HomeMy WebLinkAboutRieth-Riley/Eng/CO #6/68,110.98/6th Street and Keystone Parkway – Project #16-ENG-05 City of Carmel Project 16-ENG-05
96th Street and Keystone Parkway
CHANGE ORDER # 06
This change order covers some items of additional work that came up during construction. See the detailed description on the
next page.
Contract Price prior to this Change Order $28,697,297.92
Contract Price will be increased/decreased by this Change Order $68,110.98
New Contract Price including this Change Order $28,765,408.90
Amount Adjusted Contract Cumulative% Change
Price from Original Contract
Original Contract $28,793,000.00 $28,793,000.00 N/A
CO 01 $25,843.67 _$28,818,843.67 0.09%
CO 02 $3,481.80 $28,822,325.47 0.10%
CO 03 $0.00 $28,822,325.47 0.10%
CO 04 $46,996.32 $28,869,321.79 0.26%
CO 05 ($172,023.87) $28,697,297.92 -0.33%
CO 06 $68,110.98 $28,765,408.90 -0.10%
CITY OF CARMEL
TO: CONTRACT CHANGE ORDER NO.: 6
DATE: 2/12/2019
PROJECT NAME: 16-ENG-05
CITY REQ.NO.:
CITY PO NO.:
CITY PO DATE:
Cizt
I. You are directed to make the following changes in this Contract: 4
The purpose of this change order is to address changes to the contract.
Work covered in this change order includes the following:
Sawcut for Temporary HMA Widening
During removal of the existing median shoulder along Keystone Parkway,the contractor discovered inadequate
pavement thickness remaining at the edge of the removal.The solution was to cut along the edgeline,farther into the
mainline pavement,in search of sufficient thickness.Removing this additional strip of existing pavement exposed
sufficient thickness of pavement to remain in place.This required a total of 1498 LFT of saw cutting.
Light Pole,Remove
Along the west side of the Penske parcel,twelve light poles remained within the new right of way limits.It was not in
the contract for these light poles to be removed.In order for construction work to proceed,the contractor could not wait
for the parcel owner to remove the light poles themselves.James H.Drew provided a price to remove these poles and
move them to a storage location on the property.Three additional light poles in two other parcels,one at the Burger
King parcel and two at the AZR parcel,also needed to be removed.James H.Drew agreed to perform the work at the
same price they quoted for removal of the Penske light poles.The total number of light poles removed is 15 EACH.
Temporary Construction Panel Sign—Relocate
James H.Drew had planned to remove an existing box truss sign structure on SB Keystone Parkway at I-465.City of
Cannel requested that the temporary construction panel sign that had been ground mounted on SB Keystone be
relocated to the existing box truss for better visibility during early construction phases.Due to a miscommunication,JH
Drew had a crane scheduled to remove the box truss.This crane was used to relocate the temporary panel sign while on
site.
Renascent Additional MOB
Due to delays in Right of Way acquisition,Renascent was unable to complete demolition of all four parcels with one
mobilization.These delays resulted in two additional mobilizations for the contractor,one for the Burger King/Chase
Bank parcel and one for the Marathon parcel.
Maintaining Traffic-Priority Way RAB
With the delays to the start of construction on the Keystone Parkway Corridor contract,the Priority Way Intersection
contract was completed first.This delay resulted in phasing issues between the two projects.Additional MOT was
required on the newly constructed Priority Way Roundabout in order for the traveling public to safely transition from
the roundabout into the MOT setup currently in place along 96th Street between Priority Way and Keystone Parkway.
Houses and Buildings,Remove,Parcel No.10-Additional
The demolition plan for Parcel 10 showed leaving the block walls and brick building in the SE corner of the parcel.This
plan also indicated leaving a 40 FT strip of asphalt pavement along the east side and a 25 FT strip of asphalt pavement
along the south side of the parcel.During the permit process,it was questioned as to why it was necessary to leave these
areas intact.Upon further investigation with the Design Engineer and City of Cannel,it was deemed that leaving these
areas was not necessary. Therefore,Renascent was instructed to demo these areas as well.This was not in their original
bid,so a price was submitted and approved for this additional work.
