00 $47.00 MGTGTUD Geotextlle for Underdrain roll 4 $117.00 $126.00 $9.00 $36.00 MAGTSNM Topsoil ryd 511.00 $20.00 $21.00 $1.00 $511.00 Total Material $594.00 ** all other material suppliers (pre -cast, pipe, aggregates, castings) held their pricing for spring 2018. Piete 1 Grand Total (No Mark-up) $13,925.19 Memo To: Doug Haney, Corporation Counsel From: Lisa Scott CC: Jeremy Kashman Date: 11/28/18 Re: C.O. #8 - 96"' & Hazel Dell RAB Project #16 -ENG -35 Doug, please find attached 1 original of same change order for project #16 -ENG -35. Please review & initial for the next BPW Meeting. Change Order #8- Original Contract Amount: $1,588,508.79 Increase: $45,363.51 New Contract Amount $1,677,745.74 Thank you, Lisa Scott 0 Page 1