HomeMy WebLinkAboutDaily Field Report_2018.10.19Contractor: JG Morris
Weather: Sunny Temperature (°F):
Arrival Time: 13:00 Departure Time: 14:00
ATC Rep: Filley, Nicolas
Date: 10/19/2018
A. Description of Work: Proofroll B. Location Details: Building pad
C. Tests Performed: Proofroll
D. Equipment and Crew: Fully Loaded Tri Axle
E. Problems/NonCompliance/Failing Tests
Discrepancy
Number
NonCompliance Who Advised Status Resolution Description
2 Soft soils showing excessive
pumping and rutting
Project Manager Open
Specs. Available OnSite: Yes No Plans Available OnSite: Yes No
Request for other information; specs./plans, mill certifications, details or manufacturer's literature:
Remarks or Comments:
The ATC representative arrived on site at 13:00 as requested by JG Morris. Upon arriving at site, ATC representative checked in with
JG Morris. ATC representative was informed of work requiring testing and inspections.
The area being proofrolled included entire building pad. The equipment utilized for proofrolling consisted of fully loaded tri axle.
Soft soil conditions were observed at the east side of the building pad. The soft subgrade soils were silty sand.
Due to excessive pumping and deflection, the ATC engineer was notified. It is our recommendation that the soils be aerated and
allowed to dry.
The area was not approved.
Any rainfall event that occurs after the proofroll observation may impact the condition of any exposed subgrade. It is our
recommendation that if a rainfall event occurs after the proofroll observation, the soils should be reevaluated by ATC prior to further
work.
Before departing the site, ATC representative notified JG Morris of field inspection results.
✔ ✔
Daily Field Report Report #: DRPO000003
7988 Centerpoint Drive
Suite 100
Indianapolis, IN 46256
Phone: 3175794031
Fax: 3178494278
Client:
J G Morris Construction
., .
., YY .
Project:
170MT00382
Belle Tire, Carmel