16 IN Gate Valve
It was in the original scope of work for the TRICO sanitary sewer force main in the NW corner of the 96th Street and
Keystone Parkway intersection to be relocated by the Contractor.This work was originally planned to occur in Phase 3,
but it was in conflict with a storm sewer structure that was to be installed in Phase 2.It was also discovered that the
location of the tie-in would fall under the ramp that was to be built in Phase 2.Therefore,it was concluded that part of
Version 2016-08-31 AR-6
the relocation had to occur in Phase 2.This required some re-design of the force main relocation process,which resulted
in the need for a new 16 IN Gate Valve in order to phase the relocation.
Box Culvert Access Points
Castings for Storm STR 810A and a box culvert access point just to the SE had to be adjusted approximately 2.5-3.0
FT in order to match the proposed grade in the area.This adjustment was not accounted for in the re-design of the box
culvert structure.Additional pre-cast sections as well as labor and equipment make up the additional cost of this work.
Overhead Sign Structure,Monotube—Additional Cost
Due to changes in the panel signs covered in Construction Change No.9,the height of sign structure GDO-3 uprights
were adjusted to compensate.Also,the span of sign structure GDO-3 was adjusted to achieve clear zone compliance.
This cost change is material costs passed on from the supplier plus appropriate markups.
Construction Engineering—Additional
SurveyTech has incurred additional costs for additional staking due to Construction Changes,utility relocations,and
property acquisition.Additional staking on the SW corner of the project for IPL relocation was also recently required.
This item covers that additional costs of this work.
Connect Penske Lot Drain to Box Culvert(Time and Materials)
The construction plans indicated connection of Penske Chevrolet storm drains to new ditch structures.The storm drain
in question(west of entrance)had no such direction in the construction drawings.This Penske storm drain could not be
connected to the new ditch structure(STR 496)due to elevation restrictions.After discussion at a Progress Meeting,
City of Cannel agreed to proceed with direct connection to the box culvert.The attached proposal covers the T&M
work necessary to make this connection.
Sanitary ARV Structure—Adjust to Grade
The casting for the Sanitary ARV structure(installed by others)at MSE Wall 5 had to be lowered in order to match the
grade of the moment slab in this area.The attached proposal covers the time and materials required to complete this
work.
Testing for Contaminated Materials—Expedited Test Results
Blue River Environmental indicated that the results of the testing for contaminated materials could be expedited at an
additional cost.The normal expectation for test results is 5-7 days($1,100 per test).The two tiers for expedited results
are 24 hours($2,755.44 per test)and 48 hours($2,143.12 per test).City of Cannel elected to go with the 48 hour
expedited results so that work could proceed ahead of the IPL relocation scheduled for late winter 2019.Cost difference
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+)OR(-)DAYS
0339 $1,384.40
0340 $4,377.90
0341 $5,707.45
0342 $7,762.80
0343 $5,505.82
0344 $9,387.11
0345 $7,975.11
0346 $2,759.81
0347 $5,168.29
0348 $3,240.29
0349 $5,103.35
0350 $2,436.81
0351 $7,301.84
II. The following referenced Documents further describe the changes outlined in Paragraph I,and
are to be considered a part of this Change Order: R.F.P.: W.D.C.No.:
Other:
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $ 28,697,297.92
Version 2016-08-31 AR-6
Contract Price will be increased/decreased by this Change Order $ 68.110.98
New Contract Price including this Change Order $ 28,765,408.90
Contract Time Prior to this Change Order Days 5/31/2019 Completion Date
Net increased/decreased resulting from this Change Orde: 0 Days
Current Contract Time including this Change Ord 0 Days 5/31/2019 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time extension;
incurred at any time resulting from the performance of the changed work.
