CONTRACT CHANGE ORDER
CO No.: 08
Date: 3/8/19
Contract No.: Bid Package#17
Project No.: 17080.000
Project Name: City of Carmel
Brookshire Golf
Clubhouse,Bath House&
Pool Project
12120 Brookshire
Parkway
Carmel,IN 46033
TO: CONTRACTOR FROM: OWNER
Gaylor Electric,Inc. City of Carmel
17225 Kraft Court City Hall-Third Floor
Noblesville,IN 46060 One Civic Square
Carmel,Indiana 46032
Ratio Architects,Inc. ("Architect")
101 South Pennsylvania Street
Indianapolis,IN 46204
I. You are directed to make the following changes in the Contract: (Brief Description)
SCHEDULE
ITEM AMOUNT (+)OR(-)DAYS
1. COR#068-Provide new switch
and motion sensor,including wiring
to control 3 can lights outside of the
Diddle room and S10 light dimension
per SI-055. $835 0
2. COR#073-Reduce 50 pair fiber line
from starter shack to clubhouse to 25
pair fiber line per City of Carmel IT. -$1,643 0
1
City of Carmel Trade Contractor Agreement—Exhibit "0"
II. The following referenced documents further describe the changes outlined in Paragraph I,and are
to be considered a part of this Change Order:
RFP No.: CCD No.: Other: SI-055
4 �
List of Attachments: jj,��
The changes result in the following adjustment of the Contract Price and Contract Time:-
Contract Sum prior to this Change Order $576.970
Contract Sum will be increased/decreased by this Change Order $ -808
New Contract Sum including this Change Order $576.162
Contract Time Prior to this Change Order • No Change Days No Change Completion Date
Net increased/decreased resulting from this Change Order 0 Days
Current Contract Time including this Change Order No Change Days No Changq Completion Date
The changes above in the Contract Price and Time include all direct, indirect,delay, acceleration, loss of
efficiency and impact costs and time impacts incurred or encountered by Contractor resulting from the
performance of the change work. Contractor acknowledges that this Change Order constitutes
compensation in full for any delays, acceleration, or loss of efficiency encountered by Contractor in the
performance of the Work through the date of this Change Order.
The Above Changes Are The Above Changes Are The Above Changes Are
Recommended: ARCHITECT Acce ted: ' TRACTOR Approved: OWNER
By. By: By: —
Name: Name:/ 11)1 0c C- Name:
Date: Date: a//i 9 Date:_ _
2
0 /,, Gaylor - CCO #8
Approved and Adopted this day of Pam ,20/r .
CITY OF CARMEL, INDIANA
By and through its Board of Public Works and Safety
BY:
James Brainard,Presiding Officer
V Date: 3 a2 O - /7
d
Mary Burke gembAr
Date. -' -l�
Lori S. Watson ember
Date: ,1/cDv/
ATTEST/
p
(/
Christine S. Pauley,Clerk-Tr9aa,
Date: .Jta0/( 7