IA
EXHIBIT O
CONTRACT CHANGE ORDER
TO: CONTRACTOR
PKS Construction, Inc.
450 S. Ritter Ave, Suite 1A
Indianapolis, IN 46219
CO No.:
04
Date:
12/19/18
Contract No.:
Bid Package #6
Project No.:
17080.000
Project Name:
City of Carmel
Brookshire Golf
Clubhouse, Bath House &
Pool Project
12120 Brookshire
Parkway
Carmel, IN 46033
FROM: OWNER
City of Carmel
City Hall — Third Floor
One Civic Square
Carmel, Indiana 46032
Ratio Architects, Inc. ("Architect")
101 South Pennsylvania Street
Indianapolis, IN 46204
I. You are directed to make the following changes in the Contract: (Brief Description)
SCHEDULE
ITEM AMOUNT (+) OR (-) DAYS
1. COR #040 — SI -016 to furnish and
install 2 sets of wood framed stairs
per SI -016. $12,298 0
2. COR #060 — furnish and install Audio
Visual Scope of work per Sensory
Technologies proposal for Phase 1. $35,065 0
1
City oJ'Carme! Trade Contractor Agreement — Exhibit " O "
11. The following referenced documents further describe the changes outlined in Paragraph 1, and are
to be considered a part of this Change Order:
RFP No.: CCD No.:
List of Attachments:
Other: S1-016
The changes result in the following adjustment of the Contract Price and Contract Time:
Contract Sum prior to this Change Order ................................... $831,979
Contract Sum will be increased/decreased by this Change Order....... $ 47363
New Contract Sum including this Change Order ........................... $879,342
Contract Time Prior to this Change Order ..:................................... No Change Days No Change Completion Date
Net increased/decreased resulting from this Change Order............ 0 Days
Current Contract Time including this Change Order ...................... No Change Days No Change Completion Date
The changes above in the Contract Price and Time include all direct, indirect, delay, acceleration, loss of
efficiency and impact costs and time impacts incurred or encountered by Contractor resulting from the
performance of the change work. Contractor acknowledges that this Change Order constitutes
compensation in full for any delays, acceleration, or loss of efficiency encountered by Contractor in the
performance of the Work through the date of this Change Order.
The Above Changes Are
Recommended: ARCHITECT
BY
Name: Jake Plummer, RATIO
Date: 12/21/18
The Above Changes Are
Accepted: CONTRACTOR
i:� I
Name: David Kojetin
Date: 12/20/2018
The Above Changes Are
Approved: OWNER
Name:
Date:
+� PKS - CCO #4
Approved and Adopted this day of 2010.
CITY OF CARMEL, INDIANA
By and through its Board of Public Works and Safety
BY: 62:e4 .
James Brainard, Presiding Officer
Date:
AT T
Jhristine S. Pauley, Olerk-Tre�syf�er/�
Date: � / 7