The Above Changes Are The Above Changes Are Approved:
Recommended Accepted:
American Structurepoint Inc_ Rieth-Riley Construction Co.Inc / • - o?lGu., P
ENGINEER CONTRACTOR ,`�,I Br�'•.r d, . r
7260 Shadeland Station Indianapolis,IN 46221 I.._4_
Address Address Mary Burke Member
Lop!'I"Member
Indianapolis,IN 4626 Indianapolis,IN 46221
City/State/Zip City/State/Zip Jer- Kal nan,P ., City
ngineer
By: By: ATT T:
2. 7. - )Phone: (317)401-0263 Pho e: 317) 51 00 --4-- A
stine S. Pa ey,Clerk-
Treasurer
Date: Z/Le b C1 Date: �i//i g/t 1Date: -Shelf
Version Nth-OR-1I AR-6
o American Structurepoint, Inc.
STRUCTUREPOINT
• Change Order Details
96th Street and Keystone Parkway
Description: 16-ENG-05
Construction of a roundabout interchange at the
intersection of 96th Street and Keystone Parkway,
including the reconstruction of Keystone Parkway
from I-465 to 98th Street, and reconstruction of 96th
Street from Haverstick Road to Enterprise Drive.
The Project includes new construction of a twospan
bridge over 96th Street.
Change Order: 6 Date Created: 02/11/2019
Status: Approved Date Approved:
Type: Changed Conditions
Summary: EWA Items 2018
Change Order Description: The purpose of this change order is to address changes to the contract.
Work covered in this change order includes the following:
Sawcut for Temporary HMA Widening
During removal of the existing median shoulder along Keystone Parkway, the
contractor discovered inadequate pavement thickness remaining at the edge of
the removal. The solution was to cut along the edgeline, farther into the
mainline pavement, in search of sufficient thickness. Removing this additional
strip of existing pavement exposed sufficient thickness of pavement to remain
in place. This required a total of 1498 LFT of saw cutting.
Light Pole, Remove
Along the west side of the Penske parcel, twelve light poles remained within the
new right of way limits. It was not in the contract for these light poles to be
removed. In order for construction work to proceed, the contractor could not
wait for the parcel owner to remove the light poles themselves.James H. Drew
provided a price to remove these poles and move them to a storage location on
the property. Three additional light poles in two other parcels, one at the
Burger King parcel and two at the AZR parcel, also needed to be removed.
James H. Drew agreed to perform the work at the same price they quoted for
removal of the Penske light poles. The total number of light poles removed is 15
EACH.
Temporary Construction Panel Sign -- Relocate
James H. Drew had planned to remove an existing box truss sign structure on
SB Keystone Parkway at I-465. City of Carmel requested that the temporary
construction panel sign that had been ground mounted on SB Keystone be
relocated to the existing box truss for better visibility during early construction
phases. Due to a miscommunication,JH Drew had a crane scheduled to remove
the box truss. This crane was used to relocate the temporary panel sign while
on site.
Renascent Additional MOB
Due to delays in Right of Way acquisition, Renascent was unable to complete
demolition of all four parcels with one mobilization. These delays resulted in
two additional mobilizations for the contractor, one for the Burger King/Chase
Bank parcel and one for the Marathon parcel.
Maintaining Traffic - Priority Way RAB
Change Order Details: 96th Street and Keystone Page 1 of 4 02/18/2019
Parkway
With the delays to the start of construction on the Keystone Parkway Corridor
contract, the Priority Way Intersection contract was completed first. This delay
resulted in phasing issues between the two projects. Additional MOT was
required on the newly constructed Priority Way Roundabout in order for the
traveling public to safely transition from the roundabout into the MOT setup
currently in place along 96th Street between Priority Way and Keystone
Parkway.
