HomeMy WebLinkAbout12-18-1987ri r' i 8 19U?
COCHRAN AGENCIES, INC.
Professional Insurance Services
December 18, 1987
Mr. Charles Kiphart
Department of Community De�relopment
40 East Main Street
Carmel, Indiana 46032
Re: Letter Dated 12/14/87
Dear Mr. Kiphart:
In response to your letter and our conversation I'm writing,
as requested, to address the issues as documented in your letter.
I'll address each item individually as they pertain to our project
at 1118 S. Rangeline Road.
1) Drainage Facilities
Discussions were made between my contractor and the City
Engineer on this issue and I thought all the problems
were resolved. We will recontact the City Engineers Office
and resolve all problems and will resubmit new site plans.
2) Landscaping
We will comply with the plans as submitted. Part of the
landscaping will start this month. The balance will be
completed by 4/15/68-
3) Trash Enclosure
Estimated completion date is 12/23/87.
4) Curbing
Poured curbing will present an economic burden. Aq alternative
approach and new site plan will be presented to the B.Z.A.
Keep in mind this curbing is in the rear of Building and can't
be seen from Rangeline. The state of the art for strom control
curbing is prefabricated concrete "nail downs" curbing. The
reason it may be replaced if damaged and may be altered if
required.
1118 S. Rangeline Rd 0 Carmel, Indiana 46032 0 (317) 844-5017