SECOND FLOOR DEMOLITION PLAN - AREA D
KEYED DEMO PLAN NOTES (NOTED WITH O)
1 REMOVE WALL CONSTRUCTION IN ITS ENTIRETY. PRIOR TO
DEMOLITION, CAREFULLY INVESTIGATE CONCEALED CONDITIONS TO
VERIFY THERE IS NO ACTIVE INFRASTRUCTURE. WHERE WALL TO BE
DEMOLISHED STOPS SHORT OF CEILING, CAREFULLY REMOVE WALL
CONSTRUCTION TO MINIMIZE CEILING GRID REPAIR UNLESS NOTED
OTHERWISE
2 REMOVE AND SALVAGE ALUMINUM STOREFRONT FOR FUTURE REUSE
TURN OVER TO OWNER
3 ALL ABANDONED OR UNECESSARY FIXTURES, OUTLETS OR
COVERPLATES TO BE REMOVED. MEP TRADES TO REMOVE/CAP ITEMS
AS REQUIRED SO THEY ARE FULLY CONCEALED BY NEW
CONSTRUCTIOWFINISHES. EXPOSED COVERPLATES OR CAPS ARE
NOT ACCEPTABLE UNLESS SPECIFICALLY APPROVED BY PROJECT
TEAM. THIS NOTE IS TYPICAL, THROUGHOUT ENTIRE SECOND FLOOR
4 REMOVE DOOR AND/OR GLAZING INCLUDING FRAME AND HARDWARE.
TURN HARDWARE OVER TO OWNER
5 REMOVE CEILING TILE, GRID AND SUSPENSION SYSTEM IN ITS
ENTIRETY. RE -SUPPORT REMAINING ADJACENT CEILING GRID AS
REQUIRED. COORDINATE WITH NEW CONSTRUCTION
6 REMOVE AND SALVAGE ALL UNDAMAGED CARPET AND/OR VCT FOR
REINSTALL. REMOVE ADHESIVE
T REMOVE EXISTING GYPSUM BOARD BULKHEAD IN ENTIRETY
8 EXISTING RESTROOMS TO REMAIN
9 REMOVE EXISTING WALL CONSTRUCTION AS REQUIRED FOR NEW
DOOR ROUGH OPENING
10 EXISTING CHASE TO REMAIN
11 EXISTING CONFERENCE ROOM TO REMAIN
12 EXISTING MEP ROOMS TO REMAIN
13 EXISTING WINDOWS, METAL SILL, KNEE WALL, BULKHEAD AND BLINDS
TO REMAIN. PROTECT AS REQUIRED
eS 17 ieT�
1 / D102C
14 EXISTING GYPSUM BOARD COLUMN SURROUND TO BE REMOVED AND
REINSTALLED AS PART OF NEW WORK. ADJACENT CONSTRUCTION
THAT IS BEING DEMOLISHED SHOULD BE CAREFULLY REMOVED TO
MINIMIZE REPAIR AND PATCHING. REMOVE AND RETAIN FIRE
EXTINGUISHER CABINET HOUSINGS WHERE THEY EXIST. RETAIN
EXISTING FIRE EXTINGUISHERS FOR RE -USE
15 WHERE DEMOLISHED WALL CONSTRUCTION INTERSECTS EXTERIOR
WINDOW MULLION, REFER TO DETAIL 2/D102.A
16 REMOVEAND SALVAGE DOOR, FRAMEAND HARDWARE FOR
REINSTALLATION
17 REMOVE PORTION OF WALL FOR STOREFRONT INSTALL
18 DEMOLISH ALL CEILING GRIDS AND SALVAGE UNDAMAGED CEILING
TILES FOR REUSE. SEE NEW WORK PLANS FOR NEW LAYOUT
19 NOT USED
20 REMOVE AND SALVAGE FIRE EXTINGUISHER IN ENTIRETY FOR REUSE
IN NEW CONSTRUCTION
21 REMOVE PORTION OF WALL TO DIMENSION INDICATED
22 REMOVE AND SALVAGE ALUMINUM STOREFRONT FOR REUSE IN NEW
HUDDLE ROOM
23 REMOVE AND SALVAGE ALUMINUM STOREFRONT FOR REUSE IN NEW
ELEVATOR LOBBY
24 REMOVE CARPET AND/OR VCT. REMOVE ADHESIVE
B G'
KEY PLAN
2" = V-0"
NOTES:
1. REFER T01IT SCALE SHEETS FOR PLAR KEYNOTES.
2. AREAS SHOWN IN GRAY ARE EXISTING TO REMAIN.
n
OAMERICAN
M■ STRUCTUREPOINT
INC
72605MpalanE Shtian I IMianapolle, Indiana M256
TEL 317.M7.MM I RUX317.593.0270
www.wmarmmoma.aam
GEICO CORPORATE
SECOND FLOOR
RENOVATION
101 W. 103RD ST.
INDIANAPOLIS, IN 46290
`JPUpu n,gllj/
No.
AR10900003
CERTIFIED BY
ISSUANCE INDEX
DATE:
11/21/18
PROJECT PHASE:
CONSTRUCTION DOCUMENTS
REVISION SCHEDULE
ENO. DESCRIPTION I DATE
Project Number 2017.01381
SECOND FLOOR
DEMOLITION PLAN -
AREA D
D102.D
DATE: 03/15/19