Houses and Buildings, Remove, Parcel No.10 -Additional
The demolition plan for Parcel 10 showed leaving the block walls and brick
building in the SE corner of the parcel. This plan also indicated leaving a 40 FT
strip of asphalt pavement along the east side and a 25 FT strip of asphalt
pavement along the south side of the parcel. During the permit process, it was
questioned as to why it was necessary to leave these areas intact. Upon further
investigation with the Design Engineer and City of Carmel, it was deemed that
leaving these areas was not necessary. Therefore, Renascent was instructed to
demo these areas as well. This was not in their original bid, so a price was
submitted and approved for this additional work.
16 IN Gate Vavle
It was in the original scope of work for the TRICO sanitary sewer force main in
the NW corner of the 96th Street and Keystone Parkway intersection to be
relocated by the Contractor. This work was originally planned to occur in Phase
3, but it was in conflict with a storm sewer structure that was to be installed in
Phase 2. It was also discovered that the location of the tie-in would fall under
the ramp that was to be built in Phase 2. Therefore, it was concluded that part
of the relocation had to occur in Phase 2. This required some re-design of the
force main relocation process, which resulted in the need for a new 16 IN Gate
Valve in order to phase the relocation.
Box Culvert Access Points
Castings for Storm STR 810A and a box culvert access point just to the SE had
to be adjusted approximately 2.5 -3.0 FT in order to match the proposed grade
in the area. This adjustment was not accounted for in the re-design of the box
culvert structure. Additional pre-cast sections as well as labor and equipment
make up the additional cost of this work.
Overhead Sign Structure, Monotube -- Additional Cost
Due to changes in the panel signs covered in Construction Change No.9, the
height of sign structure GDO-3 uprights were adjusted to compensate. Also, the
span of sign structure GDO-3 was adjusted to achieve clear zone compliance.
This cost change is material costs passed on from the supplier plus appropriate
markups.
Construction Engineering -- Additional
SurveyTech has incurred additional costs for additional staking due to
Construction Changes, utility relocations, and property acquisition. Additional
staking on the SW corner of the project for IPL relocation was also recently
required. This item covers that additional costs of this work.
Connect Penske Lot Drain to Box Culvert (Time and Materials)
The construction plans indicated connection of Penske Chevrolet storm drains
to new ditch structures. The storm drain in question (west of entrance) had no
such direction in the construction drawings. This Penske storm drain could not
be connected to the new ditch structure (STR 496) due to elevation restrictions.
After discussion at a Progress Meeting, City of Carmel agreed to proceed with
direct connection to the box culvert. The attached proposal covers the T&M
work necessary to make this connection.
Sanitary ARV Structure --Adjust to Grade
The casting for the Sanitary ARV structure (installed by others) at MSE Wall 5
had to be lowered in order to match the grade of the moment slab in this area.
The attached proposal covers the time and materials required to complete this
work.
