HomeMy WebLinkAboutDaily Field Report_2018.10.12Contractor: JG Morris Jr. Weather: Sunny Temperature (°F): 68 Arrival Time: 13:00 Departure Time: 14:00 ATC Rep: Craner, Laura R Date: 10/12/2018 A. Description of Work: Proofroll B. Location Details: Building pad C. Tests Performed: Proofroll D. Equipment and Crew: Fully loaded tri­axle E. Problems/Non­Compliance/Failing Tests Discrepancy Number Non­Compliance Who Advised Status Resolution Description 1 Specs. Available On­Site: Yes No Plans Available On­Site: Yes No Request for other information; specs./plans, mill certifications, details or manufacturer's literature: Remarks or Comments: The ATC representative arrived on site at 13:00 as requested by JG Morris. Upon arriving at site, ATC representative checked in with Sammy. ATC representative was informed of work requiring testing and inspections. The area being proof­rolled included building pad. The equipment utilized for proof­rolling consisted of fully loaded tri­axle. Deflection was observed. Soft soil conditions were observed at throughout the building pad. The soft sub­grade soils were silty clay. Material removed extended to a depth of 0 and was from 0 to 0. Due to excessive pumping and deflection, the ATC engineer was notified. It is our recommendation that the soil be dried and another proofroll be performed before work continues.. The area(s) was/were not approved. Any rainfall event that occurs after the proof­roll observation may impact the condition of any exposed sub­grade. It is our recommendation that if a rainfall event occurs after the proof­roll observation, the soils should be re­evaluated by ATC prior to further work. Before departing the site, ATC representative notified Sammy of field inspection results. ✔ ✔ Daily Field Report Report #: DRPO­000001 7988 Centerpoint Drive Suite 100 Indianapolis, IN 46256 Phone: 317­579­4031 Fax: 317­849­4278 Client: J G Morris Construction ., . ., YY . Project: 170MT00382 Belle Tire, Carmel Page 1 of 3 2 The area(s) was/were not approved. Any rainfall event that occurs after the proof­roll observation may impact the condition of any exposed sub­grade. It is our recommendation that if a rainfall event occurs after the proof­roll observation, the soils should be re­evaluated by ATC prior to further work. Before departing the site, ATC representative notified Sammy of field inspection results. Upload Image/PDF: Upload Image/PDF: Daily Field Report Report #: DRPO­000001 7988 Centerpoint Drive Suite 100 Indianapolis, IN 46256 Phone: 317­579­4031 Fax: 317­849­4278 Client: J G Morris Construction ., . ., YY . Project: 170MT00382 Belle Tire, Carmel Page 2 of 3 2