HomeMy WebLinkAboutCJ181033.0187DAILY SUMMARY REPORT
Report Number:CJ181033.0187
Service Date:12/10/18 7770 W New York St
Report Date:12/19/18 Indianapolis, IN 46214-2988
317-273-1690
Client Project
Gibraltar Construction Corp West Park: The Groves
Attn: Douglas Perry 3030 West 116th St.
2932 N Webster Ave Carmel, IN 46032
Indianapolis, IN 46219
Project Number: CJ181033
Services: As requested, a representative of Earth Exploration, Inc. was on project site to perform construction materials testing
services.
Earth Exploration, Inc. Rep.: Jamie Conwell
Reported To:Gibraltar Construction
Contractor:
Report Distribution:
(1) Gibraltar Construction Corp, Douglas
Perry
(1) City of Carmel IN, Mike Sheeks
(1) Johnson Wilbur Adams, Inc., Michael Wilbur (1) Smith Group JJR, Jessie Fink Reviewed By:____________________________________
Jeremy Clem
Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CT0001, 10-16-13, Rev.10 Page 1 of 1
FOUNDATION OBSERVATIONS
All tests meet specifications See Foundation Observation Report for details
Some tests do not meet specifications See Construction Observation Report
All tests do not meet specifications None Performed
IN-PLACE DENSITY TESTS
All tests meet specifications See In-Place Density Test Report for details
Some tests do not meet specifications Passing retests obtained
All tests do not meet specifications None performed
CONCRETE, GROUT, MORTAR SAMPLING/TESTS
Tests performed:Slump
Slump
Entrained Air Temperature Unit Wt.Yield
Number of specimens cast Total Quantity Yd3
Specimen Type:Cylinders Beams Motar Cubes Grout
Prisms Other
None Performed
ASPHALT SAMPLING/TESTS
Tests performed:Nuclear Density Temperature Thickness Bulk Sampling
Number of Tests Total Quantity Tons
Core Sampling Number of Cores Marshall Density Extraction/Gradation
None Performed Stability / Flow
Weather: Cloudy, low 30’s
See attached Daily Construction Observation Report.
DAILY SUMMARY REPORT
Report Number:CJ181033.0187
Service Date:12/10/18 7770 W New York St
Report Date:12/19/18 Indianapolis, IN 46214-2988
317-273-1690
Client Project
Gibraltar Construction Corp West Park: The Groves
Attn: Douglas Perry 3030 West 116th St.
2932 N Webster Ave Carmel, IN 46032
Indianapolis, IN 46219
Project Number: CJ181033
Services: As requested, a representative of Earth Exploration, Inc. was on project site to perform construction materials testing
services.
Earth Exploration, Inc. Rep.: Jamie Conwell
Reported To:Gibraltar Construction
Contractor:
Report Distribution:
(1) Gibraltar Construction Corp, Douglas
Perry
(1) City of Carmel IN, Mike Sheeks
(1) Johnson Wilbur Adams, Inc., Michael Wilbur (1) Smith Group JJR, Jessie Fink Reviewed By:____________________________________
Jeremy Clem
Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
AF0001, 10-16-13, Rev.3 Page 1 of 1
Weather: Cloudy, low 30’s
1.Earth Exploration, Inc., a Terracon Company (Earth) was on site at the request of Bill with Gibraltar
Construction to perform a subgrade inspection. Upon arrival Earth checked the subgrade along the north
east corner of the building for future sidewalk and concrete paving. It was observed that the subgrade was
frozen and not suitable for the placement of stone or concrete. Earth notified Bill of condition and work was
cancelled until later date.