Testing for Contaminated Materials -- Expedited Test Results
Change Order Details: 96th Street and Keystone Page 2 of 4 02/18/2019
Parkway
Blue River Environmental indicated that the results of the testing for
contaminated materials could be expedited at an additional cost. The normal
expectation for test results is 5-7 days ($1,100 per test). The two tiers for
expedited results are 24 hours ($2,755.44 per test) and 48 hours ($2,143.12
per test). City of Carmel elected to go with the 48 hour expedited results so
that work could proceed ahead of the IPL relocation scheduled for late winter
2019. Cost difference is ($1,043.12 per test) for 48 hour results.
Awarded Project Amount: $28,793,000.00
Authorized Project Amount: $28,697,297.92
Change Order Amount: $68,110.98
Revised Project Amount: $28,765,408.90
New Items
Line Number Item Unit Approved Quantity Unit Price Dollar Amount
Section: 1 -801-08400
3390 109-04299 DOL 1,384.40 $1.000 $1,384.40
FORCE ACCOUNT WORK
Reason: Saw Cut,Temporary HMA Widening
3400 202-01502 EACH 15.00 $291.860 $4,377.90
LIGHT STANDARD, REMOVE
Reason: Light Pole Removal: Penske, BK Lot, Haver Way Mall &AZR
3410 802-02475 EACH 1.00 $5,707.450 $5,707.45
SIGN, PANEL, RELOCATE
Reason: Overhead Box Truss Removal &Temp Panel Sign Relocation
3420 110-07025 EACH 2.00 $3,881.400 $7,762.80
MOBILIZATION AND DEMOBILIZATION
Reason:Additional Mobilization, Demo Parcels 11/33 and 12
3430 801-06775 LS 1.00 $5,505.820 $5,505.82
MAINTAINING TRAFFIC
Reason:Additional MOT, Priority Way
3440 202-03000 LS 1.00 $9,387.110 $9,387.11
HOUSES AND BUILDINGS, REMOVE, PARCEL NO
Reason:Additional, Parcel 10
3450 715-04836 EACH 1.00 $7,975.110 $7,975.11
GATE VALVE
Reason: 16 in. Gate Valve, Force Main Revision
3460 109-04299 DOL 1.00 $2,759.810 $2,759.81
FORCE ACCOUNT WORK
Reason: Box Culvert Access Points
3470 802-76100 EACH 1.00 $5,168.290 $5,168.29
OVERHEAD SIGN STRUCTURE, MONOTUBE
Reason: Additional Cost
3480 105-06845 LS 1.00 $3,240.290 $3,240.29
CONSTRUCTION ENGINEERING
Reason:Additional Staking
Change Order Details: 96th Street and Keystone Page 3 of 4 02/18/2019
Parkway
•
Line Number Item Unit Current Paid Quantity Unit Price Amount
1460 146 LFT 24.00 546.000 S1,104.00
PIPE,TYPE 2, CIRCULAR, 18 IN.
1530 153 LET •86.00 S82.000 -S7,052.00
PIPE, SLOTTED DRAIN, 12 IN.
2200 220 DAY 62.00 $5.000 $310.00
FLASHING ARROW SIGN
2210 221 LS 0.05 S496,615.990 $24,830.80
MAINTAINING TRAFFIC
2230 223 LET 160.00 $12.000 S1,920.00
BARRICADE, III-A
2390 239 EACH 1.00 $8,678.000 $8,678.00
CANTILEVER SIGN SUPPORT FOUNDATION, DRILLED SHAFT 36 IN.
Section Totals: $810,243.04
Project Total: $810,243.04
Summary
Current Approved Work: $810,243.04 Approved Work To Date: $9,426,859.50
Stockpile Advancement: $0.00 Stockpile Advancement To Date: $0.00
Current Retainage: $81,024.30 Retainage To Date: $942,685.95
Current Retainage Released: $0.00 Retainage Released To Date: $775,913.34
Stockpile Recovery: S0.00 Stockpile Recovery To Date: $0.00
Current Liquidated Damages: $0.00 Liquidated Damages To Date: $0.00
Current Adjustment: $0.00 Adjustments To Date: $0.00
Current Taxes: S0.00 Taxes To Date: $0.00
Current Payment: $729,218.74 Payments To Date: $9,260,086.89
Recommended for Payment:
,c,� 2/_/,--,4-.t _ - i \C-(,, 2-j Z1 ��
1
Resident Project Representative Date
Contractor Date
( e g,f L//ri'5
Owner Date
Payment Invoice: 96th Street and Keystone Page 2 of 2 02/12/2019
Parkway
CITY OF CARMEL
ENGINEERING
DEPARTMENT
Memo
To: Doug Haney, Corporation Counsel
From: Lisa Scott
CC: Jeremy Kashman
Date: 02/18/19
Re: C.O.#6 Project#16-ENG-05 96th and Keystone Parkway
Doug, please find attached eloriginals of same change order for project #16-ENG-05 96th Street and Keystone
Parkway. Please review&initial for the next BPW Meeting.
Change Order #6- Original Contract Amount: $28,793,000.00 Increase: $68,110.98 New Contract Amount:
$28,765,408.90